WEBVTT

00:00.880 --> 00:04.320
I call to order the September 8th,

00:04.320 --> 00:06.920
2026 City of Port Washington,

00:06.920 --> 00:10.220
Board of Public Works meeting to order.

00:11.960 --> 00:13.840
Chairman Gaspard is not able to make it tonight,

00:13.840 --> 00:15.160
so I'm filling in for him.

00:15.160 --> 00:18.980
Also not in attendance is Mr. Brooks.

00:20.920 --> 00:23.120
I guess item two is to approve the minutes

00:23.120 --> 00:24.800
from the previous meeting.

00:24.800 --> 00:29.000
That would be August 25th, 2026.

00:29.000 --> 00:31.680
Any questions or comments on those minutes?

00:31.680 --> 00:33.720
No, but I'll make a motion to approve the minutes

00:33.720 --> 00:34.880
as written.

00:34.880 --> 00:37.680
All right, a motion by older woman Miller.

00:37.680 --> 00:38.520
I have a second.

00:38.520 --> 00:39.560
Second.

00:39.560 --> 00:41.000
Second by Mr. Paulie.

00:41.000 --> 00:42.120
All in favor.

00:42.120 --> 00:42.960
All right.

00:45.200 --> 00:48.760
Agenda item number three, public comments and appearances.

00:48.760 --> 00:50.680
Anybody wishing to address the board

00:50.680 --> 00:54.120
can step to the podium, address your name,

00:54.120 --> 00:55.920
state your name, address,

00:55.920 --> 00:58.120
and you have three minutes to speak.

00:59.840 --> 01:03.200
Any publics, public comments?

01:04.240 --> 01:05.080
No.

01:06.280 --> 01:11.280
Seeing none, we'll move to item number four.

01:11.560 --> 01:15.600
Presentation of kid number five, project planning.

01:15.600 --> 01:16.440
Kapoor.

01:29.840 --> 01:31.000
Thank you.

01:48.200 --> 01:50.280
I think we're all set here.

01:53.160 --> 01:55.600
Thank you everybody for having us back up.

01:55.600 --> 01:57.000
My name is Ben Wood.

01:57.000 --> 01:58.440
I'm with Strand Associates.

01:58.440 --> 02:01.520
I recognize Aaron Grohl from Kapoor.

02:01.520 --> 02:03.200
We're here tonight to give you an update

02:03.200 --> 02:07.120
on the overall TID 5 project plan.

02:07.120 --> 02:12.120
We were back in front of you last, back in April,

02:12.600 --> 02:15.200
kind of laying out a plan for you.

02:15.200 --> 02:17.760
Part of that plan talked about how important it was

02:17.760 --> 02:19.520
to coordinate and work together

02:19.520 --> 02:21.760
across the community here.

02:21.760 --> 02:24.880
Tonight's presentation is a follow up on that

02:24.880 --> 02:27.920
now that the projects have some more definition

02:27.960 --> 02:32.800
to them, it's a good time to provide an update to the board.

02:32.800 --> 02:36.480
And of course, we recognize that we're still striving

02:36.480 --> 02:41.080
to work with the city to partner across departments

02:41.080 --> 02:44.840
and whether it's businesses or outside entities

02:44.840 --> 02:46.800
that are affected by these projects

02:46.800 --> 02:51.800
to coordinate often regarding this plan.

02:52.120 --> 02:55.720
So tonight we're going to just touch very briefly

02:55.720 --> 02:58.600
on an overview of the TID project plan.

02:58.600 --> 03:01.360
We'll look at a broad project map and schedule.

03:01.360 --> 03:03.280
And then we're going to go through each

03:03.280 --> 03:07.080
of the forthcoming projects, kind of one by one

03:07.080 --> 03:10.680
to give you some details on their scope and schedule.

03:10.680 --> 03:12.560
And we'll wrap up with a summary.

03:13.920 --> 03:17.320
So all of the projects here are identified

03:17.320 --> 03:20.200
in the TID 5 project plan.

03:20.200 --> 03:23.680
Reminder that TID 5 is a developer finance TID.

03:23.720 --> 03:28.720
The developer is at risk for the financing of this plan.

03:28.960 --> 03:32.040
That includes approximately $180 million

03:32.040 --> 03:34.600
of city led projects.

03:34.600 --> 03:38.160
The basis of the project need in the TID project plan

03:38.160 --> 03:41.880
includes, of course, the expanded service area,

03:41.880 --> 03:44.400
but also redundancy and resiliency projects

03:44.400 --> 03:48.800
within the existing city and its infrastructure and capacity.

03:50.360 --> 03:53.600
This map you'll recognize from a lot of meetings

03:53.600 --> 03:55.920
in the past, but I just want to break it down.

03:55.920 --> 04:00.760
This is the overall map of the city led TID projects.

04:00.760 --> 04:03.800
Of course, in the upper portion of the map,

04:03.800 --> 04:06.800
we have the yellow and the pink.

04:06.800 --> 04:09.160
Those are the vantage-owned lands

04:09.160 --> 04:13.080
and the yellow is what's under construction right now.

04:13.080 --> 04:16.200
The blue areas, kind of toward the southern portion

04:16.200 --> 04:18.880
of that are the Canalesville obligation areas

04:18.880 --> 04:21.080
where the city has agreed to provide

04:21.080 --> 04:23.760
municipal utility service.

04:23.760 --> 04:26.680
The green areas that kind of surround that are areas

04:26.680 --> 04:30.760
that the Southeastern Wisconsin Regional Planning Commission

04:30.760 --> 04:34.080
encourage the city to include as ancillary areas

04:34.080 --> 04:38.320
that may have potential for future development

04:38.320 --> 04:41.600
that could also connect to municipal utilities

04:41.600 --> 04:44.560
sometime down the road.

04:44.560 --> 04:47.800
And then individual projects on this map,

04:47.800 --> 04:49.760
I guess I'll point over here.

04:49.760 --> 04:51.920
These are all numbered by project year

04:51.920 --> 04:55.480
and they're kind of grouped together by color and purpose.

04:55.480 --> 04:59.000
And I know this is kind of hard to understand

04:59.000 --> 05:01.240
and digest individual projects on this,

05:01.240 --> 05:04.680
but we'll get through each of these sort of one by one.

05:04.680 --> 05:08.160
But generally speaking, we have projects associated

05:08.160 --> 05:12.400
with the TID 5 development site up here to serve that.

05:12.400 --> 05:16.720
We have projects that are within the existing cities,

05:16.720 --> 05:19.080
service area and realm of infrastructure

05:19.080 --> 05:23.880
that need to be addressed in order to improve service

05:23.880 --> 05:26.320
to that area that are in this plan.

05:29.120 --> 05:32.720
A new portion of this since April is an overall

05:32.720 --> 05:36.360
Gantt chart of how all of these projects

05:36.360 --> 05:38.240
and their schedules align.

05:39.400 --> 05:42.200
There's a lot going on here and this is,

05:42.200 --> 05:44.200
I'm showing this now to kind of set the table

05:44.200 --> 05:46.720
for going through these one by one.

05:46.720 --> 05:48.720
But I wanted to start with this overall summary

05:48.880 --> 05:51.880
but for now what I want you to understand is legend.

05:51.880 --> 05:54.640
The overall project arrow here just represents

05:54.640 --> 05:58.120
the entire project length starting at design

05:58.120 --> 06:02.120
and permitting all the way through final completion.

06:02.120 --> 06:05.720
The star on that Gantt chart represents

06:05.720 --> 06:08.720
the construction contract award

06:08.720 --> 06:12.520
and then the hatched lines here

06:12.520 --> 06:17.520
represents when active construction will be going on.

06:19.480 --> 06:22.080
So the first three projects at the top

06:22.080 --> 06:25.800
are utility extensions intended to serve

06:25.800 --> 06:29.480
the vantage lands that are under development right now.

06:29.480 --> 06:31.840
The black and gray projects in the middle

06:31.840 --> 06:34.080
are projects that are more internal

06:34.080 --> 06:36.560
to the city's existing infrastructure,

06:36.560 --> 06:40.560
including wastewater treatment, plant planning,

06:40.560 --> 06:42.880
water projects, some interceptor work,

06:42.880 --> 06:45.360
the Valley Creek restoration.

06:45.360 --> 06:48.680
The pink projects here represent three different phases

06:48.720 --> 06:52.640
of the interceptor that needs to be upsized

06:52.640 --> 06:55.080
at the downstream point of the vantage lands

06:55.080 --> 06:57.120
all the way to the wastewater treatment plant

06:57.120 --> 07:00.240
and how that's getting phased over multiple years

07:00.240 --> 07:02.720
and multiple bid packages.

07:02.720 --> 07:04.800
The two different types of blue projects

07:04.800 --> 07:07.960
or the two different shades of blue projects down here,

07:07.960 --> 07:10.720
they represent utility looping around

07:10.720 --> 07:12.800
the existing vantage lands

07:12.800 --> 07:17.280
as does the last project, the Brown project down here.

07:17.280 --> 07:18.800
Those all have this note that those

07:18.800 --> 07:21.720
are development dependent right now.

07:21.720 --> 07:25.920
We're trying to get through these most urgent projects

07:25.920 --> 07:29.960
to get them a minimum level of service

07:29.960 --> 07:33.320
and then depending on how adjacent lands

07:33.320 --> 07:36.440
could potentially specifically develop

07:36.440 --> 07:39.320
might kind of shape how the schedule

07:39.320 --> 07:43.280
and the planning of those final looping projects

07:43.280 --> 07:46.300
are how those come to pass.

07:48.080 --> 07:50.480
With that, we're gonna get into these kind of one by one

07:50.480 --> 07:52.120
and I'm gonna turn it over to Aaron

07:52.120 --> 07:53.880
to talk about the first project.

07:55.520 --> 07:56.360
Thanks, Ben.

07:57.360 --> 07:58.200
Good evening, everybody.

07:58.200 --> 08:00.000
Thanks again for having us.

08:00.000 --> 08:03.960
So this slide should be familiar to you

08:03.960 --> 08:07.520
other than a few updates, basically the schedule.

08:07.520 --> 08:09.880
So this was bid outs just recently

08:09.880 --> 08:14.880
and prices were submitted by contractors for this 26-1,

08:15.000 --> 08:16.880
which is Highland Drive utilities.

08:16.880 --> 08:18.880
It's about 8,000 feet of water main

08:18.880 --> 08:20.880
and 3,000 feet of sanitary sewer

08:20.880 --> 08:22.880
and it's to serve the sewer and water

08:22.880 --> 08:24.880
for the Canalsville area.

08:26.880 --> 08:31.880
We're also looping on the south to the south connection point

08:31.880 --> 08:36.880
within the city and serving the obligation areas

08:36.880 --> 08:39.880
part of the inter municipal agreement

08:39.880 --> 08:41.880
between the city and the town.

08:42.880 --> 08:46.880
Bids were received as I just stated a few weeks ago

08:46.880 --> 08:51.880
and the intent is to recommend for award this October

08:52.880 --> 08:57.880
upon internal reviews between staff, city staff,

08:58.880 --> 09:01.880
the consultants and also the attorneys.

09:02.880 --> 09:06.880
The intent for this project is likely to start up

09:06.880 --> 09:10.880
in as early as January, but most likely would start up

09:10.880 --> 09:15.880
in March in 2027 with completion

09:16.120 --> 09:19.640
and towards the end of next year.

09:19.640 --> 09:24.640
This is however subject to DNR and PSC approvals

09:25.440 --> 09:28.560
which they are in the works as we speak.

09:32.480 --> 09:36.680
26-2, similar to 26-1.

09:36.680 --> 09:41.360
So this is the northern portion to serve

09:41.360 --> 09:44.240
the north side of the vantage site

09:44.240 --> 09:47.520
that runs up KW up to Lake Drive.

09:47.520 --> 09:51.680
This is just water main and we're attending

09:51.680 --> 09:56.080
on installing these in trenchless methods

09:56.080 --> 09:59.120
to minimize amount of construction impacts

09:59.120 --> 10:01.720
and traffic impacts to the property owners

10:01.720 --> 10:03.680
along this stretch.

10:03.680 --> 10:06.480
Also adding metering vaults, pressure-reducing

10:06.480 --> 10:09.560
station and automatic flushing hydrants

10:09.560 --> 10:12.280
for this project as well.

10:12.280 --> 10:15.920
Again, the purpose of this is to loop the water

10:15.920 --> 10:18.280
all the way to the northern connection point

10:18.280 --> 10:20.720
for the development and to serve

10:20.720 --> 10:23.480
Knesswell obligation area as well.

10:24.640 --> 10:28.880
Similar to 26-1, bids were received a few weeks ago.

10:29.920 --> 10:32.440
We're under review as we speak

10:32.440 --> 10:36.320
and we anticipate bringing that to the Board of Public Works

10:36.320 --> 10:39.800
next month for recommending award

10:39.800 --> 10:43.360
assuming our review suggests so.

10:44.360 --> 10:49.360
Again, this as well is pending DNR and PSC approvals.

10:51.800 --> 10:53.880
The construction schedule for this

10:53.880 --> 10:57.320
likely would start up in January of next year

10:57.320 --> 11:02.320
and would run into late spring, early summer.

11:06.320 --> 11:11.040
So key considerations that we identified

11:11.040 --> 11:14.480
through these projects, we worked hand-in-hand

11:14.480 --> 11:19.480
with the DOT, Ozaki County, the town,

11:21.000 --> 11:24.720
the vantage development and we wanted to make sure

11:24.720 --> 11:27.040
that we address traffic.

11:27.040 --> 11:31.160
Traffic was a big issue to ensure that we can route

11:32.160 --> 11:33.800
the residents that live in this area,

11:33.800 --> 11:37.040
businesses that are in this area around the site

11:37.040 --> 11:42.040
and that these projects combine with vantage traffic

11:42.920 --> 11:44.280
that they will flow together.

11:44.280 --> 11:47.800
So we worked hard together with the vantage staff

11:47.800 --> 11:50.840
and their team to ensure that these traffic patterns

11:50.840 --> 11:53.400
work with what they're intending on doing

11:53.400 --> 11:55.800
and try to minimize the impacts to the city

11:55.800 --> 11:59.040
and also the town residents and the county residents.

11:59.040 --> 12:01.320
So the traffic routes that you see here

12:01.320 --> 12:02.760
are detour routes.

12:02.760 --> 12:06.080
Again, these have already been approved by the DOT

12:06.080 --> 12:08.480
and the county and the town as well

12:08.480 --> 12:10.880
in our coordination efforts and trying to make sure

12:10.880 --> 12:13.320
that we're all on the same page.

12:18.120 --> 12:21.200
So the next step, the next project is 27-2

12:21.200 --> 12:22.680
which is County Trunk Highway H.

12:22.680 --> 12:27.680
So this is the next phase to serve Canalsville

12:28.160 --> 12:30.480
in the obligation area.

12:30.480 --> 12:34.600
This basically is from the intersection of KW and H

12:34.600 --> 12:39.600
and it runs to the Northwest from the intersection.

12:41.560 --> 12:44.520
We're about 2,500 feet or 2,400 feet of water main,

12:44.520 --> 12:47.000
1,800 feet of sanitary sewer.

12:47.000 --> 12:49.440
As I just stated, it's to serve the Canalsville

12:49.440 --> 12:52.760
obligation area and also create a connection

12:52.760 --> 12:57.760
between a water main connection between County Trunk KW

12:58.200 --> 13:03.200
and County Trunk H to improve water flow

13:03.560 --> 13:05.240
and service for the residents

13:05.240 --> 13:07.960
and the property owners in this area.

13:07.960 --> 13:10.080
We're currently designing this project.

13:11.280 --> 13:13.680
We are anticipating on going out to bid

13:13.680 --> 13:17.640
with this late in 2026 or early 27

13:17.640 --> 13:20.400
with construction in 2027.

13:21.600 --> 13:25.720
Permits have not been submitted for this stretch yet.

13:25.720 --> 13:28.680
So they'll be submitted once we get a little bit further

13:28.680 --> 13:30.360
along in our design.

13:32.520 --> 13:35.440
Aaron, can you tell everybody what the Canalsville

13:35.440 --> 13:38.800
obligation area is or what it means?

13:38.800 --> 13:40.880
So let me go back here real quick.

13:42.440 --> 13:45.880
So the Canalsville obligation area has been stated earlier.

13:45.880 --> 13:49.440
It's in blue and I know you can't, it's hard to see

13:49.440 --> 13:54.440
but there's the annexation of the area that's in yellow

13:54.880 --> 13:58.400
and pink that was town and now is city.

13:59.480 --> 14:02.920
The agreement was to between the town and the city

14:02.920 --> 14:07.920
was to serve water and sewer to the town of Canalsville.

14:08.680 --> 14:10.560
So the town of Canalsville is actually

14:10.560 --> 14:12.120
the town of Port Washington.

14:12.120 --> 14:14.720
It's a portion of the town of Port Washington.

14:14.720 --> 14:19.000
And in order for this agreement to move forward,

14:20.000 --> 14:23.120
water and sewer being extended first to the area,

14:23.160 --> 14:26.040
the larger blue area that's to the left,

14:26.040 --> 14:31.040
which holy is running up and down KW and H

14:31.680 --> 14:35.000
and then also a little bit left on Mink Ranch Road.

14:35.000 --> 14:37.000
And then the second area, which is a small

14:37.000 --> 14:40.840
sliver along Konechunk Highway LL

14:40.840 --> 14:43.720
as you're heading to the northeast.

14:43.720 --> 14:46.640
That's another area that is also within the town

14:46.640 --> 14:48.080
of Canalsville.

14:48.080 --> 14:51.520
That has been agreed upon to be served in the future

14:51.520 --> 14:56.520
as that section of that portion of the service area develops.

15:00.240 --> 15:02.440
Okay, all right, sure.

15:06.280 --> 15:09.280
All right, from that, I'm gonna turn this back over to Ben.

15:10.800 --> 15:11.640
Thank you.

15:13.280 --> 15:16.560
Wastewater treatment planning, the schedule,

15:16.560 --> 15:20.080
this doesn't have any construction associated with it

15:20.080 --> 15:22.240
on that little bar chart at the top there,

15:22.240 --> 15:27.240
but both wastewater treatment plant facility plan

15:27.240 --> 15:30.960
and a sanitary sewer service area updates

15:30.960 --> 15:33.840
are happening concurrently right now

15:33.840 --> 15:36.160
and they're expected to be completed

15:36.160 --> 15:38.360
toward the middle of next year.

15:38.360 --> 15:40.760
So shown on the left there is obviously

15:40.760 --> 15:44.400
the footprint of the wastewater treatment plant.

15:44.400 --> 15:48.720
You can see that reality comes at a premium down here.

15:48.720 --> 15:50.680
It's kind of running out of space.

15:50.680 --> 15:55.760
DNR requires that as you're approaching 80% of plant capacity

15:55.760 --> 16:00.000
that you have to go through what they call a facility plan

16:00.000 --> 16:02.720
to proactively review options

16:02.720 --> 16:05.640
for how you would expand your treatment processes

16:05.640 --> 16:08.160
within your existing plant footprint

16:08.160 --> 16:11.720
or how you might expand the plant

16:12.760 --> 16:16.600
in order to address capacity.

16:16.600 --> 16:20.480
So far, based on the flows that Vantage has given us,

16:20.480 --> 16:24.080
we're not expecting that a capacity expansion will be warranted,

16:24.080 --> 16:26.960
but again, we're going through this process proactively

16:28.800 --> 16:33.120
just to follow the DNR guidelines in that regard.

16:33.120 --> 16:35.720
Part of that includes reviewing options

16:35.720 --> 16:37.920
for how the plant would be expanded

16:37.920 --> 16:41.240
if extra capacity was needed.

16:41.240 --> 16:44.520
The image on the right shows the service area.

16:44.560 --> 16:47.320
Again, it's got that same composition of the yellow

16:47.320 --> 16:49.680
and the pink being the Vantage lands,

16:49.680 --> 16:52.240
the blue being the Canalsville obligation

16:52.240 --> 16:54.320
and green being those adjacent lands

16:54.320 --> 16:58.160
that the Regional Planning Commission asked the city

16:58.160 --> 17:02.880
to include that sewer service area update

17:02.880 --> 17:06.080
is actually a process that is led by sewer pack

17:06.080 --> 17:10.200
or Southeastern Wisconsin Regional Planning Commission.

17:10.200 --> 17:12.280
It's led by sewer pack staff

17:13.280 --> 17:17.880
and as far as we know, they are on track

17:17.880 --> 17:22.880
for a second quarter completion of that plan next year.

17:23.680 --> 17:27.160
This plan and the areas within it,

17:27.160 --> 17:30.640
sewer pack has to approve this service area

17:30.640 --> 17:34.880
before sanitary sewers can be indeed installed

17:34.880 --> 17:38.040
and permitted by DNR to kind of serve the rest

17:38.040 --> 17:39.520
of the areas beyond that.

17:39.520 --> 17:42.280
So what's included right now is all

17:42.280 --> 17:45.600
of the Canalsville obligation area,

17:45.600 --> 17:47.440
all of the yellow lands,

17:47.440 --> 17:49.920
and then it's the pink and the green

17:49.920 --> 17:53.640
that are kind of subject to sewer packs update right now.

17:56.440 --> 17:58.680
The next one, this is kind of a busy slide,

17:58.680 --> 18:00.680
but it's an important project for the city.

18:00.680 --> 18:02.880
It's the Water Booster Station,

18:02.880 --> 18:06.960
Water Distribution Facility and the Associated Water Means.

18:06.960 --> 18:09.200
So I'm gonna ask you to just focus on the pictures

18:09.200 --> 18:10.040
first.

18:10.040 --> 18:12.000
So on the upper left here we have one

18:12.000 --> 18:14.120
of the existing two booster stations

18:14.120 --> 18:16.440
that are out in the distribution system.

18:16.440 --> 18:18.240
This is the Oakland Station.

18:19.800 --> 18:22.280
Stray and conducted a water system master plan

18:22.280 --> 18:25.240
and facility condition assessment of this

18:25.240 --> 18:30.240
and presented the findings of that to the Public Works Board.

18:30.840 --> 18:33.280
I believe both in January and in March

18:34.240 --> 18:36.400
that these existing two,

18:36.400 --> 18:38.480
both the Oakland and Sunset stations

18:38.480 --> 18:40.000
that are out in the system,

18:40.000 --> 18:42.760
are aged beyond their useful life.

18:42.760 --> 18:45.400
One of the stations actually had a critical failure,

18:45.400 --> 18:48.120
I believe that was last year in 2025.

18:49.200 --> 18:53.800
And it's very important that those booster stations

18:53.800 --> 18:55.120
be replaced.

18:55.120 --> 18:57.720
Our master plan demonstrated the best way to do that

18:57.720 --> 19:00.880
is to build a brand new consolidated booster station.

19:02.360 --> 19:05.400
And we were asked as a followup

19:05.400 --> 19:08.920
to do a booster station sighting study.

19:08.920 --> 19:13.000
We reviewed seven potential sites throughout the city.

19:13.000 --> 19:15.240
The selected site is actually right next

19:15.240 --> 19:20.160
to the existing Oakland station still on Oakland Avenue.

19:20.160 --> 19:25.160
And then the larger map down here on the bottom shows

19:25.160 --> 19:28.720
that along with a upsized and consolidated booster station,

19:28.720 --> 19:31.920
the yellow path shows the route that we're proposing

19:32.080 --> 19:35.880
that water mains be replaced with a larger diameter main

19:35.880 --> 19:39.440
in order to have the carrying capacity

19:39.440 --> 19:43.440
that those pumps can put out through that station.

19:44.360 --> 19:47.640
Now this route has a couple of jogs in it

19:47.640 --> 19:50.320
and part of that is taking into account

19:50.320 --> 19:53.160
the condition of the existing water mains.

19:53.160 --> 19:56.120
And we tried to route the water mains along areas

19:56.120 --> 19:58.680
that have other needs anyways

19:58.680 --> 20:00.760
where the existing water main has experienced

20:00.760 --> 20:03.480
a lot of breaks or potentially has led service lines,

20:03.480 --> 20:04.560
et cetera.

20:04.560 --> 20:07.000
And that just helps kind of

20:07.000 --> 20:09.360
economize the project and get the highest return

20:09.360 --> 20:11.440
on investment for the project scope.

20:12.360 --> 20:15.840
So included in the scope would be a new booster station.

20:15.840 --> 20:19.080
We would demolish the Oakland and sudden set stations

20:19.080 --> 20:22.920
relay approximately 6,000 feet of water main.

20:22.920 --> 20:25.760
And then also what those past master plan

20:25.760 --> 20:29.440
and sighting studies considered was that the water

20:29.480 --> 20:34.480
department is in need of a new distribution garage facility.

20:34.960 --> 20:38.000
We talked in the past that due to the current

20:38.000 --> 20:40.960
and almost completed capacity expansion

20:40.960 --> 20:42.200
at the water plant right now,

20:42.200 --> 20:45.560
they actually lost garage spaces

20:45.560 --> 20:49.240
as part of that construction project.

20:49.240 --> 20:52.120
They're in desperate need of room for equipment,

20:52.120 --> 20:53.680
materials, et cetera.

20:54.560 --> 20:56.680
And again, that booster station,

20:56.680 --> 20:59.760
this water main and that distribution facility,

20:59.760 --> 21:02.320
are projects that are in the TID project plan

21:02.320 --> 21:04.440
and will be funded through the TID.

21:05.520 --> 21:08.920
So understood that the city is still looking at

21:08.920 --> 21:12.160
high level options as to whether or not

21:12.160 --> 21:14.880
it makes sense to put that station at this site

21:14.880 --> 21:17.400
or consolidated at a different site

21:17.400 --> 21:19.240
apart from the booster station.

21:21.840 --> 21:23.040
The purpose of the project,

21:23.040 --> 21:25.600
this booster station pressurizes the high zone.

21:25.600 --> 21:29.920
So if you take a look at this upper middle graphic right here,

21:29.920 --> 21:34.200
this graphic is covered colored by the different pressure zones.

21:34.200 --> 21:36.920
The water plant pumps into the main zone,

21:36.920 --> 21:41.320
which is shaded in purple and then booster pumps

21:41.320 --> 21:45.320
pressurized that to even a higher hydraulic grade

21:45.320 --> 21:48.920
up to the green area, which is the high zone.

21:48.920 --> 21:52.560
And TID 5 is indeed in that high pressure zone.

21:52.560 --> 21:55.240
At project completion, that zone will be pressurized

21:55.240 --> 21:58.720
by dedicated pumps at the water plant

21:58.720 --> 22:00.560
and a dedicated transmission main

22:00.560 --> 22:02.600
that currently pump up there.

22:02.600 --> 22:04.760
And then this booster station will provide

22:04.760 --> 22:08.040
the required redundancy to work together

22:08.040 --> 22:10.560
with the pumps at the plant to make sure

22:10.560 --> 22:14.240
that zone is constantly pressurized.

22:14.240 --> 22:18.800
For project schedule, we expect design to start yet this year.

22:18.800 --> 22:21.720
Bidding would take place in 2027.

22:21.760 --> 22:25.360
We're anticipating approximately the third quarter.

22:25.360 --> 22:28.520
We understand due to the existing or past failure

22:28.520 --> 22:30.640
at the Oakland station, that booster station

22:30.640 --> 22:32.640
is kind of a critical need.

22:32.640 --> 22:35.520
We still have to go through public service commission approval

22:35.520 --> 22:38.320
on the project, things of that nature

22:38.320 --> 22:41.320
because we're talking about process and controls equipment.

22:41.320 --> 22:45.480
Some of those things require a more involved design

22:45.480 --> 22:47.000
and have longer lead times.

22:47.000 --> 22:50.240
And that's why you see kind of a schedule here

22:50.240 --> 22:53.520
with design taking approximately nine months

22:53.520 --> 22:58.040
and then construction starting by fourth quarter of next year

22:58.040 --> 23:00.760
and going all the way through 2028.

23:04.120 --> 23:05.440
That was a lot.

23:05.440 --> 23:06.440
Take a break here.

23:07.440 --> 23:09.560
Valley Creek restoration.

23:09.560 --> 23:12.520
So I know that Rob has been in front of the board

23:12.520 --> 23:15.760
in the past talking about this project as well.

23:15.760 --> 23:17.760
The scope is stream restoration

23:17.760 --> 23:20.440
and the overall Valley Creek restoration plan

23:20.440 --> 23:22.040
is shown in this map here.

23:23.000 --> 23:25.880
In the bar chart across the top,

23:25.880 --> 23:29.800
we're showing that Valley Creek has been under design.

23:30.760 --> 23:35.320
The city has partial funds for this project

23:35.320 --> 23:38.000
are identified in the TID project plan

23:38.000 --> 23:41.480
and they understand the city's expecting to hear back

23:41.480 --> 23:44.880
whether or not a grant application was successful.

23:44.880 --> 23:47.640
They're expecting to hear back on that in October.

23:47.640 --> 23:52.560
That funding will help to kind of dictate the schedule here

23:52.560 --> 23:55.360
and that's why we're just showing this phased over

23:55.360 --> 23:59.800
potentially several years depending on how the funding works out.

23:59.800 --> 24:03.280
So there will have to be, I'm sure more updates

24:03.280 --> 24:04.920
on this project will be forthcoming

24:04.920 --> 24:09.960
once the funding is understood better.

24:09.960 --> 24:12.800
The purpose of this and why it's in the TID project plan

24:12.800 --> 24:17.480
is it provides resiliency down at the treatment plant sites

24:17.720 --> 24:19.720
obviously the wastewater plant and water plants

24:19.720 --> 24:20.800
are right next to each other

24:20.800 --> 24:23.720
and they've experienced flooding in the past

24:23.720 --> 24:25.520
associated with Valley Creek.

24:27.040 --> 24:29.720
Key consideration here is that coordination

24:29.720 --> 24:32.240
between the design team that's working on this

24:32.240 --> 24:35.520
which is Stantec and then both Strand and Kapoor

24:35.520 --> 24:40.520
is ongoing as the interceptor relay projects

24:42.400 --> 24:44.680
kind of are in a shared corridor with this.

24:44.680 --> 24:46.200
So just know that we've already had

24:46.200 --> 24:50.200
some coordination meetings to try to optimize

24:50.200 --> 24:53.080
the design between all the teams working in this corridor.

24:55.120 --> 24:57.600
I'm gonna tee up the Jackson Interceptor project

24:57.600 --> 25:02.160
and maybe ask Erin to chime in on this one a little bit.

25:02.160 --> 25:04.520
So to get oriented with where we are on the map here

25:04.520 --> 25:08.120
you can see the wastewater treatment plant is up here.

25:08.120 --> 25:11.160
The Jackson Street Interceptor has experienced

25:11.160 --> 25:14.040
charging in the past during wet weather events

25:15.040 --> 25:18.480
where the manholes kind of back up

25:18.480 --> 25:22.600
and the pipes don't have adequate carrying capacity.

25:22.600 --> 25:26.280
It's in the TID project plan to upsize this interceptor

25:26.280 --> 25:29.240
in order to provide some wet weather relief

25:29.240 --> 25:33.840
just to make sure that those surcharging issues

25:33.840 --> 25:37.080
are not exacerbated by any of the additional flows

25:37.080 --> 25:39.720
that may be coming into the plant

25:39.720 --> 25:42.160
as the result of all of the development

25:42.240 --> 25:44.600
in the TID 5 area.

25:46.440 --> 25:49.680
The schedule on this is that Kapoor has already surveyed

25:49.680 --> 25:51.720
this and has designed ongoing.

25:52.560 --> 25:55.800
We're looking at a 2028 construction year

25:55.800 --> 25:58.880
and that was selected kind of in coordination

25:58.880 --> 26:03.880
with Roger and Rob to be cognizant of other city projects

26:04.760 --> 26:08.160
that are already planned for 2027 and 2029.

26:08.160 --> 26:11.600
28 was the best year that was identified for this.

26:13.160 --> 26:15.160
And I guess with that Erin, did you want to talk

26:15.160 --> 26:18.080
any project stats or specifics?

26:20.320 --> 26:22.960
Really the only update that I have is that survey

26:22.960 --> 26:26.520
is mostly complete.

26:26.520 --> 26:29.560
We will be starting design here very shortly.

26:31.120 --> 26:34.520
And beyond that, I think Ben covered everything else.

26:34.520 --> 26:35.360
Thanks.

26:35.360 --> 26:36.360
All right, great.

26:37.200 --> 26:43.200
And then that kind of ties into the sanitary interceptor

26:43.200 --> 26:44.720
up sizing.

26:44.720 --> 26:47.800
If we look at this map, the black lines up here

26:47.800 --> 26:51.080
actually the projects that were completed earlier this year

26:51.080 --> 26:54.560
that the city took on over this last winter.

26:54.560 --> 26:58.160
And that was the initial sanitary and water utility

26:58.160 --> 27:01.080
extensions to the southern point of connection

27:01.960 --> 27:06.960
to the vantage development area.

27:07.680 --> 27:12.000
So what we identified is the need to upsize

27:12.000 --> 27:15.640
a couple of the portions going all the way

27:15.640 --> 27:17.280
from Terrace Drive all the way down

27:17.280 --> 27:20.640
to the wastewater treatment plant.

27:20.640 --> 27:24.400
Now this is broken into three separate phases.

27:25.240 --> 27:28.600
Phase one is, well, they're ordered here

27:28.640 --> 27:30.120
by construction year.

27:30.120 --> 27:33.720
Phase one is project 27-1.

27:33.720 --> 27:35.360
That's the furthest downstream,

27:35.360 --> 27:38.680
and we need to upsize that add capacity.

27:38.680 --> 27:43.680
We're actually splitting that 27-1 into two sub phases,

27:44.680 --> 27:48.280
A, which is actually on the grounds of the wastewater plants

27:48.280 --> 27:52.480
and B, which kind of follows the Valley Creek corridor

27:52.480 --> 27:53.520
and goes up a little bit.

27:53.520 --> 27:57.120
That'll include up sizing sewers

27:57.120 --> 28:01.120
to both 30 and 36-inch respectively.

28:02.000 --> 28:07.000
And 28-2 is the second piece that runs,

28:10.440 --> 28:12.880
forgive me, I'm blanking on the cross street here,

28:12.880 --> 28:15.480
but runs all the way up to Terrace Drive

28:15.480 --> 28:20.120
to the LL area, hails trail, thank you.

28:21.000 --> 28:26.000
That includes a little over 4,000 feet of 20-inch,

28:26.280 --> 28:28.680
21-inch diameter sewer.

28:28.680 --> 28:31.280
And then 30-1 is the middle piece,

28:31.280 --> 28:35.280
and we're saying that we're only gonna touch that if needed.

28:35.280 --> 28:38.120
And the background on that is,

28:40.440 --> 28:45.040
we included that in the TID project plan to be conservative,

28:45.040 --> 28:47.440
but that middle piece that 30-1

28:47.480 --> 28:50.280
is already 21-inches in diameter.

28:50.280 --> 28:52.480
And so when we've done our updated planning

28:52.480 --> 28:55.240
since that TID project plan was approved,

28:55.240 --> 28:58.400
we identified this needs to be 21-inch all the way down

28:58.400 --> 29:03.400
to here where it needs to get upsized to 30-36,

29:05.360 --> 29:07.920
accordingly, as you get closer to the plant.

29:07.920 --> 29:12.520
So upon further analysis, this one is in good shape

29:12.520 --> 29:15.640
for the flows in that planning area.

29:15.640 --> 29:18.680
So that's why on the bar chart at the top there,

29:18.680 --> 29:22.160
that 30-1, that middle portion is pushed all the way out

29:22.160 --> 29:23.800
on the schedule.

29:23.800 --> 29:26.200
It's actually more likely at this point

29:26.200 --> 29:28.300
that that project is not needed at all.

29:33.040 --> 29:38.040
Schedule on this, 27-1 is the most important piece.

29:38.200 --> 29:43.200
Design, Kapoor is designing this 27-1B.

29:44.200 --> 29:46.400
They've already started on that.

29:46.400 --> 29:48.680
Stream needs authorization from the board,

29:48.680 --> 29:51.120
which we'll be approaching you with next month

29:51.120 --> 29:54.040
to do the furthest downstream on the grounds

29:54.040 --> 29:55.920
of the wastewater plant.

29:55.920 --> 29:59.800
We'll need to get started on that next month.

30:03.440 --> 30:04.880
That's it for the interceptor.

30:06.200 --> 30:10.000
Utility looping projects, these are all clumped together.

30:10.000 --> 30:13.120
And as I stated earlier in the presentation,

30:13.120 --> 30:15.400
these are the projects that kind of complete

30:15.400 --> 30:16.400
this overall loop.

30:16.400 --> 30:21.400
So 26-1 and 26-2 loop the site on the west side

30:22.320 --> 30:24.800
all the way up to the northern point of connection

30:24.800 --> 30:28.320
to the existing vantage construction area.

30:29.720 --> 30:32.440
These last remaining projects would loop water

30:32.440 --> 30:35.480
and sewer up on the east side

30:35.480 --> 30:39.720
and also extend sanitary service on the west side

30:39.720 --> 30:42.920
within the Canalsville obligation areas.

30:42.920 --> 30:45.240
Again, we're pushing those out a little bit yet,

30:45.240 --> 30:49.720
just waiting to see how exactly things develop

30:49.720 --> 30:54.240
and allow for kind of sewer pack and DNR input

30:54.240 --> 30:58.240
on finalizing the service area plans

30:58.240 --> 31:01.120
before we get too far down the line with those.

31:06.520 --> 31:09.240
I believe that's all I need to say about those projects

31:09.240 --> 31:11.240
unless you have anything to add, Aaron.

31:12.240 --> 31:14.120
All right, so in summary,

31:16.200 --> 31:19.120
specific city-led projects are being refined

31:19.120 --> 31:21.280
and are becoming actionable.

31:21.280 --> 31:23.920
You're gonna see Aaron back next month,

31:23.920 --> 31:27.040
hopefully with a recommendation on awarding 26-1

31:27.040 --> 31:31.120
and 26-2 strand, we'll have some contracts

31:31.120 --> 31:33.920
coming before the board also in October

31:33.920 --> 31:35.380
and potentially November.

31:36.480 --> 31:40.400
Approximately $100 million in city-led TID-5 projects

31:40.400 --> 31:43.040
are planned over the next five years.

31:44.160 --> 31:47.440
Financing again is by the developer.

31:47.440 --> 31:49.600
Extensive project coordination is ongoing

31:49.600 --> 31:53.640
between the different projects and the project teams.

31:53.640 --> 31:55.520
The governments and departments involved

31:55.520 --> 31:58.280
as well as the community and the organizations

31:58.280 --> 32:02.120
and this overall plan's gonna continue to be revised

32:02.120 --> 32:05.920
as we work through the plan and specific projects.

32:06.920 --> 32:10.960
With that, all that's left is to open it up to questions,

32:10.960 --> 32:14.160
but as stated, I just wanted to put this overall schedule

32:14.160 --> 32:17.280
back in front of you and that you have a little background

32:17.280 --> 32:19.400
on each of these projects and can again,

32:19.400 --> 32:23.760
try to digest how these all kind of align together.

32:26.160 --> 32:27.680
We'll take any questions?

32:30.120 --> 32:31.280
Go ahead.

32:31.280 --> 32:33.960
Can we go back to 26-3 for a minute?

32:33.960 --> 32:35.280
Got a couple questions.

32:38.960 --> 32:42.040
Let's see, we've got 26-1 and 26-2

32:44.520 --> 32:47.840
and then we've got 27-2 is the county A-H,

32:47.840 --> 32:49.520
I'm sorry, the county A-H project.

32:49.520 --> 32:53.440
What is the project where you the Oakland Avenue?

32:53.440 --> 32:56.760
Oh, the booster station, 27-3, sure.

32:56.760 --> 32:57.720
Oh, it's 27-3, okay.

32:57.720 --> 32:58.800
Yep.

32:58.800 --> 33:02.640
So that yellow section that goes across the railroad tracks,

33:02.640 --> 33:04.760
is that kind of where we're moving at North

33:04.760 --> 33:06.800
because we keep hitting obstructions?

33:06.800 --> 33:08.120
Is that what that plan is?

33:09.120 --> 33:12.200
Yeah, I'll just say that all that is

33:13.400 --> 33:15.720
entirely different projects.

33:16.760 --> 33:18.920
It's in the same vicinity, but that yellow section

33:18.920 --> 33:20.840
is entirely on Oakland Avenue.

33:20.840 --> 33:23.520
It does have to cross our need to railroad tracks again.

33:25.120 --> 33:27.320
But that's water, the other project is sewer.

33:27.320 --> 33:28.240
Oh, I see, okay.

33:29.240 --> 33:33.040
So with the areas where it goes along the street,

33:33.040 --> 33:36.000
will the street be ripped up for a few months

33:36.000 --> 33:37.520
when we get to that?

33:37.520 --> 33:39.880
Yeah, that's actually a great question.

33:39.880 --> 33:43.080
What we've planned is areas of the street

33:43.080 --> 33:46.160
that are in good shape and are okay

33:46.160 --> 33:49.880
with just like your standard utility trench patch,

33:49.880 --> 33:52.520
fine, that'll probably be the approach.

33:52.520 --> 33:55.600
But a lot of these streets actually aren't in good enough

33:55.640 --> 33:58.680
shape that a trench patch would make sense.

33:58.680 --> 34:02.000
So in those cases, it's gonna be a full reconstruct

34:02.000 --> 34:04.200
of the road surface also.

34:04.200 --> 34:07.240
And then that would be scheduled to coincide

34:07.240 --> 34:08.880
with the lead line replacements

34:08.880 --> 34:09.960
when the street gets ripped down.

34:09.960 --> 34:10.800
Correct.

34:10.800 --> 34:14.240
When we're doing the water means, Dan already has

34:14.240 --> 34:16.800
an inventory of the lead service laterals

34:16.800 --> 34:20.800
and anywhere we encounter those, those will be replaced.

34:21.720 --> 34:22.560
Thank you.

34:22.560 --> 34:23.400
Yep, for sure.

34:24.400 --> 34:27.160
So just that, that's not probably be about

34:27.160 --> 34:31.280
six, seven months of construction in that area.

34:31.280 --> 34:33.240
Yep, road's torn up.

34:33.240 --> 34:36.160
So expect it to be a whole summer when we get there.

34:37.800 --> 34:40.080
So I don't know if you know this number

34:40.080 --> 34:41.880
any of the city employees know this number,

34:41.880 --> 34:46.120
but how many customers, commercial or residential,

34:46.120 --> 34:50.600
will we have in that small little blue silver strip on LL

34:51.600 --> 34:54.440
that runs, I mean, I know pliers is there

34:54.440 --> 34:57.160
in the town of Port, but are there any other

35:00.360 --> 35:03.240
homes or businesses along that route?

35:03.240 --> 35:07.200
Yeah, it's a great question on this little blue strip

35:07.200 --> 35:10.040
over here, right now there's only approximately

35:10.040 --> 35:12.560
four rooftops, I would say.

35:13.560 --> 35:15.680
It's agricultural.

35:15.680 --> 35:19.640
It's one of the reasons, you know, the city is obligated

35:19.640 --> 35:21.880
to provide utility service, and I know there's

35:21.880 --> 35:24.600
an agreement kind of ongoing, but we've won

35:24.600 --> 35:29.560
to at least delay and take into consideration

35:29.560 --> 35:32.800
will there be more users or more connections

35:32.800 --> 35:35.440
kind of on this corner before really starting

35:35.440 --> 35:37.960
to put this portion in.

35:37.960 --> 35:42.960
Okay, and then I'm sorry, it's in the same area,

35:43.440 --> 35:45.840
this utility looping project.

35:45.880 --> 35:49.960
So the light blue and or the dark blue,

35:49.960 --> 35:53.680
is any of that like redundancy or is that like,

35:53.680 --> 35:58.240
makes it supercharged or am I not getting it completely?

35:58.240 --> 36:02.520
No, actually you're asking a really great question here

36:02.520 --> 36:05.640
because I'm just gonna say the light blue projects

36:05.640 --> 36:08.760
which are labeled over here, that's just,

36:08.760 --> 36:11.440
they kind of go to here on LL.

36:11.440 --> 36:14.960
The dark blue project is just sanitary sewer

36:15.520 --> 36:18.800
and the sole purpose of that is to be able to serve

36:19.800 --> 36:22.800
the rest of the Canalsville obligation area here.

36:22.800 --> 36:23.880
Okay.

36:23.880 --> 36:27.600
And then the brown project just kind of completes

36:27.600 --> 36:32.600
this northeast corner to make the water main loop.

36:34.080 --> 36:39.080
So without this project, the water main

36:40.000 --> 36:42.040
the water main's will be able to serve

36:42.040 --> 36:47.040
the current advantage development area adequately.

36:47.560 --> 36:51.600
This looping adds redundancy that somewhere down the line

36:51.600 --> 36:53.280
if this water main is out of service

36:53.280 --> 36:56.720
or there's water main break as things age or whatever

36:56.720 --> 36:58.840
then there's another loop.

36:58.840 --> 36:59.680
Okay.

37:02.080 --> 37:04.120
And it also makes it more expandable.

37:04.960 --> 37:06.440
Yes.

37:06.440 --> 37:10.840
So within TID-5, all of the pink lands are also in TID-5.

37:10.840 --> 37:15.280
There is, there has not been any specific site development

37:15.280 --> 37:17.000
proposal for that.

37:17.960 --> 37:22.960
But yeah, that's another good point is that

37:23.280 --> 37:25.640
and why we're kind of delaying these projects

37:25.640 --> 37:29.760
is depending on how the pink lands develop,

37:29.760 --> 37:33.680
it might be better, more strategic to expand sewer over here

37:33.680 --> 37:35.600
or sewer over here.

37:35.600 --> 37:37.720
Maybe it still makes sense to do both.

37:37.720 --> 37:39.360
It all kind of depends, but.

37:39.360 --> 37:41.560
Oh, that date might change depending on.

37:41.560 --> 37:42.880
Correct.

37:42.880 --> 37:44.000
Whatever is other.

37:44.000 --> 37:44.840
Yep.

37:44.840 --> 37:45.680
Thank you.

37:45.680 --> 37:46.520
Yep.

37:50.600 --> 37:52.720
Any other questions, comments?

37:54.160 --> 37:55.400
Well, thank you.

37:55.400 --> 37:57.240
Yes, absolutely.

37:57.240 --> 38:00.880
We'll be doing it again at the council meeting on the 15th.

38:00.880 --> 38:01.720
Cool.

38:04.680 --> 38:08.840
Moving on to agenda item number five,

38:08.840 --> 38:12.560
consideration and possible action on water treatment plant

38:12.560 --> 38:16.080
change order number seven to improve the east path

38:16.080 --> 38:17.880
behind the water treatment plant

38:17.880 --> 38:22.240
with concrete paving, a ramp and storm water drainage.

38:23.200 --> 38:24.040
Dan.

38:34.640 --> 38:35.480
Sure.

39:02.040 --> 39:02.880
Okay.

39:03.680 --> 39:08.680
So I'm just going to have some pictures in the background, but I'll start talking first.

39:08.680 --> 39:15.680
The East Path Project has been on our list for improvement since the treatment plant project started.

39:15.680 --> 39:24.680
Unfortunately, we had a rough start with some of the unknowns which caused a lot of the change orders before this one.

39:24.680 --> 39:32.680
It was unknown if we were going to have enough time or funds available to plan and complete a project like this.

39:32.680 --> 39:40.680
So what we did is we put it on our 10-year CIP, identified it as a project that we wanted to do,

39:40.680 --> 39:47.680
and basically had a placeholder in case we were unable to complete this as part of this project.

39:47.680 --> 39:56.680
With our current schedule, we are showing in two weeks from now we're going to do our last underground work

39:56.680 --> 39:59.680
behind the building on the east side of the property.

39:59.680 --> 40:06.680
So this created an opportunity for this project to be completed before winter.

40:06.680 --> 40:14.680
So we asked SCH and CD Smith to design and give a surprise for completing a project like this.

40:14.680 --> 40:24.680
I just want to say that so this project is not only for utility needs,

40:24.680 --> 40:33.680
but it's also to kind of bring back the popular destination that this area was before the project started.

40:33.680 --> 40:44.680
It's been two years now since this path has been closed and we're looking at another eight months potentially if nothing is done now.

40:44.680 --> 40:53.680
We have had many surrounding citizens and residents reach out and ask when the path was going to be completed.

40:53.680 --> 41:01.680
Or what's going to happen with it and concerned about security of with the fencing around and not being able to access

41:01.680 --> 41:07.680
between the park and the south side of where the lighthouse is and everything.

41:07.680 --> 41:19.680
So restoring this path, gaining access and I guess making it more safe for customers and residences.

41:19.680 --> 41:22.680
Another big deal for us.

41:22.680 --> 41:26.680
So we want to move on with this.

41:26.680 --> 41:31.680
So I want to just show some pictures. This is kind of the before of what the path looked like.

41:31.680 --> 41:43.680
You can see basically what they did in the past is they put grass and topsoil right up to the building wall.

41:43.680 --> 41:47.680
When they redid the plant in the 90s and they put this EFS finish on the plant.

41:47.680 --> 41:54.680
So what that grass did is actually destroyed all of the EFS that it is touching right now.

41:54.680 --> 42:03.680
So when we had to remove all of this to do some of the underground work in the back, we also had to replace all the EFS along here.

42:03.680 --> 42:10.680
These are the two pump rooms, the current pump room plant one and plant two.

42:10.680 --> 42:18.680
And this is kind of looking to the north that larger grassy area is the plant to clear well.

42:18.680 --> 42:24.680
So the more flat area is actually an underground tank.

42:24.680 --> 42:30.680
And then this is kind of just looking at it to the south. So this is standing in the park looking south.

42:30.680 --> 42:39.680
A lot of the say brush bushes you see those are kind of just overgrown bushes that were allowed to grow.

42:39.680 --> 42:42.680
That has since been removed with the project.

42:42.680 --> 42:50.680
So this is just an overview of what it kind of looks like right now.

42:50.680 --> 42:55.680
And then I'll get to the rendering here. So this is what we're looking to do.

42:55.680 --> 42:58.680
This is from the south side looking north.

42:59.680 --> 43:12.680
You'll see the very south portion of the building. That's the new clear well tank and then pump room right to the west of the tank is a ramp.

43:12.680 --> 43:18.680
So that ramp leads to a new pump room door. The original plan had just a stoop with staircase.

43:18.680 --> 43:24.680
But the tank would have needed extra cover along the footing.

43:24.680 --> 43:38.680
So we would have had to have gone back to this type of look to get that extra weight over the footing.

43:38.680 --> 43:44.680
If we didn't decide to put a ramp there.

43:44.680 --> 43:53.680
So the ramp also gives us access. You can kind of see the the white door where I was showing the pointer.

43:53.680 --> 44:00.680
It gives us access to the new pump room. Right. Thanks. So, yeah.

44:00.680 --> 44:03.680
Okay. So right here is the new pump room door.

44:03.680 --> 44:09.680
And then the ramp gives us access to get in that door.

44:09.680 --> 44:16.680
Otherwise we're having to go upstairs and we have to bring in service trucks and potentially cranes to pull up pumps and stuff.

44:16.680 --> 44:22.680
So this makes access a lot better.

44:22.680 --> 44:26.680
This is from the north looking south.

44:26.680 --> 44:29.680
I'm just actually going to go back to this first slide. So.

44:29.680 --> 44:32.680
Right here, these are.

44:32.680 --> 44:37.680
Kind of bump outs, but they're actually our two shore well tanks.

44:37.680 --> 44:45.680
So the plan would be to actually have a curb go north south in front of the tanks.

44:45.680 --> 44:48.680
So it's kind of not exactly how it would be.

44:48.680 --> 44:54.680
But we want to we have to access those tanks with large vehicles and.

44:54.680 --> 44:59.680
Our large jet truck every couple of years. We actually sent a diver into these tanks to clean them.

44:59.680 --> 45:06.680
So currently before this project, it was kind of logistic nightmare to get bigger equipment back there.

45:06.680 --> 45:11.680
So making this path concrete and widening it.

45:11.680 --> 45:15.680
Not only gives us better access to inside the facility, it's a better access to the.

45:16.680 --> 45:18.680
The actual shore wells.

45:18.680 --> 45:22.680
So that's the utility need of this.

45:22.680 --> 45:25.680
If we.

45:25.680 --> 45:30.680
Continue on to the north, like I said, this is the current clear well.

45:30.680 --> 45:36.680
The plan would be to get rid of the soil that's on it right now and push the path to the west.

45:36.680 --> 45:42.680
So we would have an exposed tank wall just like we do in many other spots throughout the building.

45:42.680 --> 45:48.680
And then the path would hug the wall and we would open up more green space to the east.

45:48.680 --> 45:50.680
So all of this space over here.

45:50.680 --> 45:54.680
Would be approximately 20 22 feet wide.

45:54.680 --> 45:57.680
We're now in spaces. It's maybe eight feet.

45:57.680 --> 46:02.680
So this gives us potential for future bench spots picnic table spots.

46:02.680 --> 46:09.680
If you guys remember the south side of the property had was all grass and some trees and we had a couple of picnic tables and.

46:09.680 --> 46:14.680
Quite a few people throughout the seasons came and sat there and enjoyed the time.

46:14.680 --> 46:19.680
So we want to open up the view again and make it more accessible for.

46:19.680 --> 46:26.680
Residents and visitors to enjoy the beautiful view that's right there.

46:26.680 --> 46:29.680
Part of the cost.

46:29.680 --> 46:31.680
So.

46:31.680 --> 46:36.680
The ramp up I go back.

46:36.680 --> 46:45.680
The ramp was about 32,000 of this cost was to build this ramp.

46:45.680 --> 46:51.680
And then it was about 80,000 to do the utility portion of the concrete path.

46:51.680 --> 47:00.680
And then an additional about 27,000 to do the extended footage to get us to.

47:00.680 --> 47:05.680
The north portion of this property where the water treatment plant meets the park.

47:05.680 --> 47:10.680
It was brought up.

47:10.680 --> 47:14.680
What would the cost be if we did this at a future date?

47:14.680 --> 47:18.680
Are we reached out to CD Smith and they said that.

47:18.680 --> 47:25.680
Next year they're they're anticipating maybe a 15 to 18% increase on the construction costs and materials with.

47:25.680 --> 47:29.680
The high construction demand as you just heard.

47:29.680 --> 47:30.680
So.

47:30.680 --> 47:35.680
Doing this project now not only gets us to a faster.

47:35.680 --> 47:38.680
Opening but then also.

47:38.680 --> 47:43.680
If we choose to do this saves us money by waiting to do it in the future.

47:43.680 --> 47:46.680
Any questions?

47:46.680 --> 47:47.680
Of course.

47:47.680 --> 47:48.680
Yeah.

47:48.680 --> 47:52.680
So I just thought of this now and I apologize for not bringing it up earlier.

47:53.680 --> 47:54.680
But.

47:54.680 --> 47:56.680
The Cedar Creek Valley project.

47:56.680 --> 48:00.680
One of the things at the very end will have a bridge.

48:00.680 --> 48:03.680
Where the creek's going to flow into the.

48:03.680 --> 48:08.680
How will that work with this new project.

48:08.680 --> 48:11.680
Or do we have have we thought about that.

48:11.680 --> 48:13.680
So it's.

48:13.680 --> 48:16.680
Kind of hard to see but the outfall is right here.

48:16.680 --> 48:17.680
Yeah.

48:17.680 --> 48:19.680
So it's kind of like at the end there.

48:20.680 --> 48:22.680
So this very last pipe.

48:22.680 --> 48:23.680
Yeah.

48:23.680 --> 48:26.680
That would be the end of the path which there's already kind of a break there anyway.

48:26.680 --> 48:27.680
Okay.

48:27.680 --> 48:28.680
So that.

48:28.680 --> 48:31.680
Kind of would be the start of that.

48:31.680 --> 48:32.680
That other.

48:32.680 --> 48:35.680
We wouldn't be laying down concrete just to pull it up later.

48:35.680 --> 48:36.680
Correct.

48:36.680 --> 48:37.680
Thank you.

48:41.680 --> 48:44.680
Continuing north of that bridge then is there.

48:45.680 --> 48:50.680
To replace the asphalt behind the Yacht Club to the wastewater.

48:50.680 --> 48:53.680
Concrete because there's kind of that section of ready asphalt.

48:53.680 --> 48:54.680
Yeah.

48:54.680 --> 48:56.680
I think that would be that would tie into the.

48:56.680 --> 48:58.680
The Valley Creek project is.

48:58.680 --> 49:01.680
Replacing that final footage.

49:01.680 --> 49:03.680
Of that section.

49:03.680 --> 49:04.680
Yeah.

49:04.680 --> 49:08.680
So with the budget you said 80,000 is the.

49:08.680 --> 49:12.680
The tanks and the infrastructure is does that need to happen right now.

49:12.680 --> 49:17.680
Regardless or is that part of the original plan was to just.

49:17.680 --> 49:21.680
Replace the asphalt and put back top soil.

49:21.680 --> 49:25.680
So there's about 10,000 in the project.

49:25.680 --> 49:27.680
So we'd actually have a 10,000 credit.

49:27.680 --> 49:30.680
If we did this that would go towards this price.

49:30.680 --> 49:34.680
But there is money in the budget to just put the asphalt back.

49:34.680 --> 49:37.680
And then put the soil back where it was.

49:38.680 --> 49:42.680
Also with that the path itself right now.

49:42.680 --> 49:44.680
Like to the north here.

49:44.680 --> 49:46.680
It's barely 10 feet wide.

49:46.680 --> 49:49.680
So we're adding another four to six feet.

49:49.680 --> 49:51.680
So if.

49:51.680 --> 49:56.680
If there were to be some sort of emergency in the park or the Yacht Club.

49:56.680 --> 50:00.680
It's pretty impossible to get a fire truck back there right now.

50:00.680 --> 50:03.680
Or any ambulance would fit, but it'd be pretty tight.

50:04.680 --> 50:08.680
Can you go back to the rendering slide.

50:08.680 --> 50:14.680
Maybe the one with the view from the north.

50:14.680 --> 50:15.680
Yeah.

50:15.680 --> 50:18.680
So it's 20 feet between the rocks and the.

50:18.680 --> 50:21.680
East edge of the concrete there.

50:21.680 --> 50:22.680
Yeah.

50:22.680 --> 50:24.680
With this were to be 16 feet.

50:24.680 --> 50:29.680
We could even take this and take it down to 14 to give two more feet here.

50:30.680 --> 50:34.680
If you remember being down here, this is a pretty steep.

50:34.680 --> 50:37.680
Decline from the the rock wall.

50:37.680 --> 50:42.680
So this curb that would go north south would actually be 12 inches.

50:42.680 --> 50:46.680
So we're going to gain a little bit elevation where we'll try to level this.

50:46.680 --> 50:49.680
Grassy air out as best as we can with that extra footage.

50:49.680 --> 50:51.680
We'll be able to make it a little.

50:51.680 --> 50:52.680
Yeah.

50:52.680 --> 50:56.680
So the rendering is a little deceiving because the grade actually comes down.

50:57.680 --> 50:58.680
Yeah.

50:58.680 --> 51:00.680
To that path rather than being flat across there.

51:00.680 --> 51:06.680
And then there's a storm, a catch basin on the south end of the walk to.

51:06.680 --> 51:07.680
Yeah.

51:07.680 --> 51:12.680
So not shown, but right about in, in this area, we'd have a catch basin and it'd connect

51:12.680 --> 51:16.680
into a storm catch basin right here.

51:16.680 --> 51:19.680
So we'd be able to take most of the pass flow.

51:19.680 --> 51:23.680
Catch it and then, you know, put it into our sewers.

51:23.680 --> 51:26.680
Right now, we'll pre project.

51:26.680 --> 51:31.680
It was pretty icy back there during winter.

51:31.680 --> 51:37.680
So that curb is going to extend past those kind of half circle concrete areas where the

51:37.680 --> 51:38.680
benches are.

51:38.680 --> 51:39.680
Yeah.

51:39.680 --> 51:40.680
It'll be a step there.

51:40.680 --> 51:41.680
And how, how high did you say that was?

51:41.680 --> 51:44.680
12 inches, 12 inches.

51:44.680 --> 51:49.680
And we have a, there's an electrical transfer box right here too.

51:49.680 --> 51:52.680
That's not shown, but that would be protected by the curb too then.

51:53.680 --> 52:00.680
Will there be breaks in that curb every so often to allow access onto the green space?

52:00.680 --> 52:01.680
Yeah.

52:01.680 --> 52:02.680
Good question.

52:02.680 --> 52:04.680
So we were anticipating.

52:04.680 --> 52:10.680
Two or three spots on the north side more, kind of away from our working area that we

52:10.680 --> 52:13.680
would do stairs into the area.

52:13.680 --> 52:20.680
So that's built into this quote too.

52:21.680 --> 52:22.680
Well, I think it looks great.

52:22.680 --> 52:25.680
I'm thrilled to have a path back.

52:25.680 --> 52:26.680
Yeah.

52:26.680 --> 52:30.680
Any other questions or.

52:30.680 --> 52:35.680
How long do you think the project will take and like what's the, what's the, is there any

52:35.680 --> 52:39.680
risk with lead times and parts or anything that gets started yet this year?

52:39.680 --> 52:41.680
Luckily most of it is concrete.

52:41.680 --> 52:47.680
The only lead time issue might be a getting the storm catch basin.

52:48.680 --> 52:51.680
But there's plenty to do for CD Smith in the meantime.

52:51.680 --> 52:59.680
So if the underground work is slated to start September 21st, if that takes two weeks or

52:59.680 --> 53:08.680
one to two weeks, CD Smith would basically start immediately going into this project with hopefully

53:08.680 --> 53:10.680
completing it by the end of fall.

53:10.680 --> 53:13.680
It should be pretty easy to get down to further ground freezes.

53:13.680 --> 53:14.680
Yep.

53:15.680 --> 53:20.680
And avoiding any winter concrete costs.

53:20.680 --> 53:21.680
One last question.

53:21.680 --> 53:25.680
So I can't tell by the existing site.

53:25.680 --> 53:28.680
Are there trees there or would trees have to be planted?

53:28.680 --> 53:31.680
There's currently no trees and there, there wasn't any trees.

53:31.680 --> 53:32.680
Any kind of like.

53:32.680 --> 53:33.680
Shade.

53:33.680 --> 53:34.680
Any kind.

53:34.680 --> 53:38.680
We could try to add trees more to the north area.

53:38.680 --> 53:40.680
But again, this is a rock wall.

53:40.680 --> 53:45.680
So the rocks, although you see them here, they do extend to the west.

53:45.680 --> 53:50.680
So we'd have to pick the right kind of tree to.

53:50.680 --> 53:55.680
Our wastewater treatment plant outfall runs down that path too.

53:55.680 --> 53:57.680
So we can be cognizant of that.

53:57.680 --> 53:58.680
Okay.

53:58.680 --> 54:02.680
But we could do we approve those paths in the front.

54:02.680 --> 54:06.680
It could be something similar maybe later on down the road.

54:06.680 --> 54:07.680
Yeah.

54:07.680 --> 54:08.680
Absolutely.

54:09.680 --> 54:18.680
How many benches do you actually anticipate being along there?

54:18.680 --> 54:19.680
That depends.

54:19.680 --> 54:23.680
I don't know our bench policy here.

54:23.680 --> 54:27.680
I was I was anticipating to.

54:28.680 --> 54:30.680
I was thinking about the.

54:30.680 --> 54:32.680
Picking table areas.

54:32.680 --> 54:36.680
You know, with hopefully shade in the future and then benches between.

54:36.680 --> 54:40.680
So I would say at least for benches.

54:40.680 --> 54:48.680
It's a it's a large area.

54:48.680 --> 54:49.680
Okay.

54:49.680 --> 54:52.680
Only ask because the rendering looks really nice.

54:52.680 --> 54:53.680
Yeah.

54:54.680 --> 54:55.680
Yep.

54:55.680 --> 54:57.680
That's the goal.

54:57.680 --> 54:59.680
Any more questions?

54:59.680 --> 55:01.680
Just just one.

55:01.680 --> 55:05.680
Would this be considered under park and rec then as part of the park?

55:05.680 --> 55:08.680
Or is it going to be part of the water treatment?

55:08.680 --> 55:09.680
This would be water treatment.

55:09.680 --> 55:11.680
I mean, we we take care of it.

55:11.680 --> 55:12.680
Right now.

55:12.680 --> 55:13.680
Okay.

55:13.680 --> 55:20.680
Yeah.

55:21.680 --> 55:23.680
There's no more questions.

55:23.680 --> 55:26.680
They entertain a motion.

55:26.680 --> 55:33.680
I'll move to accept or to approve the recommendation of staff on this project.

55:33.680 --> 55:34.680
As written.

55:34.680 --> 55:37.680
The motion by elder woman Miller.

55:37.680 --> 55:39.680
The second.

55:39.680 --> 55:43.680
I'll second.

55:43.680 --> 55:47.680
I guess if there's no more comments or discussion all in favor.

55:47.680 --> 55:48.680
Hi.

55:49.680 --> 55:50.680
Motion carries.

55:50.680 --> 55:58.680
Thank you.

55:58.680 --> 56:00.680
Thanks, Dan.

56:00.680 --> 56:04.680
That brings us to item number six.

56:04.680 --> 56:08.680
Review staff monthly reports.

56:08.680 --> 56:10.680
Okay.

56:11.680 --> 56:14.680
I'll just add.

56:14.680 --> 56:16.680
We just met two weeks ago.

56:16.680 --> 56:20.680
So I won't necessarily go through all these, but are there.

56:20.680 --> 56:24.680
Are there any questions about anything in any of the reports.

56:24.680 --> 56:26.680
For this evening.

56:26.680 --> 56:27.680
Yeah.

56:27.680 --> 56:35.680
Not that we're not very busy or that there aren't exciting things, but.

56:35.680 --> 56:39.680
Yeah, I'll just take any questions if anyone has any on the reports.

56:40.680 --> 56:44.680
I guess not.

56:44.680 --> 56:45.680
Okay.

56:45.680 --> 56:48.680
Moving on to chairman's business.

56:48.680 --> 56:50.680
I have none.

56:50.680 --> 56:54.680
Members liaison's business.

56:54.680 --> 56:57.680
Nope.

56:57.680 --> 57:05.680
Next meeting is October 13th, 2026 here at 530 p.m.

57:06.680 --> 57:11.680
And I guess that brings us to item 10 adjournment.

57:11.680 --> 57:14.680
I have a motion.

57:14.680 --> 57:16.680
I'll make the motion to adjourn the meeting.

57:16.680 --> 57:18.680
Motion by Alderman Beaster.

57:18.680 --> 57:19.680
Second.

57:19.680 --> 57:20.680
Second by Mr. Polly.

57:20.680 --> 57:22.680
I'm all in favor.

57:22.680 --> 57:23.680
Hi.

57:23.680 --> 57:25.680
Do I do this again?

57:25.680 --> 57:26.680
Yeah.

57:26.680 --> 57:31.680
Thanks, Nick.
