1
00:00:00,000 --> 00:00:08,240
Item 13 review 26-1 and 26-2 utility extension projects to provide sewer and water service

2
00:00:08,240 --> 00:00:11,560
to Canellsville in the town of Port Washington.

3
00:00:11,560 --> 00:00:12,560
Roger.

4
00:00:12,560 --> 00:00:20,480
All right, well, I'll turn this over to Aaron from Kapoor, but essentially he's going to

5
00:00:20,480 --> 00:00:28,200
give us an overview of our next sewer and water project that we have coming in and sort

6
00:00:28,200 --> 00:00:33,480
of our impacts that's going to create with the area.

7
00:00:33,480 --> 00:00:36,320
Good evening, everybody.

8
00:00:36,320 --> 00:00:44,560
We'll bring this up there.

9
00:00:44,560 --> 00:00:52,320
Thanks, Roger.

10
00:00:52,320 --> 00:00:54,320
Again, I'm Aaron Groh with Kapoor and Associates.

11
00:00:54,320 --> 00:00:58,840
We've been here a few times talking in front of the group here tonight, so thanks for

12
00:00:58,840 --> 00:01:00,560
having me.

13
00:01:00,560 --> 00:01:07,680
So right now we are complete with our design plans for the next phase to extend utilities

14
00:01:07,680 --> 00:01:14,680
to the north for Canellsville and also to serve the vantage site.

15
00:01:14,680 --> 00:01:19,600
Those two projects are 26-1 and 26-2.

16
00:01:19,600 --> 00:01:28,360
Two of the key parts of this are that we still are in discussions with PSC for approval.

17
00:01:28,360 --> 00:01:34,560
Water main PSC governs water main and specifically if there is water main that is at least three

18
00:01:34,560 --> 00:01:39,440
miles of length or longer, which this project has.

19
00:01:39,440 --> 00:01:44,680
So we are still in the process of we've had a couple of meetings with PSC.

20
00:01:44,680 --> 00:01:49,960
We've had several clarifications, questions and answers going back and forth with them.

21
00:01:49,960 --> 00:01:55,360
And we have not gotten all the answers that we need to verify that we can move forward

22
00:01:55,360 --> 00:01:59,840
with this project and submit to PSC accordingly.

23
00:01:59,840 --> 00:02:08,560
So that is one item that is going to drive the schedule for these projects.

24
00:02:08,560 --> 00:02:17,240
So that being said, this is a very similar presentation to what I provided before a month

25
00:02:17,240 --> 00:02:18,400
or two ago.

26
00:02:18,400 --> 00:02:23,480
So this first project is 26-1, there is 10,000 feet of water main and 5,000 feet of sanitary

27
00:02:23,480 --> 00:02:24,480
sewer.

28
00:02:24,480 --> 00:02:31,120
It's a long, highland drive, main branch road, and then on Conantrunk Highway KW up to where

29
00:02:31,120 --> 00:02:35,480
the boat storage facility is.

30
00:02:35,480 --> 00:02:39,960
Also will provide sanitary and water laterals to Canalesville per the agreement between

31
00:02:39,960 --> 00:02:43,000
the city and the town.

32
00:02:43,000 --> 00:02:49,120
And we are estimating at just under $8 million for the construction costs and you add 20%

33
00:02:49,120 --> 00:02:52,800
engineering contingencies in there, it brings it up to about 9.4.

34
00:02:52,800 --> 00:03:00,200
Our schedule still is hoping to shoot for late June or early July with construction considering

35
00:03:00,200 --> 00:03:04,520
in late July or early August.

36
00:03:04,520 --> 00:03:10,520
As I just mentioned before with these projects, PSC permitting is still an item that is driving

37
00:03:10,520 --> 00:03:17,400
the schedule and until we can identify the permit process with PSC, we are in a holding

38
00:03:17,400 --> 00:03:21,240
pattern until we get that approval.

39
00:03:21,240 --> 00:03:27,520
Travel control detours routes is another item as far as how we broke this project into

40
00:03:27,520 --> 00:03:29,000
different phases.

41
00:03:29,000 --> 00:03:39,960
And then we also want to identify attractive sized projects to bring a lot of bidders to

42
00:03:39,960 --> 00:03:44,360
these two jobs, 26.1 and 26.2.

43
00:03:44,360 --> 00:03:48,320
We don't want to put out such a large project that you only have two or three bidders.

44
00:03:48,320 --> 00:03:53,800
We want to have normal size contracts that we think we can attract 10 or 15 different

45
00:03:53,800 --> 00:03:57,720
contractors that can put out really competitive prices.

46
00:03:57,720 --> 00:04:00,920
So 26.2, very similar.

47
00:04:00,920 --> 00:04:03,240
So this is 11,000 feet of water main.

48
00:04:03,240 --> 00:04:09,520
It's only water main and it's on KW Lake Drive from the storage facility north to Lake

49
00:04:09,520 --> 00:04:17,000
Drive and then east to the main entrance to the vantage project.

50
00:04:17,000 --> 00:04:26,040
Also add water main services along KW and to other other parcels that are within the town.

51
00:04:26,040 --> 00:04:29,200
This will provide secondary fee to redundancy.

52
00:04:29,200 --> 00:04:34,960
So what Roger was just speaking about before redundancy is a key component to engineering.

53
00:04:34,960 --> 00:04:38,840
And this is one of the main reasons why we want to provide the water to the north side

54
00:04:38,840 --> 00:04:44,440
of the project site for redundancy reasons.

55
00:04:44,440 --> 00:04:48,320
This estimated cost is $5 billion for construction.

56
00:04:48,320 --> 00:04:55,000
But if you add engineering contingencies, about 20% brings us up to just over $6 million.

57
00:04:55,000 --> 00:05:02,120
This schedule similar June or early July to bid out and advertise with construction.

58
00:05:02,120 --> 00:05:10,640
This section is just water main and this is completely driven by the schedule of PSC.

59
00:05:10,640 --> 00:05:15,440
So instead of maybe starting this in July or August, we don't expect this project to

60
00:05:15,440 --> 00:05:19,800
start until at least October.

61
00:05:19,800 --> 00:05:22,560
Water main we would expect to be installed by directional drilling.

62
00:05:22,560 --> 00:05:26,800
The PSC permits as I mentioned before.

63
00:05:26,800 --> 00:05:30,800
The reason why we want to add directional drilling as a construction method is because

64
00:05:30,800 --> 00:05:36,800
it's quicker and it will also reduce the impacts to traffic in the businesses and the properties

65
00:05:36,800 --> 00:05:38,720
that are along KW.

66
00:05:38,720 --> 00:05:44,720
It's smaller work zones and just be easier for traffic to get around while they're working

67
00:05:44,720 --> 00:05:49,320
within KW.

68
00:05:49,320 --> 00:05:59,280
So this is a layout of proposed detours and work zones in the first phase of 26-1.

69
00:05:59,280 --> 00:06:05,880
So this is when we start up, we expect to start up in the intersection of H and Minker

70
00:06:05,880 --> 00:06:06,880
Anch Road.

71
00:06:06,880 --> 00:06:14,200
We'll have to shift traffic onto counter-chunk highway H and just southbound lanes only.

72
00:06:14,200 --> 00:06:15,800
So only in one direction.

73
00:06:15,800 --> 00:06:22,200
A detour will also go on to counter-chunk B to H and also on A to LL.

74
00:06:22,200 --> 00:06:25,720
We've met with the county city staff and Kapoor.

75
00:06:25,720 --> 00:06:29,520
We met with the county to make sure that they were in agreement with these routes and these

76
00:06:29,520 --> 00:06:33,440
routes they concurred with us to do this.

77
00:06:33,440 --> 00:06:39,160
One of the things that we discussed as well, could we maybe have a detour route on B up

78
00:06:39,160 --> 00:06:45,600
to A on the left side instead of having the yellow route that we show which is on

79
00:06:45,600 --> 00:06:48,640
LL and counter-chunk highway A.

80
00:06:48,640 --> 00:06:54,000
We have to have the detour on LL and A for numerous phases and therefore we felt just

81
00:06:54,000 --> 00:06:59,160
from a consistency standpoint for those that are driving out here, if we change the detours

82
00:06:59,160 --> 00:07:02,720
back and forth and back and forth, it's going to get confusing.

83
00:07:02,720 --> 00:07:06,560
So even though maybe it'll be a little bit longer detour route, we just feel it's better

84
00:07:06,560 --> 00:07:14,720
for those that live in the area so it's a consistent detour route.

85
00:07:14,720 --> 00:07:19,480
The roads that are under construction will remain open to local traffic only, so that's

86
00:07:19,480 --> 00:07:20,480
key.

87
00:07:20,480 --> 00:07:27,120
So we still can get on the construction routes when we're working on Highland or Mink Ranch

88
00:07:27,120 --> 00:07:29,600
or KW.

89
00:07:29,600 --> 00:07:35,400
And then on this first little section here on Mink Ranch and I-43 crossing, we'll also

90
00:07:35,400 --> 00:07:44,520
be working on extending our concrete and asphalt pavement that's going to be coordinated with

91
00:07:44,520 --> 00:07:45,520
the next phase.

92
00:07:45,520 --> 00:07:49,720
You can go to the next sheet, please, thank you.

93
00:07:49,720 --> 00:07:56,760
So this is on Highland Drive, so we will be connecting to where we ended the current construction

94
00:07:56,760 --> 00:08:02,360
project that just finished, which is just on Highland Drive, just on the north side

95
00:08:02,360 --> 00:08:05,320
of the bridge on Highland Lane.

96
00:08:05,320 --> 00:08:11,320
So we'll connect to that point and then extend to Kinda Trunk Highway H and the intersection

97
00:08:11,320 --> 00:08:14,320
of KW.

98
00:08:14,320 --> 00:08:22,040
We'll stop just short of KW and H to allow that section of road to remain open to traffic.

99
00:08:22,040 --> 00:08:28,360
We also want to make sure with the phasing of this that we are cognizant of the garbage

100
00:08:28,360 --> 00:08:34,960
drop-off for the town and then also for the local restaurant that's right at this intersection.

101
00:08:34,960 --> 00:08:40,600
So that's one of the reasons why we wanted to stay short of KW and H to be able to allow

102
00:08:40,600 --> 00:08:45,000
traffic to get in and out of those areas during construction.

103
00:08:45,000 --> 00:08:51,160
And then this detour would be route through County Trunk Highway LL and A.

104
00:08:51,160 --> 00:08:55,400
Next phase, so this is the third and final phase for 26-1.

105
00:08:55,400 --> 00:09:02,520
So this is extending up KW and also a little bit of an extension on County Trunk Highway

106
00:09:02,520 --> 00:09:09,240
H. So we're completing everything else that's within that, within the project scope, extending

107
00:09:09,240 --> 00:09:12,160
up to the boat storage facility.

108
00:09:12,160 --> 00:09:18,840
And then we also will extend several hundred feet up County Trunk Highway H this season.

109
00:09:18,840 --> 00:09:24,040
So then the following season, if you remember our five-year outlook, County Trunk Highway

110
00:09:24,040 --> 00:09:30,920
H, H is anticipated to be constructed in 2028 and we want to be completely out of that busy

111
00:09:30,920 --> 00:09:35,920
intersection with County Trunk H and County Trunk KW.

112
00:09:35,920 --> 00:09:38,400
We don't want to be in that intersection two years in a row.

113
00:09:38,400 --> 00:09:44,720
So we plan extending about two or three hundred feet north into H, get outside of the concrete

114
00:09:44,720 --> 00:09:49,600
pavement, the concrete pavement where that ends is where we end our project.

115
00:09:49,600 --> 00:09:54,320
The northbound lanes of County Trunk Highway H would be closed during this process.

116
00:09:54,320 --> 00:10:00,560
And so anybody that's coming from the city proper, running up, will be asked to detour

117
00:10:00,560 --> 00:10:07,360
on County Trunk Highway LL to A. Again, the roads under construction remain open to local

118
00:10:07,360 --> 00:10:12,720
traffic and then we also want to make sure that we're cognizant of the restaurant that's

119
00:10:12,720 --> 00:10:18,560
on the intersection for this third phase of 26-1.

120
00:10:18,560 --> 00:10:21,920
Lastly, it's 26-2.

121
00:10:21,920 --> 00:10:27,880
So this is just the water main only in County Trunk Highway KW and on Lake Drive.

122
00:10:27,880 --> 00:10:34,320
The detour is on LL and A to the right and the yellow that you see.

123
00:10:34,320 --> 00:10:41,600
As I noted before, we expect to have this directionally drilled and then wherever there's hydrants,

124
00:10:41,600 --> 00:10:45,640
which is about every 600 feet, there'll be an open cut within the road.

125
00:10:45,640 --> 00:10:50,920
So we expect to have the majority of the road to remain as is.

126
00:10:50,920 --> 00:10:55,520
As they install the water main, they'll cut open a location for where the hydrant is and

127
00:10:55,520 --> 00:10:56,960
then continue on.

128
00:10:56,960 --> 00:11:03,040
So we're trying to make sure that we minimize the amount of impacts to the residents and

129
00:11:03,040 --> 00:11:07,640
the business owners along KW.

130
00:11:07,640 --> 00:11:16,360
We're also specifying that when one project is going on 26-1, we can't be working in

131
00:11:16,360 --> 00:11:18,440
KW in 26-2.

132
00:11:18,440 --> 00:11:23,680
So our specifications are written in such a way that one job needs to finish before the

133
00:11:23,680 --> 00:11:24,680
other one starts.

134
00:11:24,680 --> 00:11:28,400
So we don't have two contractors working on KW at the same time.

135
00:11:28,400 --> 00:11:32,840
Again, we're trying to be as cognizant as we can to the business owners and the residents

136
00:11:32,840 --> 00:11:33,840
along KW.

137
00:11:34,840 --> 00:11:36,080
Just a question.

138
00:11:36,080 --> 00:11:39,640
Wouldn't it be preferable, though, to have them both working simultaneously so we can

139
00:11:39,640 --> 00:11:44,040
have a shorter closure on KW?

140
00:11:44,040 --> 00:11:52,040
Well, part of that also is driven by the PSC approval, which we expect that we won't

141
00:11:52,040 --> 00:11:58,480
get on this leg on 26-2, and therefore, this section likely won't start up until October.

142
00:11:58,480 --> 00:12:02,280
So part of that has to do with that plays a role into this, too.

143
00:12:02,360 --> 00:12:07,960
Yeah, I hate to see us close it, open it for a week, and then close it again.

144
00:12:07,960 --> 00:12:08,960
Understood.

145
00:12:08,960 --> 00:12:09,960
Yes.

146
00:12:09,960 --> 00:12:12,800
We'll be very cognizant of working with both continents, assuming that we have two different

147
00:12:12,800 --> 00:12:15,240
contractors that win these awards.

148
00:12:15,240 --> 00:12:20,120
We'll work with them to try and make sure that we minimize those changes.

149
00:12:20,120 --> 00:12:26,800
There's some things that you can't avoid, but point taken.

150
00:12:26,840 --> 00:12:35,280
Also, we identified that during warm weather, we'll use asphalt patching, and if it gets

151
00:12:35,280 --> 00:12:40,200
to cold weather, we're going to require them to use concrete patching.

152
00:12:40,200 --> 00:12:47,840
One other thing is that we're specifying to minimize potential risk or overruns to the

153
00:12:47,840 --> 00:12:48,840
city.

154
00:12:48,840 --> 00:12:52,320
We're anticipating that all this work would occur.

155
00:12:52,800 --> 00:13:02,640
26-1 would occur yet all in the 26, year of 26, 26-2 may trickle into the year 2027.

156
00:13:02,640 --> 00:13:09,160
If that's the case, what our specifications are saying is that contractor, we don't expect

157
00:13:09,160 --> 00:13:15,640
for them to work from the timeframe of December 15th to March 15th.

158
00:13:15,640 --> 00:13:19,880
And if they so choose, they can do so at their own risk and at no additional cost to

159
00:13:19,880 --> 00:13:20,880
the city.

160
00:13:20,880 --> 00:13:24,720
Therefore, no change orders for cold weather applications or things of that nature.

161
00:13:24,720 --> 00:13:30,880
So we expect them no work from December to March, however, we would allow them if they

162
00:13:30,880 --> 00:13:36,520
wanted to do it, again, at no additional cost to the city.

163
00:13:36,520 --> 00:13:38,600
And I think that is the final sheet.

164
00:13:38,600 --> 00:13:39,600
Any questions?

165
00:13:39,600 --> 00:13:47,480
Yeah, on the detour running on LL as opposed to B. Do we have any concern about, especially

166
00:13:47,480 --> 00:13:51,880
when Lake and LL will be closed for that project, that all of the construction traffic

167
00:13:51,880 --> 00:13:56,680
is going to also be accessing the site from East off of LL?

168
00:13:56,680 --> 00:13:57,680
Yes.

169
00:13:57,680 --> 00:14:03,640
Would it in that case be better to have that detour on B so that it is not sharing the

170
00:14:03,640 --> 00:14:06,200
roads with all the construction traffic?

171
00:14:06,200 --> 00:14:09,920
Other than, of course, when you get up to A, you're going to have an intersection with

172
00:14:09,920 --> 00:14:10,920
construction traffic.

173
00:14:10,920 --> 00:14:13,520
There are multiple reasons why we chose that.

174
00:14:13,520 --> 00:14:19,840
We also were looking at, you know, there's a tight angle on B and H as well.

175
00:14:19,840 --> 00:14:25,800
And if you if you ran a ran the detour with some of these tight angles, we also a consideration

176
00:14:25,800 --> 00:14:33,600
of when the county part of this work is county work where the detours need to be done through

177
00:14:33,600 --> 00:14:34,840
county roads, right?

178
00:14:34,840 --> 00:14:39,640
So you will a road might be a good application to have a detour, but we really can't if we

179
00:14:39,640 --> 00:14:43,240
have some of the county projects going on where the county is going to be paving on

180
00:14:43,240 --> 00:14:44,240
some of this.

181
00:14:44,240 --> 00:14:47,040
So those all played into it.

182
00:14:47,040 --> 00:14:55,200
We also coordinated these with the vantage design team, specifically Graf and they're

183
00:14:55,200 --> 00:15:00,320
the ones that I looked at improving all the intersections and coordinating the traffic

184
00:15:00,320 --> 00:15:04,920
signals, the temporary traffic signals that are planned for the intersection with I-43.

185
00:15:04,920 --> 00:15:10,040
And we bounced all these off of them and made sure that it worked with their plans.

186
00:15:10,040 --> 00:15:13,360
And there were they felt that this would work as well.

187
00:15:13,360 --> 00:15:18,160
So we don't need to take any extraordinary measures at lake in L.L. just by having all

188
00:15:18,160 --> 00:15:21,280
the traffic piling up there during construction.

189
00:15:21,280 --> 00:15:25,960
Other than right now where we have sheriff's deputies out directing traffic twice a day.

190
00:15:25,960 --> 00:15:33,640
Well part of the so, yes, so the there will be traffic alleviated because right now Highland

191
00:15:33,640 --> 00:15:40,320
Drive does not have any access to construction traffic as we're completing that work.

192
00:15:40,320 --> 00:15:43,280
We're about a week to two weeks from that all being complete.

193
00:15:43,280 --> 00:15:48,600
And at that point in time, the vantage team will open the southern entrance off of Highland

194
00:15:48,600 --> 00:15:50,400
Drive.

195
00:15:50,400 --> 00:15:55,160
So about half the trucks and equipment that are coming now to lake.

196
00:15:55,160 --> 00:15:58,600
Half of them now will be coming up the south side on Highland Drive.

197
00:15:58,600 --> 00:16:04,840
So we'll alleviate a lot of the pressure that you have at both K.W. and L.L. at Lake

198
00:16:04,840 --> 00:16:05,840
Drive.

199
00:16:05,840 --> 00:16:09,760
So that's probably going to be the biggest impact of being able to open up the access

200
00:16:09,760 --> 00:16:11,720
point off of Highland Drive.

201
00:16:11,720 --> 00:16:12,720
All right.

202
00:16:12,720 --> 00:16:13,720
Any other questions?

203
00:16:13,720 --> 00:16:14,720
Yes.

204
00:16:14,720 --> 00:16:17,360
Have you spoken to Johnson Bus Company?

205
00:16:17,360 --> 00:16:20,520
Are we concerned about school kids and?

206
00:16:20,520 --> 00:16:21,520
Yes.

207
00:16:21,520 --> 00:16:26,160
So we've spoken with them and we also have it written on to our specifications that

208
00:16:26,160 --> 00:16:33,280
we will be coordinating with them and we will discuss the contractor will be required

209
00:16:33,280 --> 00:16:38,520
to meet with Johnson Bus once we have a preliminary schedule put together and we can talk with

210
00:16:38,520 --> 00:16:41,960
them as far as what the best routes are is that they need to go north or if they need

211
00:16:41,960 --> 00:16:43,120
to go south.

212
00:16:43,120 --> 00:16:47,480
So yes, that is written into our contract specifically that the contractor has to meet

213
00:16:47,480 --> 00:16:55,360
with Johnson Bus to make sure that they are able to proceed business-wise as they should.

214
00:16:55,360 --> 00:16:56,360
Yes.

215
00:16:56,360 --> 00:16:58,840
So we do want to hear stories about how they are in our late school.

216
00:16:58,840 --> 00:16:59,840
Yes.

217
00:16:59,840 --> 00:17:00,840
We understood.

218
00:17:00,840 --> 00:17:01,840
Thank you.

219
00:17:01,840 --> 00:17:09,720
Who is primarily responsible for sharing us out to the community?

220
00:17:09,720 --> 00:17:12,120
Because you know, most people aren't going to watch public works meetings.

221
00:17:12,120 --> 00:17:16,360
So if it's because like there's this construction updates website on the Vantage D.C.

222
00:17:16,360 --> 00:17:20,640
Lighthouse campus, do you guys have anything to do with that or is that Vantage themselves

223
00:17:21,640 --> 00:17:25,360
because the last update on here was from April.

224
00:17:25,360 --> 00:17:27,520
So Vantage has their own updates.

225
00:17:27,520 --> 00:17:30,800
I don't know Roger if you have any more to add to that.

226
00:17:30,800 --> 00:17:32,800
They're doing their own updates.

227
00:17:32,800 --> 00:17:34,880
Vantage has their own updates.

228
00:17:34,880 --> 00:17:43,400
We are planning on doing a PIM meeting with the town public information meeting specifically

229
00:17:43,400 --> 00:17:52,840
Johnson Bus, Pierce Restaurant, Great Lakes Bolt, Allen Edmond's got an operation in

230
00:17:52,840 --> 00:17:53,840
there.

231
00:17:53,840 --> 00:17:59,920
So we could kind of have the same meeting discussion that we're having here.

232
00:17:59,920 --> 00:18:00,920
Yes.

233
00:18:00,920 --> 00:18:01,920
And I do apologize.

234
00:18:01,920 --> 00:18:05,080
That was one of the key points I wanted to mention today and I forgot.

235
00:18:05,080 --> 00:18:10,760
We are planning on scheduling a PIM prior to any sort of road work construction.

236
00:18:11,760 --> 00:18:15,920
I just think if they could keep this construction updates website a little bit more updated

237
00:18:15,920 --> 00:18:19,000
with so people know what to expect ahead of time would be.

238
00:18:19,000 --> 00:18:20,280
So we can share.

239
00:18:20,280 --> 00:18:24,920
I can certainly share this information with Vantage and ask for them to add it to their

240
00:18:24,920 --> 00:18:25,920
site.

241
00:18:25,920 --> 00:18:30,280
That would be I would assume that they would be fine with doing that.

242
00:18:30,280 --> 00:18:31,280
Thank you.

243
00:18:31,280 --> 00:18:39,280
This is probably more of a question for Robin Roger, but since the project is going to

244
00:18:39,280 --> 00:18:45,520
be putting in curb stops for future water connections, are we doing any marketing at

245
00:18:45,520 --> 00:18:50,800
all to those property owners that they are going to be aware that they can connect to

246
00:18:50,800 --> 00:18:53,040
city water?

247
00:18:53,040 --> 00:18:57,240
Because you know, we probably don't want it happening simultaneously with the project,

248
00:18:57,240 --> 00:18:59,880
but the curb stop will be there be easy for them to continue.

249
00:18:59,880 --> 00:19:05,160
Just want to make sure that they're all aware so that they can start making those connections

250
00:19:05,160 --> 00:19:13,920
and we can produce a little bit of water revenue off of those areas.

251
00:19:13,920 --> 00:19:18,280
Well, Roger can add we haven't done it, but I know the town chairman has gone door to

252
00:19:18,280 --> 00:19:20,920
court to inform everyone.

253
00:19:20,920 --> 00:19:22,480
All right.

254
00:19:22,480 --> 00:19:23,480
Good.

255
00:19:23,480 --> 00:19:25,560
All right.

256
00:19:25,560 --> 00:19:27,600
Any other comments or questions?

257
00:19:27,600 --> 00:19:29,200
All right.

258
00:19:29,200 --> 00:19:30,200
Thank you.

259
00:19:30,200 --> 00:19:30,560
Thank you.
