WEBVTT

00:00.000 --> 00:08.240
Item 13 review 26-1 and 26-2 utility extension projects to provide sewer and water service

00:08.240 --> 00:11.560
to Canellsville in the town of Port Washington.

00:11.560 --> 00:12.560
Roger.

00:12.560 --> 00:20.480
All right, well, I'll turn this over to Aaron from Kapoor, but essentially he's going to

00:20.480 --> 00:28.200
give us an overview of our next sewer and water project that we have coming in and sort

00:28.200 --> 00:33.480
of our impacts that's going to create with the area.

00:33.480 --> 00:36.320
Good evening, everybody.

00:36.320 --> 00:44.560
We'll bring this up there.

00:44.560 --> 00:52.320
Thanks, Roger.

00:52.320 --> 00:54.320
Again, I'm Aaron Groh with Kapoor and Associates.

00:54.320 --> 00:58.840
We've been here a few times talking in front of the group here tonight, so thanks for

00:58.840 --> 01:00.560
having me.

01:00.560 --> 01:07.680
So right now we are complete with our design plans for the next phase to extend utilities

01:07.680 --> 01:14.680
to the north for Canellsville and also to serve the vantage site.

01:14.680 --> 01:19.600
Those two projects are 26-1 and 26-2.

01:19.600 --> 01:28.360
Two of the key parts of this are that we still are in discussions with PSC for approval.

01:28.360 --> 01:34.560
Water main PSC governs water main and specifically if there is water main that is at least three

01:34.560 --> 01:39.440
miles of length or longer, which this project has.

01:39.440 --> 01:44.680
So we are still in the process of we've had a couple of meetings with PSC.

01:44.680 --> 01:49.960
We've had several clarifications, questions and answers going back and forth with them.

01:49.960 --> 01:55.360
And we have not gotten all the answers that we need to verify that we can move forward

01:55.360 --> 01:59.840
with this project and submit to PSC accordingly.

01:59.840 --> 02:08.560
So that is one item that is going to drive the schedule for these projects.

02:08.560 --> 02:17.240
So that being said, this is a very similar presentation to what I provided before a month

02:17.240 --> 02:18.400
or two ago.

02:18.400 --> 02:23.480
So this first project is 26-1, there is 10,000 feet of water main and 5,000 feet of sanitary

02:23.480 --> 02:24.480
sewer.

02:24.480 --> 02:31.120
It's a long, highland drive, main branch road, and then on Conantrunk Highway KW up to where

02:31.120 --> 02:35.480
the boat storage facility is.

02:35.480 --> 02:39.960
Also will provide sanitary and water laterals to Canalesville per the agreement between

02:39.960 --> 02:43.000
the city and the town.

02:43.000 --> 02:49.120
And we are estimating at just under $8 million for the construction costs and you add 20%

02:49.120 --> 02:52.800
engineering contingencies in there, it brings it up to about 9.4.

02:52.800 --> 03:00.200
Our schedule still is hoping to shoot for late June or early July with construction considering

03:00.200 --> 03:04.520
in late July or early August.

03:04.520 --> 03:10.520
As I just mentioned before with these projects, PSC permitting is still an item that is driving

03:10.520 --> 03:17.400
the schedule and until we can identify the permit process with PSC, we are in a holding

03:17.400 --> 03:21.240
pattern until we get that approval.

03:21.240 --> 03:27.520
Travel control detours routes is another item as far as how we broke this project into

03:27.520 --> 03:29.000
different phases.

03:29.000 --> 03:39.960
And then we also want to identify attractive sized projects to bring a lot of bidders to

03:39.960 --> 03:44.360
these two jobs, 26.1 and 26.2.

03:44.360 --> 03:48.320
We don't want to put out such a large project that you only have two or three bidders.

03:48.320 --> 03:53.800
We want to have normal size contracts that we think we can attract 10 or 15 different

03:53.800 --> 03:57.720
contractors that can put out really competitive prices.

03:57.720 --> 04:00.920
So 26.2, very similar.

04:00.920 --> 04:03.240
So this is 11,000 feet of water main.

04:03.240 --> 04:09.520
It's only water main and it's on KW Lake Drive from the storage facility north to Lake

04:09.520 --> 04:17.000
Drive and then east to the main entrance to the vantage project.

04:17.000 --> 04:26.040
Also add water main services along KW and to other other parcels that are within the town.

04:26.040 --> 04:29.200
This will provide secondary fee to redundancy.

04:29.200 --> 04:34.960
So what Roger was just speaking about before redundancy is a key component to engineering.

04:34.960 --> 04:38.840
And this is one of the main reasons why we want to provide the water to the north side

04:38.840 --> 04:44.440
of the project site for redundancy reasons.

04:44.440 --> 04:48.320
This estimated cost is $5 billion for construction.

04:48.320 --> 04:55.000
But if you add engineering contingencies, about 20% brings us up to just over $6 million.

04:55.000 --> 05:02.120
This schedule similar June or early July to bid out and advertise with construction.

05:02.120 --> 05:10.640
This section is just water main and this is completely driven by the schedule of PSC.

05:10.640 --> 05:15.440
So instead of maybe starting this in July or August, we don't expect this project to

05:15.440 --> 05:19.800
start until at least October.

05:19.800 --> 05:22.560
Water main we would expect to be installed by directional drilling.

05:22.560 --> 05:26.800
The PSC permits as I mentioned before.

05:26.800 --> 05:30.800
The reason why we want to add directional drilling as a construction method is because

05:30.800 --> 05:36.800
it's quicker and it will also reduce the impacts to traffic in the businesses and the properties

05:36.800 --> 05:38.720
that are along KW.

05:38.720 --> 05:44.720
It's smaller work zones and just be easier for traffic to get around while they're working

05:44.720 --> 05:49.320
within KW.

05:49.320 --> 05:59.280
So this is a layout of proposed detours and work zones in the first phase of 26-1.

05:59.280 --> 06:05.880
So this is when we start up, we expect to start up in the intersection of H and Minker

06:05.880 --> 06:06.880
Anch Road.

06:06.880 --> 06:14.200
We'll have to shift traffic onto counter-chunk highway H and just southbound lanes only.

06:14.200 --> 06:15.800
So only in one direction.

06:15.800 --> 06:22.200
A detour will also go on to counter-chunk B to H and also on A to LL.

06:22.200 --> 06:25.720
We've met with the county city staff and Kapoor.

06:25.720 --> 06:29.520
We met with the county to make sure that they were in agreement with these routes and these

06:29.520 --> 06:33.440
routes they concurred with us to do this.

06:33.440 --> 06:39.160
One of the things that we discussed as well, could we maybe have a detour route on B up

06:39.160 --> 06:45.600
to A on the left side instead of having the yellow route that we show which is on

06:45.600 --> 06:48.640
LL and counter-chunk highway A.

06:48.640 --> 06:54.000
We have to have the detour on LL and A for numerous phases and therefore we felt just

06:54.000 --> 06:59.160
from a consistency standpoint for those that are driving out here, if we change the detours

06:59.160 --> 07:02.720
back and forth and back and forth, it's going to get confusing.

07:02.720 --> 07:06.560
So even though maybe it'll be a little bit longer detour route, we just feel it's better

07:06.560 --> 07:14.720
for those that live in the area so it's a consistent detour route.

07:14.720 --> 07:19.480
The roads that are under construction will remain open to local traffic only, so that's

07:19.480 --> 07:20.480
key.

07:20.480 --> 07:27.120
So we still can get on the construction routes when we're working on Highland or Mink Ranch

07:27.120 --> 07:29.600
or KW.

07:29.600 --> 07:35.400
And then on this first little section here on Mink Ranch and I-43 crossing, we'll also

07:35.400 --> 07:44.520
be working on extending our concrete and asphalt pavement that's going to be coordinated with

07:44.520 --> 07:45.520
the next phase.

07:45.520 --> 07:49.720
You can go to the next sheet, please, thank you.

07:49.720 --> 07:56.760
So this is on Highland Drive, so we will be connecting to where we ended the current construction

07:56.760 --> 08:02.360
project that just finished, which is just on Highland Drive, just on the north side

08:02.360 --> 08:05.320
of the bridge on Highland Lane.

08:05.320 --> 08:11.320
So we'll connect to that point and then extend to Kinda Trunk Highway H and the intersection

08:11.320 --> 08:14.320
of KW.

08:14.320 --> 08:22.040
We'll stop just short of KW and H to allow that section of road to remain open to traffic.

08:22.040 --> 08:28.360
We also want to make sure with the phasing of this that we are cognizant of the garbage

08:28.360 --> 08:34.960
drop-off for the town and then also for the local restaurant that's right at this intersection.

08:34.960 --> 08:40.600
So that's one of the reasons why we wanted to stay short of KW and H to be able to allow

08:40.600 --> 08:45.000
traffic to get in and out of those areas during construction.

08:45.000 --> 08:51.160
And then this detour would be route through County Trunk Highway LL and A.

08:51.160 --> 08:55.400
Next phase, so this is the third and final phase for 26-1.

08:55.400 --> 09:02.520
So this is extending up KW and also a little bit of an extension on County Trunk Highway

09:02.520 --> 09:09.240
H. So we're completing everything else that's within that, within the project scope, extending

09:09.240 --> 09:12.160
up to the boat storage facility.

09:12.160 --> 09:18.840
And then we also will extend several hundred feet up County Trunk Highway H this season.

09:18.840 --> 09:24.040
So then the following season, if you remember our five-year outlook, County Trunk Highway

09:24.040 --> 09:30.920
H, H is anticipated to be constructed in 2028 and we want to be completely out of that busy

09:30.920 --> 09:35.920
intersection with County Trunk H and County Trunk KW.

09:35.920 --> 09:38.400
We don't want to be in that intersection two years in a row.

09:38.400 --> 09:44.720
So we plan extending about two or three hundred feet north into H, get outside of the concrete

09:44.720 --> 09:49.600
pavement, the concrete pavement where that ends is where we end our project.

09:49.600 --> 09:54.320
The northbound lanes of County Trunk Highway H would be closed during this process.

09:54.320 --> 10:00.560
And so anybody that's coming from the city proper, running up, will be asked to detour

10:00.560 --> 10:07.360
on County Trunk Highway LL to A. Again, the roads under construction remain open to local

10:07.360 --> 10:12.720
traffic and then we also want to make sure that we're cognizant of the restaurant that's

10:12.720 --> 10:18.560
on the intersection for this third phase of 26-1.

10:18.560 --> 10:21.920
Lastly, it's 26-2.

10:21.920 --> 10:27.880
So this is just the water main only in County Trunk Highway KW and on Lake Drive.

10:27.880 --> 10:34.320
The detour is on LL and A to the right and the yellow that you see.

10:34.320 --> 10:41.600
As I noted before, we expect to have this directionally drilled and then wherever there's hydrants,

10:41.600 --> 10:45.640
which is about every 600 feet, there'll be an open cut within the road.

10:45.640 --> 10:50.920
So we expect to have the majority of the road to remain as is.

10:50.920 --> 10:55.520
As they install the water main, they'll cut open a location for where the hydrant is and

10:55.520 --> 10:56.960
then continue on.

10:56.960 --> 11:03.040
So we're trying to make sure that we minimize the amount of impacts to the residents and

11:03.040 --> 11:07.640
the business owners along KW.

11:07.640 --> 11:16.360
We're also specifying that when one project is going on 26-1, we can't be working in

11:16.360 --> 11:18.440
KW in 26-2.

11:18.440 --> 11:23.680
So our specifications are written in such a way that one job needs to finish before the

11:23.680 --> 11:24.680
other one starts.

11:24.680 --> 11:28.400
So we don't have two contractors working on KW at the same time.

11:28.400 --> 11:32.840
Again, we're trying to be as cognizant as we can to the business owners and the residents

11:32.840 --> 11:33.840
along KW.

11:34.840 --> 11:36.080
Just a question.

11:36.080 --> 11:39.640
Wouldn't it be preferable, though, to have them both working simultaneously so we can

11:39.640 --> 11:44.040
have a shorter closure on KW?

11:44.040 --> 11:52.040
Well, part of that also is driven by the PSC approval, which we expect that we won't

11:52.040 --> 11:58.480
get on this leg on 26-2, and therefore, this section likely won't start up until October.

11:58.480 --> 12:02.280
So part of that has to do with that plays a role into this, too.

12:02.360 --> 12:07.960
Yeah, I hate to see us close it, open it for a week, and then close it again.

12:07.960 --> 12:08.960
Understood.

12:08.960 --> 12:09.960
Yes.

12:09.960 --> 12:12.800
We'll be very cognizant of working with both continents, assuming that we have two different

12:12.800 --> 12:15.240
contractors that win these awards.

12:15.240 --> 12:20.120
We'll work with them to try and make sure that we minimize those changes.

12:20.120 --> 12:26.800
There's some things that you can't avoid, but point taken.

12:26.840 --> 12:35.280
Also, we identified that during warm weather, we'll use asphalt patching, and if it gets

12:35.280 --> 12:40.200
to cold weather, we're going to require them to use concrete patching.

12:40.200 --> 12:47.840
One other thing is that we're specifying to minimize potential risk or overruns to the

12:47.840 --> 12:48.840
city.

12:48.840 --> 12:52.320
We're anticipating that all this work would occur.

12:52.800 --> 13:02.640
26-1 would occur yet all in the 26, year of 26, 26-2 may trickle into the year 2027.

13:02.640 --> 13:09.160
If that's the case, what our specifications are saying is that contractor, we don't expect

13:09.160 --> 13:15.640
for them to work from the timeframe of December 15th to March 15th.

13:15.640 --> 13:19.880
And if they so choose, they can do so at their own risk and at no additional cost to

13:19.880 --> 13:20.880
the city.

13:20.880 --> 13:24.720
Therefore, no change orders for cold weather applications or things of that nature.

13:24.720 --> 13:30.880
So we expect them no work from December to March, however, we would allow them if they

13:30.880 --> 13:36.520
wanted to do it, again, at no additional cost to the city.

13:36.520 --> 13:38.600
And I think that is the final sheet.

13:38.600 --> 13:39.600
Any questions?

13:39.600 --> 13:47.480
Yeah, on the detour running on LL as opposed to B. Do we have any concern about, especially

13:47.480 --> 13:51.880
when Lake and LL will be closed for that project, that all of the construction traffic

13:51.880 --> 13:56.680
is going to also be accessing the site from East off of LL?

13:56.680 --> 13:57.680
Yes.

13:57.680 --> 14:03.640
Would it in that case be better to have that detour on B so that it is not sharing the

14:03.640 --> 14:06.200
roads with all the construction traffic?

14:06.200 --> 14:09.920
Other than, of course, when you get up to A, you're going to have an intersection with

14:09.920 --> 14:10.920
construction traffic.

14:10.920 --> 14:13.520
There are multiple reasons why we chose that.

14:13.520 --> 14:19.840
We also were looking at, you know, there's a tight angle on B and H as well.

14:19.840 --> 14:25.800
And if you if you ran a ran the detour with some of these tight angles, we also a consideration

14:25.800 --> 14:33.600
of when the county part of this work is county work where the detours need to be done through

14:33.600 --> 14:34.840
county roads, right?

14:34.840 --> 14:39.640
So you will a road might be a good application to have a detour, but we really can't if we

14:39.640 --> 14:43.240
have some of the county projects going on where the county is going to be paving on

14:43.240 --> 14:44.240
some of this.

14:44.240 --> 14:47.040
So those all played into it.

14:47.040 --> 14:55.200
We also coordinated these with the vantage design team, specifically Graf and they're

14:55.200 --> 15:00.320
the ones that I looked at improving all the intersections and coordinating the traffic

15:00.320 --> 15:04.920
signals, the temporary traffic signals that are planned for the intersection with I-43.

15:04.920 --> 15:10.040
And we bounced all these off of them and made sure that it worked with their plans.

15:10.040 --> 15:13.360
And there were they felt that this would work as well.

15:13.360 --> 15:18.160
So we don't need to take any extraordinary measures at lake in L.L. just by having all

15:18.160 --> 15:21.280
the traffic piling up there during construction.

15:21.280 --> 15:25.960
Other than right now where we have sheriff's deputies out directing traffic twice a day.

15:25.960 --> 15:33.640
Well part of the so, yes, so the there will be traffic alleviated because right now Highland

15:33.640 --> 15:40.320
Drive does not have any access to construction traffic as we're completing that work.

15:40.320 --> 15:43.280
We're about a week to two weeks from that all being complete.

15:43.280 --> 15:48.600
And at that point in time, the vantage team will open the southern entrance off of Highland

15:48.600 --> 15:50.400
Drive.

15:50.400 --> 15:55.160
So about half the trucks and equipment that are coming now to lake.

15:55.160 --> 15:58.600
Half of them now will be coming up the south side on Highland Drive.

15:58.600 --> 16:04.840
So we'll alleviate a lot of the pressure that you have at both K.W. and L.L. at Lake

16:04.840 --> 16:05.840
Drive.

16:05.840 --> 16:09.760
So that's probably going to be the biggest impact of being able to open up the access

16:09.760 --> 16:11.720
point off of Highland Drive.

16:11.720 --> 16:12.720
All right.

16:12.720 --> 16:13.720
Any other questions?

16:13.720 --> 16:14.720
Yes.

16:14.720 --> 16:17.360
Have you spoken to Johnson Bus Company?

16:17.360 --> 16:20.520
Are we concerned about school kids and?

16:20.520 --> 16:21.520
Yes.

16:21.520 --> 16:26.160
So we've spoken with them and we also have it written on to our specifications that

16:26.160 --> 16:33.280
we will be coordinating with them and we will discuss the contractor will be required

16:33.280 --> 16:38.520
to meet with Johnson Bus once we have a preliminary schedule put together and we can talk with

16:38.520 --> 16:41.960
them as far as what the best routes are is that they need to go north or if they need

16:41.960 --> 16:43.120
to go south.

16:43.120 --> 16:47.480
So yes, that is written into our contract specifically that the contractor has to meet

16:47.480 --> 16:55.360
with Johnson Bus to make sure that they are able to proceed business-wise as they should.

16:55.360 --> 16:56.360
Yes.

16:56.360 --> 16:58.840
So we do want to hear stories about how they are in our late school.

16:58.840 --> 16:59.840
Yes.

16:59.840 --> 17:00.840
We understood.

17:00.840 --> 17:01.840
Thank you.

17:01.840 --> 17:09.720
Who is primarily responsible for sharing us out to the community?

17:09.720 --> 17:12.120
Because you know, most people aren't going to watch public works meetings.

17:12.120 --> 17:16.360
So if it's because like there's this construction updates website on the Vantage D.C.

17:16.360 --> 17:20.640
Lighthouse campus, do you guys have anything to do with that or is that Vantage themselves

17:21.640 --> 17:25.360
because the last update on here was from April.

17:25.360 --> 17:27.520
So Vantage has their own updates.

17:27.520 --> 17:30.800
I don't know Roger if you have any more to add to that.

17:30.800 --> 17:32.800
They're doing their own updates.

17:32.800 --> 17:34.880
Vantage has their own updates.

17:34.880 --> 17:43.400
We are planning on doing a PIM meeting with the town public information meeting specifically

17:43.400 --> 17:52.840
Johnson Bus, Pierce Restaurant, Great Lakes Bolt, Allen Edmond's got an operation in

17:52.840 --> 17:53.840
there.

17:53.840 --> 17:59.920
So we could kind of have the same meeting discussion that we're having here.

17:59.920 --> 18:00.920
Yes.

18:00.920 --> 18:01.920
And I do apologize.

18:01.920 --> 18:05.080
That was one of the key points I wanted to mention today and I forgot.

18:05.080 --> 18:10.760
We are planning on scheduling a PIM prior to any sort of road work construction.

18:11.760 --> 18:15.920
I just think if they could keep this construction updates website a little bit more updated

18:15.920 --> 18:19.000
with so people know what to expect ahead of time would be.

18:19.000 --> 18:20.280
So we can share.

18:20.280 --> 18:24.920
I can certainly share this information with Vantage and ask for them to add it to their

18:24.920 --> 18:25.920
site.

18:25.920 --> 18:30.280
That would be I would assume that they would be fine with doing that.

18:30.280 --> 18:31.280
Thank you.

18:31.280 --> 18:39.280
This is probably more of a question for Robin Roger, but since the project is going to

18:39.280 --> 18:45.520
be putting in curb stops for future water connections, are we doing any marketing at

18:45.520 --> 18:50.800
all to those property owners that they are going to be aware that they can connect to

18:50.800 --> 18:53.040
city water?

18:53.040 --> 18:57.240
Because you know, we probably don't want it happening simultaneously with the project,

18:57.240 --> 18:59.880
but the curb stop will be there be easy for them to continue.

18:59.880 --> 19:05.160
Just want to make sure that they're all aware so that they can start making those connections

19:05.160 --> 19:13.920
and we can produce a little bit of water revenue off of those areas.

19:13.920 --> 19:18.280
Well, Roger can add we haven't done it, but I know the town chairman has gone door to

19:18.280 --> 19:20.920
court to inform everyone.

19:20.920 --> 19:22.480
All right.

19:22.480 --> 19:23.480
Good.

19:23.480 --> 19:25.560
All right.

19:25.560 --> 19:27.600
Any other comments or questions?

19:27.600 --> 19:29.200
All right.

19:29.200 --> 19:30.200
Thank you.

19:30.200 --> 19:30.560
Thank you.

