00:00.000 --> 00:22.000
Okay, and that takes us into the presentation of tax incremental district number five project planning alright, so thank you for letting me kick this off. I'll be introducing the folks that are going to do most of the presentation, but I just wanted to, there's a an immense amount of interest in this project and and how we're going to be project planning for the city.

00:22.000 --> 00:33.000
And we really wanted to take this opportunity to make sure that the community knows on council knows you know are basically our one to three year immediate plans that relate to TID five.

00:33.000 --> 00:51.000
And we want to make sure that we are communicating often communicating out and letting the community know what we're doing so that we can work alongside them and and then also not work on top of each other because oftentimes it's you don't realize you know we energies is going to be here and here at the same time or you're going to be there so.

00:51.000 --> 01:08.000
We're really working on a full scope. So a lot of work has gone into this presentation that we'll do tonight it was in the packet will post it online. We'll also link to this presentation and we want to make sure people are able to get to this link so we'll link like where you can start in the video so you don't have to sit at

01:08.000 --> 01:14.000
that time and listen to you know the full council meeting if you don't want to do all of that listening.

01:14.000 --> 01:22.000
But we it does take a lot of work to condense a presentation like this down into like 25 minutes.

01:22.000 --> 01:35.000
It's very easy to do a long presentation so I do apply the staff and our consultants for working with us on on that so that we can give a broad scope of what it is so I kind of wanted to be the disclaimer for the for the project.

01:35.000 --> 01:44.000
And you know we're not going to solve all the project problems tonight. We we don't have all the exact numbers that this will everything will cost.

01:44.000 --> 01:53.000
But what we are doing is letting you know what projects are getting done and what are the immediate what are the immediate projects that are going to impact the community.

01:53.000 --> 02:03.000
So it's like the one to three one to three years. We had grave here last going through that DOT plan of what's going to be done right now in the roads the turning.

02:03.000 --> 02:12.000
So we're really trying to just communicate that out so folks know what what tonight isn't it's not an action item you aren't going to vote on anything.

02:12.000 --> 02:17.000
It's informational only and we appreciate the the input that we got.

02:17.000 --> 02:26.000
This was presented at Public Works last week and we did get some feedback which we try to incorporate within our comments since since that time.

02:26.000 --> 02:32.000
So we appreciate the feedback we've had from some of the community some of the community groups and 9th of council.

02:32.000 --> 02:40.000
And this is obviously not a final discussion. So all of these projects will move through the process like as a normal project.

02:40.000 --> 02:47.000
City staff isn't going to be making the decision on you know this is the scope of this project these will come through.

02:47.000 --> 02:55.000
We've identified them and then they'll come to the process through Public Works and then to council like any other normal project would.

02:55.000 --> 02:59.000
So we don't have a blank check unfortunately or fortunately.

03:00.000 --> 03:16.000
And then this also is a way to engage with the community so that you you all can share it with your friends or family or whoever's interested and then they can solicit to the economic development inbox which I manage and we can make sure we're getting those answers to the to the community.

03:17.000 --> 03:22.000
We'll talk about the partnerships that we have but I think the council knows.

03:22.000 --> 03:25.000
I interact a lot with the county the town.

03:25.000 --> 03:34.000
So I feel our friends groups main street the county and we're trying to make sure that we're reaching to all of those groups.

03:34.000 --> 03:38.000
We have a couple slides on that later which which I'll go into a little bit more at that time.

03:38.000 --> 03:41.000
But we're really excited to present this to you.

03:41.000 --> 03:46.000
We're excited to pull this all together and I'd like to and then introduce.

03:46.000 --> 03:49.000
We have Ben Wood from Stranden Associates.

03:49.000 --> 03:54.000
They Stranden has been working with us for many years so they are very knowledgeable on our systems.

03:54.000 --> 04:02.000
Ben will be doing most of the speaking and we also have Aaron girl from Kapoor engineers.

04:02.000 --> 04:07.000
He'll take a piece in this and then we have Roger and Rob who will have some speakers.

04:07.000 --> 04:13.000
Who will have some speaking points from our resident experts city engineer and public works.

04:13.000 --> 04:20.000
So without further ado I will let him come up and get connected and then we will ask you just to hold the question.

04:20.000 --> 04:26.000
So the end and then we'll try to answer those that we didn't capture in the presentation.

04:26.000 --> 04:27.000
Thank you Melissa.

04:27.000 --> 04:32.000
So we'll consolidate our questions and we'll wait until it's over.

04:32.000 --> 04:33.000
All right.

04:34.000 --> 04:37.000
And we're hoping we can get the system to work the entire time.

04:37.000 --> 04:38.000
Yep.

04:38.000 --> 04:39.000
Not to slice three.

04:47.000 --> 04:55.000
Okay. Thank you for that introduction Melissa. Thank you staff and council for being with us tonight.

04:55.000 --> 05:01.000
This will be as Melissa indicated very similar to what was presented last week at the public works committee.

05:01.000 --> 05:05.000
I'm happy to share it with the rest of the council here tonight.

05:05.000 --> 05:13.000
What we will cover is an overview briefly of the TID project plan that kind of sets the basis for all of the projects.

05:13.000 --> 05:25.000
The next major item will be all of the specific upcoming projects covering a variety of topics within those will kind of go through an overview map and then individual projects sites.

05:26.000 --> 05:30.000
Talking about the need and the thought process that went into each of those.

05:30.000 --> 05:38.000
While we'll step through that in kind of a map and a need orientation toward the end of the presentation, there is a project index.

05:38.000 --> 05:42.000
Before we wrap up with the summary.

05:42.000 --> 05:48.000
So for the TID project plan overview, this is a developer finance TID.

05:48.000 --> 05:57.000
Which means that the developer is at risk for the project cost and this is established in the already recorded development agreement.

05:57.000 --> 06:04.000
Approximately 180 million of city led to projects are identified in the approved.

06:05.000 --> 06:10.000
For TID project plan for TID number five as established by Ellers and shown here.

06:10.000 --> 06:19.000
The basis of the need for those specific projects covers a few categories expanded service area redundancy and resiliency and capacity.

06:19.000 --> 06:25.000
What we're going to go through specifically tonight are approximately 100 million dollars of those city led projects.

06:26.000 --> 06:37.000
And again, that is the near term forecast of project needs and toward the end will kind of address where are the balance of those projects and why aren't those being discussed in detail tonight.

06:37.000 --> 06:42.000
This map represents an overview of the project sites.

06:42.000 --> 06:48.000
It may be familiar to some of you as we've talked about specific other water or sewer system planning needs.

06:49.000 --> 06:54.000
But I want to break this down as kind of the foundation for the need for a lot of these projects.

06:54.000 --> 06:57.000
TID five covers the vantage site.

06:57.000 --> 07:01.000
The south portion which is being developed right now is shown in yellow.

07:01.000 --> 07:08.000
The north portion for which there is no imminent site specific development plan is shown in the pink.

07:09.000 --> 07:20.000
The canalsville obligation area which is a part of the town of Port Washington is shown in blue and then local adjacent lands are shown in green.

07:20.000 --> 07:31.000
The need to consider these local adjacent lands shown in green was prompted by the southeastern Wisconsin regional planning commission that.

07:31.000 --> 07:35.000
We're going to take a look at that.

07:35.000 --> 07:38.000
Encourage the city to think that.

07:38.000 --> 07:41.000
Think about what lands might.

07:41.000 --> 07:44.000
Attach themselves to municipal utilities.

07:44.000 --> 07:48.000
Once utilities are run this far north to 10 number five.

07:48.000 --> 07:59.000
So there is no obligation to serve those areas in green, but the southeastern regional planning commission wanted us to be prepared for that in the event it did happen.

08:00.000 --> 08:05.000
All of the TID five city led projects that will be discussing tonight.

08:05.000 --> 08:09.000
And we'll break down each of these kind of on a case by case basis.

08:09.000 --> 08:13.000
But I wanted to point out the various project categories as Melissa talked about.

08:13.000 --> 08:20.000
Grace was before you at the last meeting talking about some of the DOT and intersection improvement projects.

08:20.000 --> 08:23.000
We're covering the city led projects shown here.

08:23.000 --> 08:32.000
And as a note, the city led projects all start with a project number such as 26 one or 26 dash two.

08:32.000 --> 08:37.000
That is the construction start year that is planned.

08:37.000 --> 08:41.000
And then of course we understand these projects don't exist in a vacuum.

08:41.000 --> 08:48.000
You also have your normal capital improvements within the city and we're aware of the need to coordinate those.

08:49.000 --> 08:57.000
Scheduled drivers for the TID five projects include site occupancy and the city's obligations to Camelsville.

08:57.000 --> 09:01.000
Well, let's say you want to touch a little bit on city coordination.

09:01.000 --> 09:02.000
Thank you.

09:02.000 --> 09:09.000
So we realized that the city touches so many organizations.

09:09.000 --> 09:13.000
So this project will touch every corner of this city.

09:13.000 --> 09:16.000
It'll touch every corner of Ozaki County and beyond that.

09:17.000 --> 09:24.000
So one of my goals and one of my missions personally is to make sure that we are communicating.

09:24.000 --> 09:28.000
And can I go to the next one?

09:28.000 --> 09:35.000
When you think about all of the agencies that the city touches, we have the school district.

09:35.000 --> 09:39.000
We have the transportation to the bus company.

09:39.000 --> 09:43.000
We have the county and our neighbors.

09:43.000 --> 09:46.000
We have emergency services, the police department.

09:46.000 --> 09:51.000
We have on the waterfront, we have the yacht club, we have charter operations.

09:51.000 --> 09:57.000
When we're doing our, you know, our grave program, we realize that the boats that get that come out of the town of Port,

09:57.000 --> 10:00.000
we have to make sure that they can actually get their boats out to us.

10:00.000 --> 10:05.000
And there's like every, every element of the of our operations are impacted.

10:05.000 --> 10:08.000
We have the downtown businesses as partners, our economic development.

10:08.000 --> 10:11.000
So the county economic development.

10:11.000 --> 10:20.000
Then we have we energies and then our utilities and we have tourism, fish days, the veterans, like we are going to impact everyone.

10:20.000 --> 10:27.000
And so our mission here is to take this, you know, the citywide coordination and make sure that we're communicating out.

10:27.000 --> 10:40.000
And there is going to be a time that we miss a communication, but our goal is to keep a list going and make sure that when we're doing projects that we're reaching out or that the groups feel comfortable enough to reach in.

10:40.000 --> 10:49.000
And say, Hey, what about these lights are too low, because we just learned this today for the charters to get through out from the total portport Washington.

10:49.000 --> 10:51.000
And then we adjust and make sure that they can.

10:51.000 --> 11:00.000
So we're going to have misses, but know that we're trying and know that you can reach in and say, Hey, what about this may impact this run or this walk.

11:00.000 --> 11:06.000
We're going to do the best we can, but we have this in the, in our mind's eye while we're doing all this planning.

11:06.000 --> 11:07.000
So appreciate it.

11:07.000 --> 11:13.000
And next, we will have Aaron girl from before I believe.

11:13.000 --> 11:15.000
Thanks, Melissa.

11:15.000 --> 11:26.000
Good evening, everybody. So my role here is just to talk about the projects that we have planned for 2026 and then Ben will come back and speak on the projects thereafter.

11:26.000 --> 11:35.000
So this map here shows two blue stars, the southern or the lower star on the map is where we completed our work.

11:35.000 --> 11:40.000
This winter and spring completed the utility work.

11:40.000 --> 11:47.000
Paving still needs to happen in the next couple of weeks, but at least the utilities have been extended to that southern blue star.

11:47.000 --> 11:57.000
And the intent is in 26 and be completed by 2027 is to extend a water main loop up to Lake drive in the north side of the development.

11:57.000 --> 12:02.000
And also to serve a canalsville and the agreement that we have with canalsville.

12:02.000 --> 12:11.000
So with that, we want to talk about the specifics of this first project that we have planned in 26. This is a 26 dash one.

12:11.000 --> 12:16.000
This starts at the water tower along I 43 runs underneath.

12:16.000 --> 12:23.000
I 43 up to Mink Ranch Road with water main extends to the east on Mink Ranch all the way up to Highland drive.

12:23.000 --> 12:29.000
And then it connects into where the project finished this late winter early spring.

12:29.000 --> 12:31.000
And that also continues up.

12:31.000 --> 12:36.000
Kind of drunk highway KW up to approximately where the boat storage facility is.

12:36.000 --> 12:43.000
All right, so that's both sewer and water is about 9000 feet of water 3000 feet of sanitary sewer.

12:43.000 --> 12:50.000
And then we'll also extend sewer and water services or laterals to all of the parcels within canalsville.

12:50.000 --> 12:56.000
The purpose is to continue a loop for water main and then also to serve the canalsville obligation area.

12:57.000 --> 13:01.000
The schedule is first line item here is subject to permitting.

13:01.000 --> 13:04.000
I'll follow up a little bit more detail in a couple slides from here.

13:04.000 --> 13:07.000
But our plans are 90% complete.

13:07.000 --> 13:08.000
We plan on bidding now.

13:08.000 --> 13:09.000
It's already the end of April.

13:09.000 --> 13:19.000
So we expect to expect on bidding out in May and this project is expected to take about four and a half months to complete.

13:19.000 --> 13:35.000
Twenty six that's two is a continuation basically on county trunk KW from the boat storage area or facility north to lake drive and then heads east on lake drive to what was that northern blue star to maps ago.

13:35.000 --> 13:39.000
That's about 11,000 feet of water main.

13:39.000 --> 13:45.000
The intent is to complete looping for the development and also to serve canalsville.

13:46.000 --> 13:49.000
Again subject to permitting which I'll follow up more on the next slide.

13:49.000 --> 13:52.000
We're 90% complete with these plans.

13:52.000 --> 13:57.000
We'll bid these out in May and this construction timeline is about four months.

14:00.000 --> 14:02.000
Key considerations.

14:02.000 --> 14:14.000
We had some pre submittal meetings with both PSE and DNR to make sure that our team and the city staff and the approving agencies are aware of what are next.

14:15.000 --> 14:17.000
Plans are we talked about specifics.

14:17.000 --> 14:24.000
We talked about things that we were looking to do from the city standpoint and then they also told us some things that they were looking for.

14:24.000 --> 14:29.000
And so we're working and collaborating with the agencies to make sure that we're on the same page.

14:29.000 --> 14:34.000
We plan on submitting those permit applications to PSE and DNR in the next couple of weeks.

14:35.000 --> 14:45.000
Once PSE approval comes in play, the intent is to complete the water main loop up to lake drive on the northern end by January of 2027.

14:45.000 --> 14:47.000
One of the key components here is phasing.

14:47.000 --> 14:53.000
We understand that we're going to have to run both of these projects 26-1 and 26-2 concurrently.

14:53.000 --> 15:00.000
But we'll make sure that we write into our specifications that both contractors can't be working on KW at the same time.

15:01.000 --> 15:06.000
We'll make sure that the southern portion is completed before the northern portion starts.

15:06.000 --> 15:10.000
That'll help the businesses, the residents out there, and just in general traffic.

15:10.000 --> 15:15.000
Lastly is just a general preliminary detour map.

15:15.000 --> 15:20.000
This is similar to the detour that you see out there currently, but we'll finalize this map with our final plans.

15:20.000 --> 15:29.000
And once we finalize this map, we'll get that out to the public, make sure that everybody's aware of what the planned traffic changes will be based upon our construction.

15:30.000 --> 15:36.000
With that, I'll turn it back over to Ben.

15:36.000 --> 15:38.000
All right, thank you.

15:38.000 --> 15:45.000
To carry on with the plan, shown on the side are utility looping projects that are needed.

15:45.000 --> 15:51.000
So I'm going to start using the laser pointer on the back screen here to kind of help talk through these.

15:51.000 --> 16:07.000
So whereas projects 26-1 and 26-2 accomplish a partial loop, the other utility looping projects are needed along the east side up to the north to kind of complete primarily a water main loop.

16:07.000 --> 16:16.000
It's important to recognize that we're trying to optimize the project so that while water main may be the driving need,

16:16.000 --> 16:28.000
that while we have that corridor, that roadway torn up, that we also get in the gravity sewer, any force mains in there as well.

16:28.000 --> 16:43.000
So project 29-1 is kind of outlined in blue here, and that will include water, sewer, and some force main for the forthcoming lift station, which is shown as project 28-3.

16:43.000 --> 16:51.000
And that lift station would actually be kind of generally in this area. Specific site is not picked out yet.

16:51.000 --> 16:57.000
And then project 30-1, shown in the brown, would complete the loop of the water main up here.

16:57.000 --> 17:06.000
And then again, we would add gravity, sewer anywhere we can in the corridor while that area is disturbed.

17:06.000 --> 17:19.000
I want to talk about the Canalsville obligation. Canalsville is an unincorporated area within the town of Port Washington, shown in the figure here is the comprehensive land use plan map for Canalsville.

17:19.000 --> 17:31.000
There's an existing city and town agreement that establishes that the city will provide water and sewer to Canalsville and that those areas will remain part of the township.

17:31.000 --> 17:41.000
The existing agreement indicates that those water and sewer utilities have to be available for use by the end of 2027.

17:41.000 --> 17:47.000
This map shows specifically the projects that will help to accomplish this.

17:47.000 --> 17:55.000
I want to take a step back here and point out we have gravity sewer areas and lift station sewer areas.

17:55.000 --> 18:04.000
So while Canalsville is shown, all of those lands are shown in blue. There is some light blue hatched area. It's kind of difficult to see.

18:04.000 --> 18:08.000
I'm trying to outline it here. There are some light blue hatched areas.

18:08.000 --> 18:21.000
Basically, what we've determined in some preliminary analysis is that the hatched areas will not flow by gravity all the way through these sewers, all the way down to the wastewater treatment plant.

18:22.000 --> 18:33.000
And that because of the lay of the land, say at this break point by the boat storage area, gravity sewer would actually flow north to a lift station in this approximate area.

18:33.000 --> 18:38.000
And then that would have to get pumped back down into here where then it can flow by gravity.

18:38.000 --> 18:48.000
So we've discussed this concept with the town and what we've moved toward is putting in all of the water means that we can.

18:48.000 --> 18:53.000
And gravity sewers within the area where we're putting in water main.

18:53.000 --> 19:08.000
And that the lift station area projects that we would delay those beyond 2027 to allow for time to understand what the actual flows would be so that those lift stations can get sized and planned appropriately.

19:08.000 --> 19:21.000
It's also important to note that lift stations involve a lot of equipment and electronics that have longer lead times that realistically the construction schedule will just not allow for those projects to be done by the end of 2027.

19:22.000 --> 19:30.000
So as Aaron talked about project 26-1, here will include water main and sewers, and that will also serve Canalsville.

19:30.000 --> 19:38.000
And we're adding in project 27-2, which gets water main and sewer along County Highway H.

19:38.000 --> 19:50.000
At the end of each of those are anywhere from one to three properties that won't flow by gravity, but they're existing properties and the intent is that they get served on individual grinder pumps and small diameter.

19:50.000 --> 20:02.000
That covers the Canalsville West area, the Canalsville East area are these 28-3 and 29-1 projects I talked about.

20:02.000 --> 20:14.000
Actually, from this point on Highland Drive right here all the way north, the lay of the land is such that it flows all the way up to a low spot kind of at the top of the map here.

20:15.000 --> 20:28.000
That entire area, the sewer will drain to the north, have to get picked up by a lift station and then pumped in a force main all the way back to Highland Drive where it can kind of get into the existing city system.

20:28.000 --> 20:33.000
So I've noted on that project about approximately a year 2030 completion.

20:34.000 --> 20:39.000
Again, the purpose for delaying that is twofold. One, just the lead times on lift station components.

20:39.000 --> 20:51.000
And two, we want to make sure that we can get some kind of project specific or land use specific planning done so that those lift stations are sized appropriately.

20:52.000 --> 21:07.000
This map shows offsite tid improvements and these break into several categories, sewer conveyance, water distribution, wastewater treatment plant, planning and treatment plant site resiliency.

21:07.000 --> 21:15.000
This is an overview of those offsite tid projects. I'm going to take the next few slides to go through these in more detail.

21:16.000 --> 21:32.000
First of all, sewer conveyance. What this project accomplishes or these projects accomplish is not only conveying flow from the tid area down, also picking up canalsville also accounting for the flows from those green area adjacent lands.

21:33.000 --> 21:47.000
There are other local sewers that connect to this interceptor shown in pink here sewer. So it's going to help take on extra wet weather flows and convey those to the plants as well.

21:47.000 --> 22:01.000
So the pink project is from Terrace Drive all the way down to the wastewater treatment plant. It's broken up into three different bid packages, 27-3, 27-4 and 28-2.

22:01.000 --> 22:11.000
So we have kind of break points on the extents of these projects kind of as planned shown with these couple of dash marks here.

22:11.000 --> 22:22.000
Just know that those might change a little bit, but our intent and staff's intent is to keep in mind the potential disruption to local residents, users of the Inner Urban Trail.

22:22.000 --> 22:33.000
For example, project areas that might disrupt the Inner Urban Trail, we want to make sure they all get done in one construction season, Terrace Drive that gets done in one construction season.

22:34.000 --> 22:43.000
We know this is going to be a disruption to people and we just want to be cognizant of trying to coordinate that and minimize that to the extent practical.

22:43.000 --> 23:02.000
Another capacity increase project is 28-1. That's the Jackson Street Sewer Interceptor. That project is also going to upsize the diameter of that pipe and is critical to help convey what weather flows due to inflow and infiltration or what we call shorthand I&I.

23:02.000 --> 23:12.000
Water distribution upgrades. This map shows your existing water distribution system, which has two pressure zones.

23:12.000 --> 23:19.000
The purple area is the low pressure zone and that's inclusive of the water treatment plant.

23:19.000 --> 23:23.000
That's where all of the water produced is first pumped.

23:23.000 --> 23:33.000
Then there's the high pressure zone shown in green where water is repumped up to the higher elevations within the city so that everyone has appropriate pressure.

23:33.000 --> 23:44.000
Most of vantage and canalsville areas are in the high pressure zone, meaning all of that water has to get repumped from the low pressure zone up to the high pressure zone.

23:45.000 --> 23:50.000
Project 27-1 is a new consolidated booster station facility.

23:50.000 --> 23:59.000
Right now shown on the border of the low zone and the high zone are these two existing booster stations, the Oakland and the Sunset stations.

23:59.000 --> 24:12.000
A new consolidated booster station would be built that has all of the capacity as the existing two stations combined plus enough capacity for the added service area.

24:12.000 --> 24:17.000
This is a critical need because Oakland and Sunset stations are beyond their useful life.

24:17.000 --> 24:22.000
The equipment is aged and the existing stations have actually experienced a failure.

24:22.000 --> 24:29.000
That's why this one we would like to advance as quickly as possible.

24:29.000 --> 24:31.000
Treatment plant planning.

24:31.000 --> 24:37.000
This map shows the overall planning area for the wastewater treatment plants.

24:38.000 --> 24:41.000
This is the proposed sanitary sewer service area.

24:41.000 --> 24:54.000
So on the north side of that, you can see kind of the TID project site and adjacent lands, but I wanted to show the entire city extent because there are also some areas toward the west of the existing system.

24:54.000 --> 25:02.000
It's kind of moving towards Sockville that are being accounted for in wastewater treatment plant planning.

25:02.000 --> 25:12.000
The service area includes, again, Vantage, Canalsville, other known growth within the city and then some projects kind of toward the border.

25:12.000 --> 25:21.000
A facility plan is currently underway and the intent of that is to proactively forecast the project needs at the wastewater treatment plant.

25:21.000 --> 25:33.000
So that as we monitor the increase in flows to the plant, the projects are completed ahead of the time that we kind of forecast that capacity being needed.

25:33.000 --> 25:39.000
The sanitary sewer service area plan is being conducted by sewer pack.

25:39.000 --> 25:44.000
That establishes the service area relative to neighboring utilities.

25:45.000 --> 26:04.000
Quite specifically, we participated along with city staff and Sockville staff and staff from sewer pack to discuss which lands are more appropriate to be served by the city of Port Washington, which ones are to be served by Sockville, and that's accounted for in this map.

26:05.000 --> 26:09.000
Plan projects will only be implemented as the flows are realized.

26:09.000 --> 26:22.000
And then real briefly on the water treatment plant, the existing capacity is adequate for the actual usage, which is less than the planning request that came from Vantage.

26:22.000 --> 26:30.000
The actual site specific plans have actually resulted in a reduced forecasted capacity for the site.

26:31.000 --> 26:34.000
Treatment plant site resiliency.

26:34.000 --> 26:40.000
So shown in the middle here are projects 28-5 and 27-5.

26:40.000 --> 26:48.000
Note that as hopefully most of you know, the drinking water plant and the wastewater treatment plant are on a common site at the lakefront.

26:48.000 --> 26:57.000
There's been some, as was talked about earlier today, some bluff failures north of the wastewater treatment plant site.

26:57.000 --> 27:03.000
In the past, Valley Creek has been problematic and has caused some flooding at the drinking water treatment plant.

27:03.000 --> 27:11.000
Project 27-5 is the Valley Creek restoration for which an overview is shown here on the right.

27:11.000 --> 27:19.000
That design is in progress and the intent is to start bidding out that work in 2027.

27:19.000 --> 27:22.000
That will help mitigate the flooding at the plant.

27:22.000 --> 27:29.000
Some bluff stabilization is planned along with the wastewater treatment plant facility plan that is ongoing.

27:29.000 --> 27:34.000
That work is slated to start in 28 or 2029.

27:34.000 --> 27:48.000
It's critical to understand that this isn't expected to include bluff stabilization much north of the stairway that's going down from the upper to the lower portion where some of the failures have occurred.

27:48.000 --> 28:01.000
Rather, the intent behind this is that if a capacity increase is needed at the wastewater treatment plant, that means there needs to be a footprint expansion of that plant to accommodate new or expanded processes.

28:01.000 --> 28:13.000
And one of the options being considered or one of the alternatives being considered is expanding into the bluff, further stabilizing the bluff, building a retaining wall, etc.

28:13.000 --> 28:21.000
So the wastewater treatment plant facility plan that's ongoing needs to be completed first to choose what the best alternative is.

28:21.000 --> 28:26.000
One of those alternatives is bluff work.

28:26.000 --> 28:33.000
While this slide, this slide shows the project index for all of the city led projects.

28:33.000 --> 28:41.000
So whereas the previous maps kind of showed a color coded outline and name tag for each of these projects.

28:41.000 --> 28:45.000
This shows each of those projects kind of in a line item order.

28:45.000 --> 28:49.000
It actually includes a little more of a breakdown of the project.

28:49.000 --> 29:00.000
So this kind of pumpkin yellow or orange color here is all project 26-1 and it describes the various segments of water and sewer, etc.

29:00.000 --> 29:11.000
And that's the case for all of the projects on here. So if you would like to read more about the specific expense of a project that can be found here in the project index.

29:11.000 --> 29:20.000
Of course, like I mentioned, we understand that the city of Port Washington has all of its normal capital improvement needs within the city.

29:20.000 --> 29:26.000
And it's important to know that coordination between our consultant team and city staff is ongoing.

29:26.000 --> 29:39.000
We actually meet together on a weekly basis and one of the kind of rolling topics discussed is coordination of each of these projects on a case by case basis.

29:39.000 --> 29:49.000
So as Melissa opened with, just know that we recognize and it's important to us to coordinate these to be as efficient as possible.

29:49.000 --> 29:58.000
So in summary, this presentation is intended to provide the background for specific forthcoming project plans and decisions.

29:58.000 --> 30:09.000
Approximately $100 million of city led to five projects are anticipated in the next five years, the financing of which is provided by the developer.

30:10.000 --> 30:20.000
Extensive project coordination is ongoing. This is between projects, between governments and departments, the community and organizations.

30:20.000 --> 30:29.000
This overall plan will be revised as actual projects progress. And with that, we would like to go ahead and open it up for any questions.

30:29.000 --> 30:32.000
Questions.

30:33.000 --> 30:49.000
Sure, I'll go first. We talked about the Bluff stabilization work. I mean, I guess, Rob would behoove us at all to consolidate some of that work further north. I mean, can we consolidate some of that work with work further north?

30:49.000 --> 30:55.000
Do we start making decisions now in time for 2728 as a part of this work?

30:55.000 --> 31:02.000
Yeah, I think some of what we're going to discuss in the upcoming months, first of all is what we want, I probably park to look like on top of the bluff.

31:02.000 --> 31:08.000
And then we already have the engineering plans for stabilization of the bluff.

31:08.000 --> 31:20.000
And so that depending upon what the sewer pack facilities plan comes back with, we'll kind of inform our decision making going forward on stabilization.

31:21.000 --> 31:33.000
So, I just had a question. Are all the upgrades for a vantage in here? Is this assuming phase one or just phase two effect?

31:33.000 --> 31:45.000
It's just phase one, which by that, I assume you mean the yellow area or the southern part that's kind of under construction right now. It's the project specific to that.

31:46.000 --> 31:58.000
So, if the north phase, if a site specific development plan is brought forth for that, it would likely include more water main looping and sewer extension projects.

31:58.000 --> 32:03.000
Is Miller?

32:03.000 --> 32:14.000
Yes. So, is the stabilization of the bluff helped or is a hindrance because of the wastewater treatment center?

32:14.000 --> 32:21.000
Would it be appropriate to think about maybe moving that to maybe make a better structure?

32:21.000 --> 32:25.000
About specifically about moving the wastewater plant altogether?

32:25.000 --> 32:26.000
Yes.

32:26.000 --> 32:35.000
Yeah, so it's, I'm glad that you brought that up. So, the wastewater treatment plant facility plan is ongoing right now.

32:35.000 --> 32:39.000
And we expect to be done with that toward the end of this calendar year.

32:39.000 --> 32:50.000
It will consider all types of big picture alternatives for that site, one of which will be considering moving the plants altogether.

32:50.000 --> 32:54.000
So, I'm glad that you brought that up.

32:54.000 --> 33:02.000
Also, anybody that's in the Canalsville area or any of the areas that will now have water are not going to be forced to take the water.

33:03.000 --> 33:11.000
That will be their choice, the homeowners choice as to whether or not they choose to participate in our water sewer systems.

33:11.000 --> 33:19.000
That's a good question. And what I'll say to that is that's a policy decision kind of between the leaders and the public.

33:19.000 --> 33:24.000
The public service commission will have something to say about that also.

33:24.000 --> 33:35.000
What I will tell you is that the town chair for Port Washington for the town of Port Washington has actually gone door to door to talk to people to garner interest.

33:35.000 --> 33:46.000
And for those that are interested in connecting right away, Aaron has taken into that, taken that into account as he's planning those projects.

33:47.000 --> 33:54.000
That is, however, a town responsibility, correct, not a city of Port Washington responsibility because that was our understanding from the beginning.

33:54.000 --> 33:58.000
I just wanted to be clear that we're not forcing them to do anything.

33:58.000 --> 34:01.000
No, that's a separate municipality.

34:01.000 --> 34:04.000
Other questions?

34:04.000 --> 34:07.000
I just have a couple of things.

34:07.000 --> 34:14.000
One of them was same as Miss Miller there with the KW Hookup process with the town just to make sure that that's clear.

34:15.000 --> 34:28.000
One of the pieces that I'm going to ask that as you're developing and doing the different projects along KW and then LL that could you please make sure to communicate very proactively with Johnson Bus.

34:28.000 --> 34:35.000
I had a conversation with them yesterday and just if they can have a two, three week kind of run of this is when this is going to be closed, etc.

34:35.000 --> 34:41.000
Obviously, post Memorial Day should not be as big of an issue, but summer school transportation, etc.

34:41.000 --> 34:44.000
And that's been working very, very well.

34:44.000 --> 34:51.000
The other thing is the thoughtfulness that you have put in place here, I want to just applaud.

34:51.000 --> 35:02.000
I know it's what you do, but like on our end of, hey, we're going to start the south end of the project first before moving to the north, not shutting those down, coordinating with multiple contractors.

35:02.000 --> 35:05.000
Just being thoughtful for our neighbors and that flow of traffic.

35:05.000 --> 35:11.000
Lots of people shoot up H and KW to get to Belgium and then head to work and Plymouth and Sheboygan and all kinds of other places.

35:11.000 --> 35:13.000
So I really appreciate that.

35:13.000 --> 35:18.000
One other thing that I wanted to point out too is already we're feeling an impact here.

35:18.000 --> 35:27.000
I mean, I think last week and the week before with the rain is the first time in a really long time that Valley Creek did not surge.

35:27.000 --> 35:28.000
Tons of trees down.

35:28.000 --> 35:30.000
I mean, Salt Creek was huge.

35:30.000 --> 35:37.000
So you can already tell the retention, the reduction of different drain tiles on that egg land is already making a difference.

35:37.000 --> 35:39.000
So I appreciate your work on that as well.

35:39.000 --> 35:41.000
And then the last thing is an expectation.

35:41.000 --> 35:56.000
I'd like to throw out there, which is that we work with a team to create a real strong construction calendar that's almost quarterly that goes out with all of these projects so that the community can foreshadow and see this is what's coming.

35:56.000 --> 35:58.000
This is when it is.

35:58.000 --> 36:02.000
And then even putting out kind of like a next week in Port Washington social media posts.

36:02.000 --> 36:05.000
So people just are that's in front of us.

36:05.000 --> 36:10.000
So, you know, why the heck is the bike trail closed and where did this come from and how come we didn't know.

36:10.000 --> 36:15.000
And I think it's going to be really, really important for us to be as proactive as possible in those communications.

36:15.000 --> 36:16.000
So.

36:16.000 --> 36:18.000
Mr. Mayor, I did want to just mention one thing.

36:18.000 --> 36:24.000
The inner urban trail does come up a lot and I failed to mention it earlier.

36:24.000 --> 36:27.000
That is actually run by the county.

36:27.000 --> 36:33.000
They have their own web page and their own Facebook page on when their closures are and then the closures are done by we energies.

36:33.000 --> 36:37.000
So we won't always know and we won't be communicating out.

36:37.000 --> 36:45.000
We tell everyone to go to that and we put it on the website, but that is really a trail that's owned by we energies that lets us use it.

36:45.000 --> 36:53.000
And, you know, they don't always get a chance to update us, but that website on an urban trail Andy at the county keeps that updated.

36:53.000 --> 36:55.000
So just so the community knows.

36:55.000 --> 36:56.000
Yeah, thank you.

36:56.000 --> 36:59.000
I just anything within our purview. Let's.

36:59.000 --> 37:01.000
Double down on so thank you for that.

37:01.000 --> 37:05.000
Okay, that's what I had any other that spark anything else.

37:05.000 --> 37:06.000
Otherwise.

37:06.000 --> 37:08.000
You're a gas bar.

37:08.000 --> 37:12.000
I'd say just, I will presume that the.

37:12.000 --> 37:19.000
Santari sewer along the inner urban trail in the city, which actually the county does not maintain the portions in the city limit.

37:19.000 --> 37:20.000
We do.

37:21.000 --> 37:23.000
That I presume the trail will have to be closed for that.

37:23.000 --> 37:34.000
We need to make sure that that is there is public relations through the county with their website and that we get a detour route posted because that trail is very valuable to tourism in the city.

37:34.000 --> 37:35.000
Sure.

37:35.000 --> 37:36.000
Sure.

37:36.000 --> 37:37.000
Yeah.

37:38.000 --> 37:39.000
Long term game.

37:39.000 --> 37:40.000
So thank you.

37:40.000 --> 37:41.000
All right.

37:41.000 --> 37:42.000
Well done.

37:42.000 --> 37:43.000
Thank you.
