1
00:00:00,000 --> 00:00:07,000
to the council.

2
00:00:07,000 --> 00:00:08,000
All right.

3
00:00:08,000 --> 00:00:10,000
I call to order the city of

4
00:00:10,000 --> 00:00:12,000
Port Washington, Wisconsin

5
00:00:12,000 --> 00:00:14,000
Board of Public Works meeting

6
00:00:14,000 --> 00:00:18,000
for Tuesday, June 9th, 2026.

7
00:00:18,000 --> 00:00:21,000
First item is the roll call.

8
00:00:21,000 --> 00:00:23,000
All members are present except

9
00:00:23,000 --> 00:00:25,000
for Jim Pauli who is

10
00:00:25,000 --> 00:00:27,000
excused.

11
00:00:27,000 --> 00:00:29,000
That brings us to item two,

12
00:00:29,000 --> 00:00:31,000
a motion to approve the

13
00:00:31,000 --> 00:00:33,000
minutes by second and we have a

14
00:00:33,000 --> 00:00:34,000
second.

15
00:00:34,000 --> 00:00:36,000
Any question on the motion?

16
00:00:36,000 --> 00:00:38,000
Seeing none, all those in favor?

17
00:00:38,000 --> 00:00:39,000
Say aye.

18
00:00:39,000 --> 00:00:40,000
Aye.

19
00:00:40,000 --> 00:00:41,000
Opposed?

20
00:00:41,000 --> 00:00:42,000
Motion carries.

21
00:00:42,000 --> 00:00:43,000
That brings us to public

22
00:00:43,000 --> 00:00:46,000
comments and appearances.

23
00:00:46,000 --> 00:00:47,000
Are there any public comments

24
00:00:47,000 --> 00:00:50,000
and appearances?

25
00:00:50,000 --> 00:00:51,000
We don't need to fill a

26
00:00:51,000 --> 00:00:53,000
buster to, so the computer

27
00:00:53,000 --> 00:00:54,000
works.

28
00:00:54,000 --> 00:00:55,000
Okay.

29
00:00:55,000 --> 00:00:57,000
Then we'll move on to item four,

30
00:00:57,000 --> 00:00:59,000
election of board chair and

31
00:00:59,000 --> 00:01:00,000
vice chair.

32
00:01:00,000 --> 00:01:03,000
So every year we elect a new

33
00:01:03,000 --> 00:01:06,000
chairman and a vice chairman for

34
00:01:06,000 --> 00:01:08,000
the Board of Public Works.

35
00:01:08,000 --> 00:01:11,000
And with that in mind, I will

36
00:01:11,000 --> 00:01:14,000
open the floor to nominations.

37
00:01:14,000 --> 00:01:16,000
Does anybody want to make a

38
00:01:16,000 --> 00:01:19,000
nomination for board chair?

39
00:01:19,000 --> 00:01:21,000
I move for my gasper to be

40
00:01:21,000 --> 00:01:22,000
board chair.

41
00:01:22,000 --> 00:01:23,000
All right.

42
00:01:23,000 --> 00:01:26,000
So we have a nomination for my

43
00:01:26,000 --> 00:01:28,000
gasper to be board chair.

44
00:01:28,000 --> 00:01:30,000
Is there a second?

45
00:01:30,000 --> 00:01:31,000
Second.

46
00:01:31,000 --> 00:01:32,000
Second.

47
00:01:32,000 --> 00:01:33,000
All right.

48
00:01:33,000 --> 00:01:36,000
Are there any other nominations?

49
00:01:36,000 --> 00:01:39,000
Any more nominations?

50
00:01:39,000 --> 00:01:40,000
I'll ask a third time.

51
00:01:40,000 --> 00:01:42,000
Are there any more nominations?

52
00:01:42,000 --> 00:01:43,000
All right.

53
00:01:43,000 --> 00:01:45,000
Seeing none, we have a

54
00:01:45,000 --> 00:01:47,000
nomination for my gasper being

55
00:01:47,000 --> 00:01:49,000
myself to be board chair.

56
00:01:49,000 --> 00:01:50,000
All those in favor?

57
00:01:50,000 --> 00:01:51,000
Say aye.

58
00:01:51,000 --> 00:01:52,000
Aye.

59
00:01:52,000 --> 00:01:53,000
Opposed?

60
00:01:53,000 --> 00:01:54,000
Motion carries.

61
00:01:54,000 --> 00:01:55,000
So we have a board chair.

62
00:01:55,000 --> 00:01:57,000
Now we need a vice chair.

63
00:01:57,000 --> 00:01:59,000
So I will open the floor for

64
00:01:59,000 --> 00:02:04,000
nominations to be the vice chair.

65
00:02:04,000 --> 00:02:07,000
Any nomination?

66
00:02:07,000 --> 00:02:09,000
We'll sit and nominate Jim because

67
00:02:09,000 --> 00:02:14,000
he's not here.

68
00:02:14,000 --> 00:02:15,000
Sure.

69
00:02:15,000 --> 00:02:19,000
I'll nominate.

70
00:02:19,000 --> 00:02:21,000
I will nominate Mr.

71
00:02:21,000 --> 00:02:23,000
Schudendorf to be the vice chair

72
00:02:23,000 --> 00:02:25,000
if he's willing to accept.

73
00:02:25,000 --> 00:02:26,000
I'll accept.

74
00:02:26,000 --> 00:02:27,000
All right.

75
00:02:27,000 --> 00:02:28,000
I'll second.

76
00:02:28,000 --> 00:02:29,000
All right.

77
00:02:29,000 --> 00:02:31,000
Are there any additional

78
00:02:31,000 --> 00:02:34,000
nominations for vice chair?

79
00:02:34,000 --> 00:02:35,000
All right.

80
00:02:35,000 --> 00:02:37,000
Seeing none, all those in favor?

81
00:02:37,000 --> 00:02:38,000
Say aye.

82
00:02:38,000 --> 00:02:39,000
Aye.

83
00:02:39,000 --> 00:02:40,000
Opposed?

84
00:02:40,000 --> 00:02:41,000
Motion carries.

85
00:02:41,000 --> 00:02:42,000
All right.

86
00:02:42,000 --> 00:02:44,000
Congratulations to our new chair

87
00:02:44,000 --> 00:02:46,000
and vice chair.

88
00:02:46,000 --> 00:02:49,000
That will move us on to item five,

89
00:02:49,000 --> 00:02:51,000
a presentation on ecological

90
00:02:51,000 --> 00:02:54,000
restoration in Valley Creek.

91
00:02:54,000 --> 00:02:57,000
Rob.

92
00:02:57,000 --> 00:02:58,000
Thank you.

93
00:02:58,000 --> 00:03:00,000
So we have with us tonight,

94
00:03:00,000 --> 00:03:03,000
Melissa Kern, who I think is no stranger to our

95
00:03:03,000 --> 00:03:06,000
committee and Ryan Crump, who is a

96
00:03:06,000 --> 00:03:08,000
biologist, I'm sorry.

97
00:03:08,000 --> 00:03:11,000
Biologist both with Stantec.

98
00:03:11,000 --> 00:03:14,000
And so they've been working, of course, as you know,

99
00:03:14,000 --> 00:03:18,000
in Valley Creek for the last more than three years.

100
00:03:18,000 --> 00:03:22,000
Working under grants that we've received from the American

101
00:03:22,000 --> 00:03:26,000
Bird Conservancy, U.S. Fish and Wildlife,

102
00:03:26,000 --> 00:03:31,000
which is different than National Fish and Wildlife Foundation,

103
00:03:31,000 --> 00:03:34,000
U.S. Forest Service.

104
00:03:34,000 --> 00:03:38,000
And so they've done a lot of work both in Upper Lake Park

105
00:03:38,000 --> 00:03:40,000
and Burtwood Hills Nature Preserve,

106
00:03:40,000 --> 00:03:43,000
removing invasive species, planting native species.

107
00:03:43,000 --> 00:03:47,000
And of course, we're working towards the much larger project,

108
00:03:47,000 --> 00:03:52,000
which is creating the resilient and sustainable Valley Creek,

109
00:03:52,000 --> 00:03:57,000
which will have numerous stormwater or water quality benefits as well,

110
00:03:57,000 --> 00:03:59,000
fish passage, et cetera.

111
00:03:59,000 --> 00:04:04,000
And so a lot of this has been going on over the last three years,

112
00:04:04,000 --> 00:04:05,000
kind of under the radar.

113
00:04:05,000 --> 00:04:07,000
And we haven't really talked about it a ton here.

114
00:04:07,000 --> 00:04:12,000
So I asked Melissa and Ryan to come now that much of that work

115
00:04:12,000 --> 00:04:19,000
that first phase is completed to report on some of the measurable benefits

116
00:04:19,000 --> 00:04:23,000
that we're achieving and hope to achieve in the upcoming years

117
00:04:23,000 --> 00:04:25,000
with our Valley Creek project.

118
00:04:25,000 --> 00:04:26,000
All right.

119
00:04:26,000 --> 00:04:27,000
Thank you.

120
00:04:27,000 --> 00:04:29,000
Thanks, everyone, for your patience while we work through the PowerPoint.

121
00:04:29,000 --> 00:04:32,000
This would not be the same without you guys seeing some pictures

122
00:04:32,000 --> 00:04:33,000
of before and after.

123
00:04:33,000 --> 00:04:35,000
So again, Melissa Kern was Dan Tack.

124
00:04:35,000 --> 00:04:38,000
I've been working with the city for really well over five, seven years,

125
00:04:38,000 --> 00:04:40,000
you know, working to develop this project.

126
00:04:40,000 --> 00:04:42,000
And you can fast forward, Roger.

127
00:04:42,000 --> 00:04:46,000
So what we're going to talk about is give you a snapshot of the ecological restoration

128
00:04:46,000 --> 00:04:51,000
of some of the upland parks that we've been doing over the last several years.

129
00:04:51,000 --> 00:04:54,000
And then I will give you a funding update.

130
00:04:54,000 --> 00:04:56,000
So Roger, I don't know if you can advance it.

131
00:04:56,000 --> 00:05:00,000
Just to show you guys a quick agenda of what we're going to talk about.

132
00:05:00,000 --> 00:05:03,000
There we go.

133
00:05:03,000 --> 00:05:06,000
And so I list just a few of the grants and those.

134
00:05:06,000 --> 00:05:09,000
I'll go over each in detail, but those are ones that are either

135
00:05:09,000 --> 00:05:11,000
recently awarded or are still pending.

136
00:05:11,000 --> 00:05:14,000
So I want to make sure you guys have a good sense of kind of, you know,

137
00:05:14,000 --> 00:05:16,000
we're constantly working on grant funds.

138
00:05:16,000 --> 00:05:17,000
And so just a quick update on that.

139
00:05:17,000 --> 00:05:22,000
But I'm going to turn over to Ryan to give you a presentation of the upland

140
00:05:22,000 --> 00:05:28,000
ecological restoration work that we've been doing at several of your parks.

141
00:05:28,000 --> 00:05:29,000
Yeah.

142
00:05:29,000 --> 00:05:31,000
So Ryan Chrome, I've been with Stan Tack for like 10 years.

143
00:05:31,000 --> 00:05:36,000
I worked with our ecosystem restoration team doing the implementation work.

144
00:05:37,000 --> 00:05:41,000
So I'm the project manager for these different projects I'll present on today.

145
00:05:41,000 --> 00:05:45,000
We'll see some of the metrics, some of the dollars that have been contributed

146
00:05:45,000 --> 00:05:49,000
to the Valley Creek corridor, the agencies and kind of partners involved

147
00:05:49,000 --> 00:05:51,000
in just kind of what's been going on.

148
00:05:51,000 --> 00:05:54,000
So the first one, the U.S. Fish and Wildlife Service,

149
00:05:54,000 --> 00:05:58,000
that was funding from 2023 to 2025.

150
00:05:58,000 --> 00:06:03,000
The city was the sole applicant on that one for $135,000 and that funded work

151
00:06:03,000 --> 00:06:04,000
for the city.

152
00:06:04,000 --> 00:06:05,000
Birchwood Hills and Upper Lake Park.

153
00:06:05,000 --> 00:06:09,000
I'll show some maps and stuff here kind of showing where the funding areas are in a

154
00:06:09,000 --> 00:06:10,000
second.

155
00:06:10,000 --> 00:06:14,000
The next one with the American Burke Conservancy National Fish and Wildlife

156
00:06:14,000 --> 00:06:19,000
Foundation to stay in our Great Lakes program 2023 through 2026,

157
00:06:19,000 --> 00:06:23,000
approximately $45,000 within the Valley Creek corridor.

158
00:06:23,000 --> 00:06:27,000
And then the next one also with the American Burke Conservancy U.S.

159
00:06:27,000 --> 00:06:32,000
Department of Agriculture for service 2024 to 2027.

160
00:06:32,000 --> 00:06:35,000
This one's still ongoing.

161
00:06:35,000 --> 00:06:39,000
That's about $45,000 as well within that Valley Creek corridor.

162
00:06:39,000 --> 00:06:44,000
So main thing to take away here, obviously the funding partners and agencies that

163
00:06:44,000 --> 00:06:49,000
we're working with, obviously the city and the city's been doing work directly

164
00:06:49,000 --> 00:06:51,000
adjacent to a lot of these project areas as well.

165
00:06:51,000 --> 00:06:53,000
So you go to the next slide.

166
00:06:53,000 --> 00:06:57,000
So on metric specific to these funding sources.

167
00:06:57,000 --> 00:07:01,000
So the U.S. Fish and Wildlife Service funding was funding restoration

168
00:07:01,000 --> 00:07:03,000
across approximately 20.9 acres.

169
00:07:03,000 --> 00:07:06,000
That's that Birchwood Hills area and Upper Lake Park.

170
00:07:06,000 --> 00:07:13,000
As part of that, we did a large tree planting requirement was 15 or more native

171
00:07:13,000 --> 00:07:16,000
tree and shrub species planted.

172
00:07:16,000 --> 00:07:21,000
And as part of that grant, we planted over 400 trees and shrubs within

173
00:07:21,000 --> 00:07:25,000
Birchwood and cage them and protected them from browse pressure and stuff like that.

174
00:07:25,000 --> 00:07:30,000
And then in addition to that, we installed the pollinator planting in Upper

175
00:07:30,000 --> 00:07:36,000
Lake Park and had at least 25 native form and grass species throughout that

176
00:07:36,000 --> 00:07:38,000
planting as well.

177
00:07:38,000 --> 00:07:42,000
As far as the SOGO funding goes, that's part of a much larger project.

178
00:07:42,000 --> 00:07:45,000
So that's actually funding work at eight different project sites along Lake

179
00:07:45,000 --> 00:07:48,000
Michigan, Valley Creek corridor being one of them.

180
00:07:48,000 --> 00:07:53,000
So as part of that, you know, restoration of 238 acres of near shore habitat,

181
00:07:53,000 --> 00:07:59,000
stop over habitat, American bird conservancy, six acres of floodplain restoration,

182
00:07:59,000 --> 00:08:01,000
51 acres of wetland restoration.

183
00:08:01,000 --> 00:08:06,000
A lot of these common theme is going to be volunteer and public outreach and engagement.

184
00:08:06,000 --> 00:08:09,000
So there's always metrics involved there.

185
00:08:09,000 --> 00:08:13,000
We've held various volunteer plantings as part of the SOGO funding and then moving

186
00:08:13,000 --> 00:08:16,000
on to the Forest Service funding.

187
00:08:16,000 --> 00:08:19,000
You're going to see a lot of overlap in those, but again,

188
00:08:19,000 --> 00:08:21,000
large tree planting being funded through that.

189
00:08:21,000 --> 00:08:25,000
Again, that's funding three different project sites in Ozaki and Washington

190
00:08:25,000 --> 00:08:26,000
County total.

191
00:08:26,000 --> 00:08:32,000
So those trees are being split, but we just as bring planting here in 2026,

192
00:08:32,000 --> 00:08:36,000
where we installed 845 trees in the Valley Creek corridor.

193
00:08:36,000 --> 00:08:38,000
There's a volunteer opportunity as well.

194
00:08:38,000 --> 00:08:40,000
So got some of that volunteer engagement.

195
00:08:40,000 --> 00:08:43,000
18 acres of invasive species management.

196
00:08:43,000 --> 00:08:47,000
Again, this is spread across three project sites, 10 acres of native seed

197
00:08:47,000 --> 00:08:52,000
insulation and then $250,000 of stormwater intercepted through that tree planting.

198
00:08:52,000 --> 00:08:59,000
So if you scroll down just a little bit, you can see the rest of it.

199
00:08:59,000 --> 00:09:01,000
So this is the funding areas.

200
00:09:01,000 --> 00:09:06,000
It's kind of hard to see, but the red that you're seeing there in Burtwood Hills

201
00:09:06,000 --> 00:09:09,000
and that small sliver on Upper Lake Park.

202
00:09:09,000 --> 00:09:12,000
That's the US Fish and Wildlife Service funding areas.

203
00:09:12,000 --> 00:09:15,000
Moving down to the yellow is the ABC SOGO bluff.

204
00:09:15,000 --> 00:09:21,000
And then moving down from there is the ABC Forest Service funding that we just talked about.

205
00:09:21,000 --> 00:09:26,000
So you can see how they're connected along that corridor.

206
00:09:26,000 --> 00:09:31,000
Real quick, just talking about the projects, the goals and what's been done there so far.

207
00:09:31,000 --> 00:09:38,000
So trying to create sustainable restoration within these ecosystems.

208
00:09:38,000 --> 00:09:43,000
So US Fish and Wildlife Service wanted to invest and focus on habitat improvements

209
00:09:43,000 --> 00:09:46,000
or things like even the northern long-eared bat.

210
00:09:47,000 --> 00:09:49,000
Rusty Patch Bumblebee Monarchs.

211
00:09:49,000 --> 00:09:53,000
So that's where you're seeing those requirements of native trees, native shrub species

212
00:09:53,000 --> 00:09:57,000
and the high requirements of native species within that pollinator planting.

213
00:09:57,000 --> 00:10:01,000
Diversification, you know, the goal is just trying to create more sustainable

214
00:10:01,000 --> 00:10:05,000
ecosystems and trees and species that can thrive in changing climates

215
00:10:05,000 --> 00:10:09,000
and more adaptable, obviously invasive species management.

216
00:10:09,000 --> 00:10:13,000
So there was tons of woody invasives in there that we controlled and I'll show some pictures of that.

217
00:10:13,000 --> 00:10:15,000
It was pretty nasty in there.

218
00:10:15,000 --> 00:10:18,000
So we were controlling that, limiting the competition.

219
00:10:18,000 --> 00:10:21,000
And then obviously planting those native species.

220
00:10:21,000 --> 00:10:25,000
And a big thing, you know, just within this valley creek corridor is the watershed impact.

221
00:10:25,000 --> 00:10:33,000
So trying to limit the amount of erosion, plant species and just plants that are better at up taking

222
00:10:33,000 --> 00:10:38,000
that sort of water native to this region and just limiting overall erosion.

223
00:10:38,000 --> 00:10:41,000
And then again, I mentioned the public education outreach.

224
00:10:41,000 --> 00:10:44,000
So in Birchwood, we did a lot of invasive species management.

225
00:10:44,000 --> 00:10:46,000
We left some wildlife habitat in there.

226
00:10:46,000 --> 00:10:52,000
You're still going to see snags in there that are good for roost habitat for, like I said, birds, bats.

227
00:10:52,000 --> 00:10:55,000
There's habitat piles, stuff like that.

228
00:10:55,000 --> 00:10:57,000
And then the tree planting.

229
00:10:57,000 --> 00:11:03,000
And then upper lake park, we did site preparation, native seeding, and then some pollinator prairie management.

230
00:11:03,000 --> 00:11:07,000
So here's Birchwood before we went in there.

231
00:11:07,000 --> 00:11:10,000
So you can see it's pretty nasty.

232
00:11:10,000 --> 00:11:15,000
So in that picture on the right, you can just barely see the edge of our forestry mower before it went through there.

233
00:11:15,000 --> 00:11:20,000
That's a lot of barberry in the background and then honeysuckle on that left picture, but you keep going.

234
00:11:20,000 --> 00:11:23,000
Here is just some progress photos.

235
00:11:23,000 --> 00:11:26,000
So that picture on the left, you can see we've mowed through a lot of it.

236
00:11:26,000 --> 00:11:29,000
There's still some chips there, but that's kind of in the process.

237
00:11:29,000 --> 00:11:32,000
And then that picture on the right is a more final product.

238
00:11:32,000 --> 00:11:34,000
We really opened that place up.

239
00:11:34,000 --> 00:11:37,000
I know there's trails being planned in there and stuff like that.

240
00:11:37,000 --> 00:11:42,000
And then we planted trees all throughout this area and did woody resprout control.

241
00:11:42,000 --> 00:11:45,000
And then here, you can just see some pictures from the tree planting.

242
00:11:45,000 --> 00:11:49,000
So this is the pond that's in Birchwood Hills there right near the parking area.

243
00:11:49,000 --> 00:11:55,000
And then as you can see, we're getting ready for the tree planting and the tree delivery and stuff right there by the Birchwood sign.

244
00:11:55,000 --> 00:11:57,000
Upper Lake Park here.

245
00:11:57,000 --> 00:11:59,000
A couple of different stages here.

246
00:11:59,000 --> 00:12:03,000
So this is left pictures right after site prep.

247
00:12:03,000 --> 00:12:05,000
And we're getting ready for native seeding.

248
00:12:05,000 --> 00:12:08,000
The picture on the right there is after the native seeing the first growing season.

249
00:12:08,000 --> 00:12:13,000
It doesn't look like much, but what you see in there, those are all native seedlings that we planted.

250
00:12:13,000 --> 00:12:16,000
And that's just kind of what it looks like the first growing season.

251
00:12:16,000 --> 00:12:21,000
But then if you go one more, this is what it looked like growing season three.

252
00:12:21,000 --> 00:12:24,000
So lots of natives, lots of flowers.

253
00:12:24,000 --> 00:12:27,000
It was looking great.

254
00:12:27,000 --> 00:12:30,000
You can keep going.

255
00:12:31,000 --> 00:12:35,000
So again, very similar project goals and site work that happened here.

256
00:12:35,000 --> 00:12:42,000
So a lot of this was invasive species management, woodies in particular with a focus on wildlife habitat.

257
00:12:42,000 --> 00:12:46,000
Again, American bird conservancy did a lot of this funding.

258
00:12:46,000 --> 00:12:59,000
And again, a lot of this is involving, you know, improving the watershed planting native species and just kind of creating areas that are less prone to erosion.

259
00:12:59,000 --> 00:13:04,000
More stormwater capacity and that wildlife habitat.

260
00:13:04,000 --> 00:13:07,000
So we can keep going on that as well.

261
00:13:07,000 --> 00:13:10,000
Here's another before and after. So this is on that bluff.

262
00:13:10,000 --> 00:13:13,000
Portions of this bluff are actually in pretty good shape.

263
00:13:13,000 --> 00:13:17,000
So in the areas that we're in good shape, we didn't have to do a whole lot.

264
00:13:17,000 --> 00:13:19,000
We didn't actually have to do a lot of tree planting on this.

265
00:13:19,000 --> 00:13:22,000
The candy piece pretty good, but the honor store is full of woodies.

266
00:13:22,000 --> 00:13:25,000
So we moved the honey, socco, barberry, multiple rows.

267
00:13:25,000 --> 00:13:28,000
You can kind of see it before and after.

268
00:13:28,000 --> 00:13:31,000
And you can line up some trees in there and just kind of see some of that change.

269
00:13:31,000 --> 00:13:37,000
But I know the crew had a hard time out there, but it looks a lot better.

270
00:13:37,000 --> 00:13:43,000
And then the ABC Forest Service bluff that we are still kind of working on.

271
00:13:43,000 --> 00:13:46,000
A big one of this is the emerald ash borer mitigation.

272
00:13:46,000 --> 00:13:51,000
There's a lot of dead ash on that slope there. We've done a lot of tree planting in there, a lot of woody removal.

273
00:13:51,000 --> 00:13:57,000
Lots of overlap on these, but you can see, you know, forest service is really focused on the tree tree planting aspect of it.

274
00:13:58,000 --> 00:14:06,000
Increasing those habitat corridors and connectivity. So this one funds three projects across Ozaki in Washington County.

275
00:14:06,000 --> 00:14:12,000
And again, obviously we're doing all sorts of connecting habitats within the valley creek corridor as well.

276
00:14:12,000 --> 00:14:15,000
Just trying to make it more sustainable.

277
00:14:16,000 --> 00:14:24,000
Diversify the species that are there. They are again, same thing, like able to adapt to the climate changes and different things that we're seeing out there.

278
00:14:24,000 --> 00:14:30,000
We had the public out for volunteer planting in spring.

279
00:14:30,000 --> 00:14:36,000
So far we've done invasive species management, the woody removal, the woody resprouts.

280
00:14:36,000 --> 00:14:41,000
There's some wildlife habitat piles out there as well. And then the tree planting, like I said, so.

281
00:14:42,000 --> 00:14:49,000
This slope was really rough as well, but that area in particular, seeing there's lots of downed dead ash trees.

282
00:14:49,000 --> 00:14:58,000
So we opened up the canopy a lot. If you go look at that bluff there, you're going to see a lot of trees focused in those canopy gaps that were created with those dead ash trees in there.

283
00:14:58,000 --> 00:15:02,000
A big part of it's also the stormwater capture that I've mentioned.

284
00:15:02,000 --> 00:15:07,000
And here it's still just this is the planting the spring. So that's our crew out there.

285
00:15:08,000 --> 00:15:11,000
And some of the trees that were being installed.

286
00:15:15,000 --> 00:15:20,000
So my primarily primary role on this project is connect funding to the project.

287
00:15:20,000 --> 00:15:24,000
And so sometimes that means the city is directly the applicant on a grant application.

288
00:15:24,000 --> 00:15:36,000
Sometimes it's a nonprofit partner. So as Ryan mentioned, American Burke Conservancy has been a long time partner of mine and I end up bringing a lot of municipal project sites to ABC for them to apply for grants on behalf.

289
00:15:36,000 --> 00:15:44,000
So it's a collaborative effort that works out really well for the city because you guys are just a recipient of this really great work and you really don't have any administrative burden.

290
00:15:44,000 --> 00:15:54,000
There's no staff time that goes into it. It's all just kind of a win-win for you guys. So I'll keep doing that to really kind of invest in this Valley Creek corridor with, you know, supporting this bigger vision that we have.

291
00:15:54,000 --> 00:16:01,000
So what I wanted to do was just go through some of the more recent grants that we're working on. Some that have been awarded, some that are still pending.

292
00:16:02,000 --> 00:16:14,000
So starting at the top, we, the city did secure a National Fish and Wildlife Foundation sustainer Great Lakes to implement some green infrastructure projects on Upper Lake Park.

293
00:16:14,000 --> 00:16:21,000
And I do have an image of that later. So that grant has been awarded, but we're going through the federal compliance process right now.

294
00:16:21,000 --> 00:16:28,000
It's just a complicated process where we review the project for impacts to cultural resources and rare species.

295
00:16:28,000 --> 00:16:36,000
Once that's all done, the city will get a grant contract. So you guys at some point will be accepting that grant award. That'll come probably pretty soon.

296
00:16:36,000 --> 00:16:47,000
Then a complimentary to that, we applied for a state urban non-point grant, which will provide the necessary match for the federal grant from the sustainer Great Lakes program.

297
00:16:47,000 --> 00:16:55,000
So those two are kind of match each other. And that's another really great benefit of sort of stacking these grants as they get to match each other.

298
00:16:55,000 --> 00:17:02,000
So if we're awarded both those grants, then there's really no cash contribution that the city is on the hook for.

299
00:17:02,000 --> 00:17:14,000
So, and I do list the grant that you were awarded, you did offer $100,000 this match. Again, the intent was always that we would find other funding to make up that match.

300
00:17:14,000 --> 00:17:20,000
It wasn't, you know, that you guys were expecting to outlay that $100,000. And that's why we submitted that DNR grant, the one that's just down.

301
00:17:20,000 --> 00:17:26,000
So if you get $150,000 from DNR, then you've met your match requirement for the sustainer Great Lakes grant.

302
00:17:26,000 --> 00:17:36,000
Third one down is another sustainer Great Lakes grant that we are submitting for a different green infrastructure project for a Walter Street ravine project.

303
00:17:36,000 --> 00:17:46,000
I'll show a picture of that. And then the big one, the fourth one down is also through National Fish and Wildlife Foundation, but it's a different grant program called National Coastal Resilience Fund.

304
00:17:47,000 --> 00:17:57,000
So that is a multi-step grant. You guys have already received one grant and that's supporting the planning that we're doing right now for the Big Stream Restoration Project.

305
00:17:57,000 --> 00:18:04,000
This will support the implementation. We've already submitted a pre-proposal and you guys have been invited for a full proposal.

306
00:18:04,000 --> 00:18:12,000
So that's a really good sign that you guys are invited and they really like funding these pipeline projects and they gave us really good feedback on the pre-proposal.

307
00:18:13,000 --> 00:18:25,000
So we will likely ask about $5 million for that grant. I'm very hopeful that we will get it. We may end up funding the value, the bigger Valley Creek project in phases.

308
00:18:25,000 --> 00:18:33,000
So we may end up going back to the same funding source twice to get kind of roughly the same amount of money to construct the project in phases.

309
00:18:33,000 --> 00:18:39,000
That's always an option. But that one will go in at the end of this month in June here.

310
00:18:39,000 --> 00:18:44,000
And then we submitted another grant from the DNR under their targeted runoff management program.

311
00:18:44,000 --> 00:18:52,000
And that is to fund some of the regenerative stormwater conveyance systems that so it's really stabilizing the outfalls along Valley Creek.

312
00:18:52,000 --> 00:18:57,000
So it's a very green infrastructure stormwater focus grant and I'm going to show you pictures of those. So if you want to go ahead.

313
00:18:57,000 --> 00:19:02,000
Roger, I'm just going to kind of go through all of these except the big $5 million stream one.

314
00:19:03,000 --> 00:19:13,000
So Upper Lake Park, this project will connect directly with the pollinator garden that Ryan was talking about in the northwest corner of Upper Lake Park.

315
00:19:13,000 --> 00:19:19,000
There are stormwater outfalls that are discharging right at the top of some eroding gullies.

316
00:19:19,000 --> 00:19:31,000
They're causing massive erosion. And that's really contributing to the destabilization of Valley Creek and why we're doing this big project is to try and keep the sediment and slow the water down.

317
00:19:31,000 --> 00:19:46,000
So the intent here and here is put together this conceptual design is that we'll essentially build some rain gardens and some detention basins that will capture and store potentially and filtrate some of that storm water.

318
00:19:46,000 --> 00:19:54,000
So we'll have less water going down into the ravine. We'll still have to have water going down there, but the thought is we'll stabilize that outfall.

319
00:19:54,000 --> 00:20:05,000
And then this project and you know, the thought is that will be in the upland areas will be planting prairies. So eventually this will blend seamlessly into the prairie that you guys have already started restoring up there.

320
00:20:05,000 --> 00:20:15,000
And again, the two different grants, the federal grant from Solville for 375 that you have already been awarded will be matched by the hopefully by the pending DNR grant.

321
00:20:15,000 --> 00:20:18,000
We'll hear back sometime this late summer fall on that one.

322
00:20:19,000 --> 00:20:21,000
Go ahead, Roger.

323
00:20:21,000 --> 00:20:27,000
So this other urban stormwater grant is for regenerative stormwater conveyance.

324
00:20:27,000 --> 00:20:35,000
They're essentially, I think I do have some pictures after this, but they're meant to stabilize some of the outfalls that are discharging directly to the creek.

325
00:20:35,000 --> 00:20:44,000
And under this grant for roughly about $219,000, we are planning to fund at least six outfall locations.

326
00:20:45,000 --> 00:20:50,000
Erin, I don't know if you remember there are like 20 RSCs that you're envisioning along the valley creek corridor.

327
00:20:58,000 --> 00:21:07,000
Oh, so there's roughly about like 20 RSC locations. This grant will fund at six of them so we can go back next year for the same grant to fund more of them.

328
00:21:07,000 --> 00:21:14,000
So this isn't a one and done. This could be an annual thing where we have this, you know, roughly $200,000 to fund multiple stormwater.

329
00:21:14,000 --> 00:21:17,000
And I presented it to DNR as a multi phase approach.

330
00:21:17,000 --> 00:21:21,000
Go ahead. So this is just an image showing what the current condition is on the left.

331
00:21:21,000 --> 00:21:28,000
I would say most of your outfalls look like that where they're just perched in hanging and, you know, they're not constructed that way.

332
00:21:28,000 --> 00:21:32,000
That's just how much the creek has eroded over the years.

333
00:21:32,000 --> 00:21:34,000
So we definitely want to fix that.

334
00:21:34,000 --> 00:21:44,000
Do whatever we can to infiltrate, slow the water and treat it a little bit right at the outfall location and then, you know, have some intense stabilization when the water intersects the creek.

335
00:21:44,000 --> 00:21:49,000
So that's on the right is what, you know, an image of what that could look like.

336
00:21:49,000 --> 00:21:55,000
And then the other big regenerative stormwater is to focus on the Walter street ravine.

337
00:21:55,000 --> 00:21:59,000
So this is a big ravine where you have an outfall at the top of the ravine.

338
00:21:59,000 --> 00:22:03,000
It's discharging stormwater that's eroding that whole gully there.

339
00:22:03,000 --> 00:22:08,000
And so the thought is to have a series of regenerative stormwater, you know, conveyance that whole way through.

340
00:22:08,000 --> 00:22:19,000
So it's going to be like a step pool conveyance where, you know, the water kind of slows down at a pool and then it goes over like a rock outfall and then it goes into another pool and we do that the whole way down the ravine.

341
00:22:20,000 --> 00:22:27,000
So we did submit most recently for a solo grant and the amount of 365, I think it was.

342
00:22:27,000 --> 00:22:31,000
And we will and we just submitted the pre proposal.

343
00:22:31,000 --> 00:22:38,000
So we'll find out in probably a couple weeks if we're invited for the full proposal for that one, but this is current condition of Walter street ravine.

344
00:22:38,000 --> 00:22:42,000
And then I think the next image is a kind of rough.

345
00:22:42,000 --> 00:22:48,000
You can kind of barely see the the rough concept of what that would look like, but we're essentially looking at stabilizing that whole ravine.

346
00:22:48,000 --> 00:22:52,000
So that'll be a big project.

347
00:22:52,000 --> 00:22:54,000
We are offering a one to one match.

348
00:22:54,000 --> 00:23:02,000
So that match will come in the form of maybe other grants or some of the TID money that you guys have to fund work along the larger stream project.

349
00:23:02,000 --> 00:23:08,000
So I think that was the last slide. Any questions from us?

350
00:23:08,000 --> 00:23:10,000
I have a few.

351
00:23:11,000 --> 00:23:16,000
And talk to me like I'm a five year old because this is all new to me.

352
00:23:16,000 --> 00:23:26,000
So how is the storm water intercepted by tree plantings explain that concept?

353
00:23:26,000 --> 00:23:29,000
So there's a lot of water circulating through trees.

354
00:23:29,000 --> 00:23:35,000
So they do a really good job bringing water down into their root system and supporting groundwater recharge.

355
00:23:35,000 --> 00:23:37,000
So like a sponge kind of.

356
00:23:37,000 --> 00:23:47,000
And so there is a metric of tree of like one inch DBH will over the course of a year capture and infiltrate about 100,000 gallons of water.

357
00:23:47,000 --> 00:23:51,000
So trees do a good job at making.

358
00:23:51,000 --> 00:23:55,000
And then the native seedling in Upper Lake Park.

359
00:23:55,000 --> 00:24:05,000
So along with water retention, what else is that going to do rather than just natural grass and that we cut?

360
00:24:06,000 --> 00:24:09,000
So the question is the.

361
00:24:09,000 --> 00:24:11,000
What was the purpose of the native?

362
00:24:11,000 --> 00:24:12,000
Yes. Yes.

363
00:24:12,000 --> 00:24:16,000
So the grant that funded that was very focused on wildlife habitat enhancements.

364
00:24:16,000 --> 00:24:20,000
So establishing native plants is good for pollinators, birds, bats.

365
00:24:20,000 --> 00:24:34,000
So the intent was to, you know, when we get rid of the invasives, there's can sometimes be like a bear area that you want to then replant with natives to help out compete additional invasives that may want to come in, but also provides great habitats for wildlife.

366
00:24:35,000 --> 00:24:37,000
Okay. And then also deep.

367
00:24:37,000 --> 00:24:46,000
Yeah, I mean, so I would say a poll on air planting does act a little bit more like a sponge, you know, like a native prairie and grass, you know, going to filter water a lot better.

368
00:24:46,000 --> 00:24:51,000
But also with the US Fish Wildlife Service folks in a wildlife and stuff.

369
00:24:51,000 --> 00:24:54,000
I mentioned the rusty patch bumble bee in monarchs.

370
00:24:54,000 --> 00:25:02,000
So all those species that were picked for that planting were focused on benefiting, you know, with those species in mind, you know, there's preferred.

371
00:25:02,000 --> 00:25:07,000
Natives out there for those species and those are all in that mix and stuff like that as well.

372
00:25:07,000 --> 00:25:10,000
Okay. And then.

373
00:25:10,000 --> 00:25:12,000
And then the.

374
00:25:12,000 --> 00:25:20,000
So we're looking for more stormwater capacity, which will take it away from runoff into the bluff, which goes into that.

375
00:25:20,000 --> 00:25:24,000
Sand seam that that's causing all of that.

376
00:25:24,000 --> 00:25:27,000
Bluff to fall.

377
00:25:27,000 --> 00:25:31,000
So that's the purpose of all of this upstream and downstream.

378
00:25:31,000 --> 00:25:35,000
Yeah, we want to slow the water down as much as we can and infiltrate as much as we can.

379
00:25:35,000 --> 00:25:37,000
Okay, thank you.

380
00:25:37,000 --> 00:25:42,000
You use the term woody, re spout, re sprout control.

381
00:25:42,000 --> 00:25:47,000
I assume that's just to keep those invasive species from growing back.

382
00:25:47,000 --> 00:25:48,000
How do you do that?

383
00:25:48,000 --> 00:25:51,000
Yeah. So we spray an herbicide over the foliar application.

384
00:25:51,000 --> 00:26:00,000
So on the on the leaves once they leaf out, we did treat stumps as well with low volume, just like a sponge on the end of a mop stick.

385
00:26:00,000 --> 00:26:04,000
Basically, and just treat the stump as we cut it.

386
00:26:04,000 --> 00:26:06,000
And some, some of them re sprout some don't.

387
00:26:06,000 --> 00:26:10,000
And then you're still just going to have seedlings popping up from the seed bank and stuff like that.

388
00:26:10,000 --> 00:26:14,000
So we just prevent that from coming back and let the Natives take over.

389
00:26:14,000 --> 00:26:19,000
And then eventually a lot of these areas will even get shaded out with just trees that we planted and stuff like that.

390
00:26:19,000 --> 00:26:24,000
So, and you did re sprout control for two years, two years on all of them, at least.

391
00:26:24,000 --> 00:26:33,000
And more re sprout control is needed. So when we think of this big project, you know, always be thinking about bringing more money to the project to continue that effort.

392
00:26:33,000 --> 00:26:36,000
Sure.

393
00:26:36,000 --> 00:26:45,000
So, for, because you have it up, the Walter Street ravine design concept, is that going to allow for a trail to continue with that?

394
00:26:45,000 --> 00:26:48,000
And would that be funded under this as well?

395
00:26:48,000 --> 00:26:55,000
Or would that have to be a separate grant or funded through city funds elsewhere?

396
00:26:55,000 --> 00:26:59,000
Yeah, this project, the bigger project keeps growing and scope and scale, which is great.

397
00:26:59,000 --> 00:27:05,000
You know, I want us to think big about this project and include everything that we want to do.

398
00:27:05,000 --> 00:27:10,000
So yes, ideally the stabilization would be would have a corresponding trail system.

399
00:27:10,000 --> 00:27:16,000
And we're internally thinking about what that would look like, whether or not we can fund it all at the same time.

400
00:27:16,000 --> 00:27:22,000
I don't know, that's where I introduced the concept of there's going to have to maybe be some phases to how we construct this project.

401
00:27:22,000 --> 00:27:31,000
But at least if we have a vision that the community and the city have bought into, then I can, you know, fund the project over time.

402
00:27:31,000 --> 00:27:34,000
Okay, thank you.

403
00:27:34,000 --> 00:27:36,000
Yeah, it kind of ties into my question.

404
00:27:36,000 --> 00:27:40,000
Have we thought about the long-term plan for the mountain bike trails that are already down there?

405
00:27:40,000 --> 00:27:47,000
Yeah, we met with the mountain bike trail crew a couple weeks ago to talk about all the different trails.

406
00:27:47,000 --> 00:27:51,000
There is going to be some impacts to their trail system from the grading.

407
00:27:51,000 --> 00:27:55,000
Also, some of the reamyandering of the stream is going to intersect some of their trails.

408
00:27:55,000 --> 00:28:00,000
They are thrilled, by the way, that we engage them and we spent time walking through the corridor

409
00:28:00,000 --> 00:28:02,000
and discussing what the trail system could look like.

410
00:28:02,000 --> 00:28:05,000
And they're really hopeful about kind of a new and improved trail system.

411
00:28:05,000 --> 00:28:09,000
And they're super jazzed about helping with this project.

412
00:28:10,000 --> 00:28:13,000
Thank you. Those bike trails are really cool down there in the middle of the city.

413
00:28:13,000 --> 00:28:14,000
Yeah.

414
00:28:16,000 --> 00:28:19,000
Right, are there any other comments or questions?

415
00:28:19,000 --> 00:28:21,000
All right, you have anything else?

416
00:28:21,000 --> 00:28:22,000
No, thank you.

417
00:28:22,000 --> 00:28:29,000
All right, that will move us in to item six.

418
00:28:29,000 --> 00:28:37,000
Consideration and possible action on a national fish and wildlife foundations sustain our Great Lakes grant application

419
00:28:37,000 --> 00:28:42,000
for a regenerative stormwater conveyance system in the Valley Creek watershed.

420
00:28:42,000 --> 00:28:43,000
Rob?

421
00:28:43,000 --> 00:28:48,000
Okay. All right. Yeah, Melissa and Ryan just touched on on this.

422
00:28:48,000 --> 00:28:52,000
This is part, this is an application that we have submitted.

423
00:28:52,000 --> 00:28:58,000
We haven't heard back yet whether we'll be invited to submit a full proposal,

424
00:28:58,000 --> 00:29:06,000
but we would like to apply what if we are invited for again for a grant to support

425
00:29:06,000 --> 00:29:11,000
the regenerative stormwater conveyance system.

426
00:29:11,000 --> 00:29:17,000
And again, that is for, oops, I want to make sure I got my right.

427
00:29:17,000 --> 00:29:21,000
$365,000 and again, that match.

428
00:29:21,000 --> 00:29:27,000
So we are, you can choose the match that you wish to submit as part of your application.

429
00:29:27,000 --> 00:29:35,000
We would use matching funds from both the advantage donation and the TID 5 budget.

430
00:29:35,000 --> 00:29:41,000
And so we are recommending that we do submit a full proposal if invited to do so.

431
00:29:41,000 --> 00:29:46,000
And again, this is for the Walter Street ravine that was just shown.

432
00:29:46,000 --> 00:29:50,000
Okay. Any comments or questions on the item?

433
00:29:50,000 --> 00:29:52,000
Just one small one.

434
00:29:52,000 --> 00:29:57,000
Is stand tech, not that it matters, but do they serve Ozaki County?

435
00:29:57,000 --> 00:30:02,000
Are they one of their clients or any other adjoining municipalities?

436
00:30:03,000 --> 00:30:10,000
Only a lot.

437
00:30:12,000 --> 00:30:15,000
Yeah, they work with, well, they'll tell you.

438
00:30:15,000 --> 00:30:19,000
Yeah, we've, is this on?

439
00:30:19,000 --> 00:30:23,000
We've done work with Ozaki County in the past.

440
00:30:23,000 --> 00:30:28,000
I'm not aware that we have any active projects with them, but I'm not 100% sure on that.

441
00:30:28,000 --> 00:30:32,000
We are the town engineer for the town of Grafton.

442
00:30:32,000 --> 00:30:40,000
We have, you know, over the years worked with numerous other municipalities in Ozaki County.

443
00:30:40,000 --> 00:30:41,000
Yeah.

444
00:30:41,000 --> 00:30:49,000
I was just looking to see about, you know, the whole picture, you know, farther upstream than our region below to the west.

445
00:30:49,000 --> 00:30:50,000
Yeah.

446
00:30:50,000 --> 00:30:52,000
Obviously to the Easters.

447
00:30:52,000 --> 00:30:53,000
Yeah.

448
00:30:53,000 --> 00:30:55,000
Yeah, yeah, definitely.

449
00:30:55,000 --> 00:31:03,000
Yeah, I mean, we did a Valley Creek watershed plan and, you know, looking at entire watersheds is definitely important.

450
00:31:03,000 --> 00:31:04,000
Yeah.

451
00:31:06,000 --> 00:31:13,000
Let's note the, the TIFF V property with the data center is the, is the headwaters of Valley Creek.

452
00:31:13,000 --> 00:31:24,000
So we do essentially have projects and control of the entire watershed of Valley Creek right now, which is, I think, pretty unique almost anywhere to have that control.

453
00:31:25,000 --> 00:31:26,000
Yeah.

454
00:31:26,000 --> 00:31:30,000
Any other comments or questions?

455
00:31:30,000 --> 00:31:34,000
Seeing none, I will entertain a motion on this item.

456
00:31:34,000 --> 00:31:37,000
I'll move to approve the staff recommendation.

457
00:31:37,000 --> 00:31:38,000
All right.

458
00:31:38,000 --> 00:31:39,000
We have a motion by Alderman Miller.

459
00:31:39,000 --> 00:31:40,000
Is there a second?

460
00:31:40,000 --> 00:31:41,000
I'll second that.

461
00:31:41,000 --> 00:31:45,000
Second by committee member Polly.

462
00:31:45,000 --> 00:31:49,000
Any comments, questions on the motion?

463
00:31:49,000 --> 00:31:52,000
Seeing none, all those in favor say aye.

464
00:31:52,000 --> 00:31:53,000
Aye.

465
00:31:53,000 --> 00:31:54,000
Opposed?

466
00:31:54,000 --> 00:31:55,000
Motion carries.

467
00:31:55,000 --> 00:31:56,000
All right.

468
00:31:56,000 --> 00:32:09,000
That moves us to item seven consideration and possible action on a national fish and wildlife foundation national coastal resiliency fund grant application for the Valley Creek corridor project.

469
00:32:09,000 --> 00:32:10,000
Okay.

470
00:32:10,000 --> 00:32:15,000
So, yes, these, these, so the National Fish and Wildlife Foundation, they have different.

471
00:32:16,000 --> 00:32:17,000
Grant opportunities.

472
00:32:17,000 --> 00:32:20,000
I just want to just talk about sustain our great lakes.

473
00:32:20,000 --> 00:32:23,000
This is the National Coastal Resiliency Fund.

474
00:32:23,000 --> 00:32:29,000
As Melissa said, we already have one grant from them and we're using that as our planning and engineering funding.

475
00:32:29,000 --> 00:32:32,000
So our major planning and funding.

476
00:32:32,000 --> 00:32:35,000
Funding for engineering.

477
00:32:35,000 --> 00:32:42,000
So this is, yes, this is for construction and we've been invited to submit a proposal, a full proposal.

478
00:32:43,000 --> 00:32:45,000
For up to $5 million.

479
00:32:45,000 --> 00:32:54,000
And so we're very excited about the opportunity to submit that proposal and the recommendation is that we.

480
00:32:54,000 --> 00:33:02,000
Do submit that proposal for $5 million towards construction.

481
00:33:02,000 --> 00:33:04,000
Love to see this come to fruition.

482
00:33:04,000 --> 00:33:07,000
So there is that we are going to submit it with a match.

483
00:33:07,000 --> 00:33:18,000
And we can use the, the vantage grant as part of that match in addition to the money that has been set aside and did five for this work.

484
00:33:18,000 --> 00:33:20,000
All right.

485
00:33:20,000 --> 00:33:23,000
Any questions or comments on this item?

486
00:33:23,000 --> 00:33:26,000
If not, it'll entertain a motion.

487
00:33:26,000 --> 00:33:29,000
I'll, I'll make the motion to approve.

488
00:33:29,000 --> 00:33:30,000
All right.

489
00:33:30,000 --> 00:33:32,000
We have a motion by committee member.

490
00:33:32,000 --> 00:33:34,000
Is there a second?

491
00:33:34,000 --> 00:33:36,000
Second by committee member Polly.

492
00:33:36,000 --> 00:33:39,000
Any questions or discussion on the motion?

493
00:33:39,000 --> 00:33:40,000
Seeing none.

494
00:33:40,000 --> 00:33:42,000
All those in favor say aye.

495
00:33:42,000 --> 00:33:43,000
Opposed?

496
00:33:43,000 --> 00:33:44,000
Motion carries.

497
00:33:44,000 --> 00:33:45,000
All right.

498
00:33:45,000 --> 00:33:47,000
That moves us to item eight.

499
00:33:47,000 --> 00:33:57,000
Presentation on stormwater management plan updates and the Northeast Lakeshore total maximum daily limits requirements and impacts to Port Washington.

500
00:33:57,000 --> 00:33:59,000
This is a discussion only item.

501
00:34:00,000 --> 00:34:02,000
Hi, I'm Aaron Volkening.

502
00:34:02,000 --> 00:34:10,000
I'm a water resources engineer with a stand tech have been working on this project with city staff.

503
00:34:10,000 --> 00:34:22,000
This is an update to the city wide stormwater management plan that was originally prepared around 2008 has not been updated since then.

504
00:34:23,000 --> 00:34:28,000
The city obtained a DNR grant to help fund this update.

505
00:34:28,000 --> 00:34:32,000
If you want to go to the next slide, Roger.

506
00:34:32,000 --> 00:34:36,000
This is sort of introducing this project tonight.

507
00:34:36,000 --> 00:34:42,000
My understanding is we will likely be back to talk about a couple of specific details of the project.

508
00:34:42,000 --> 00:34:45,000
There are some ordinance changes that are recommended.

509
00:34:45,000 --> 00:34:53,000
There is a full report 100 plus page report that's being finalized that I think you will get for review at some point.

510
00:34:53,000 --> 00:35:00,000
But I think you've been provided the executive summary in the meeting packet and just sort of want to introduce the project to you today.

511
00:35:00,000 --> 00:35:02,000
We start talking about this.

512
00:35:02,000 --> 00:35:11,000
I like to have everyone keep in mind the reasons for municipal stormwater management plan and why do we talk about stormwater management?

513
00:35:11,000 --> 00:35:20,000
I think it's important to remember that there's general reasons we do this and then there's specific regulations that the city has to follow.

514
00:35:20,000 --> 00:35:24,000
Most of you are probably familiar with the negative impacts of stormwater.

515
00:35:24,000 --> 00:35:30,000
Things like reduced water quality erosion, which you've certainly seen in some of the streams in the city.

516
00:35:30,000 --> 00:35:35,000
Flooding impacts on infrastructure and property and stuff like that.

517
00:35:35,000 --> 00:35:38,000
All good reasons to effectively manage stormwater.

518
00:35:38,000 --> 00:35:41,000
There's also regulatory requirements.

519
00:35:41,000 --> 00:35:49,000
The city has a discharge permit from the DNR, what's called an MS4 discharge permit that has certain requirements.

520
00:35:49,000 --> 00:35:56,000
That sort of flows down from the Clean Water Act, which is a federal law and then there's state administrative code.

521
00:35:56,000 --> 00:36:05,000
There's also some more recent sort of water quality regulations or water quality requirements called TMDLs or total maximum daily loads.

522
00:36:05,000 --> 00:36:07,000
I'll talk a little bit about tonight.

523
00:36:07,000 --> 00:36:08,000
Kind of keep that in mind.

524
00:36:08,000 --> 00:36:11,000
We're sort of doing this for two different broad reasons.

525
00:36:11,000 --> 00:36:16,000
We've got just sort of general good ideas and good practices.

526
00:36:16,000 --> 00:36:21,000
And then we've also got specific regulatory requirements that the city has to meet.

527
00:36:21,000 --> 00:36:23,000
Next slide.

528
00:36:23,000 --> 00:36:27,000
And the plan is sort of organized around two different frameworks.

529
00:36:27,000 --> 00:36:31,000
One of them is what we call minimum control measures.

530
00:36:32,000 --> 00:36:42,000
There's six different areas that the city program has to have according to its discharge permit relating to things like construction erosion control,

531
00:36:42,000 --> 00:36:53,000
management of runoff, after development, pollution prevention, which relates a lot to municipal operations and public works practices.

532
00:36:53,000 --> 00:36:59,000
Two different categories related to like public education and public outreach and involvement.

533
00:36:59,000 --> 00:37:06,000
And then also illicit discharge, which is when non storm water stuff is being dumped or discharged into the system.

534
00:37:06,000 --> 00:37:15,000
The other part of the project is a storm water quality analysis on different pollutant loads that are being generated by the storm storm water system.

535
00:37:15,000 --> 00:37:19,000
Next slide.

536
00:37:20,000 --> 00:37:27,000
We reviewed the current city plan in line with these minimum control measures that the permit requires that the city does.

537
00:37:27,000 --> 00:37:34,000
And there's a lot of positive things that the city has accomplished and can point to.

538
00:37:34,000 --> 00:37:39,000
The city has a lot of development going on right now as we all know.

539
00:37:39,000 --> 00:37:44,000
And several of these permit requirements relate to managing that development.

540
00:37:44,000 --> 00:37:50,000
I think in general that the city is doing a good job at that.

541
00:37:50,000 --> 00:38:00,000
As Rob has talked to you about, the city has made a big effort in reducing chloride use, salt use during the winter for snow and ice control.

542
00:38:00,000 --> 00:38:04,000
That chloride has some pretty significant water quality impacts.

543
00:38:04,000 --> 00:38:10,000
And I know that Rob is presented on the great progress that the city has made in that area.

544
00:38:10,000 --> 00:38:19,000
And that comes under the pollution prevention aspect of the permit, something that the city can point to as like a quantifiable change.

545
00:38:19,000 --> 00:38:30,000
You participate in a regional storm water education program led by what's called Sweet or the Southeastern Wisconsin Watershed Trust.

546
00:38:30,000 --> 00:38:34,000
I think they do a pretty good job at leading that.

547
00:38:34,000 --> 00:38:37,000
Public education and outreach is required by your permit.

548
00:38:37,000 --> 00:38:41,000
And a lot of communities choose to participate in that regional effort.

549
00:38:41,000 --> 00:38:47,000
You know, it's a lot more effective than you guys like developing a whole program on your own.

550
00:38:47,000 --> 00:38:54,000
You guys supplement it I think with some nice city specific things and then also participate in that regional program.

551
00:38:54,000 --> 00:38:57,000
You've recently purchased a couple new street sweepers.

552
00:38:57,000 --> 00:39:00,000
They are vacuum type sweepers.

553
00:39:01,000 --> 00:39:08,000
They're noticeably more efficient at removing material, picking it up compared to the older mechanical broom type sweepers.

554
00:39:08,000 --> 00:39:16,000
And you're able to get some numeric pollutant reduction credit because of that change in street super equipment.

555
00:39:16,000 --> 00:39:26,000
And then finally, as we've heard tonight, the city has some really comprehensive multi-benefit programs and investments.

556
00:39:26,000 --> 00:39:33,000
They're making in different areas in the city, different watersheds and different water bodies like the Valley Creek Project.

557
00:39:33,000 --> 00:39:36,000
And there's a lot of different benefits as you've heard tonight.

558
00:39:36,000 --> 00:39:39,000
One of those is storm water management.

559
00:39:39,000 --> 00:39:41,000
Next slide.

560
00:39:41,000 --> 00:39:46,000
We do have some recommendations related to these minimum control measures.

561
00:39:46,000 --> 00:39:55,000
There's some ordinance changes are recommended to sort of bring parts of the ordinance in line with current state and federal regulations.

562
00:39:55,000 --> 00:40:02,000
And also sort of reflect how the existing ordinances have worked and what could be improved.

563
00:40:02,000 --> 00:40:09,000
So I think that's something my understanding is we'll probably be bringing forward in more detail at a future date.

564
00:40:09,000 --> 00:40:18,000
The DNR is placing an increased emphasis on inspection and maintenance of privately owned storm water BMPs.

565
00:40:19,000 --> 00:40:25,000
Not that the city has to fully do that, but private owners are supposed to be doing that.

566
00:40:25,000 --> 00:40:30,000
And over time that the DNR is going to look for more record keeping on that.

567
00:40:30,000 --> 00:40:37,000
We definitely recommend continuing to participate in this regional public education and outreach program.

568
00:40:37,000 --> 00:40:45,000
There's potentially some changes that could be made to municipal leaf management.

569
00:40:46,000 --> 00:40:50,000
Related to meeting these TMDL requirements that I'll talk a little bit about.

570
00:40:50,000 --> 00:40:57,000
And then just some administrative procedures related to how permits are handled and stuff like that.

571
00:40:57,000 --> 00:40:59,000
Next slide.

572
00:40:59,000 --> 00:41:03,000
The other part was a storm water quality analysis.

573
00:41:03,000 --> 00:41:10,000
We use computer models, computer software to estimate the runoff that's being generated in the city system.

574
00:41:11,000 --> 00:41:20,000
Certain pollutants, things like what we call total suspended salads, phosphorus, which is a, you know, some phosphorus is essential of a life.

575
00:41:20,000 --> 00:41:29,000
But in general, urban storm water has too much phosphorus that causes things like algae blooms, you know, decreased water clarity, stuff like that.

576
00:41:29,000 --> 00:41:33,000
We compare those pollutant loads to regulatory requirements.

577
00:41:33,000 --> 00:41:37,000
And then we look at some strategies or some projects to reduce those pollutant loads.

578
00:41:37,000 --> 00:41:41,000
So next slide.

579
00:41:41,000 --> 00:41:46,000
I mentioned this idea of a TMDL or a total maximum daily load.

580
00:41:46,000 --> 00:41:58,000
And that's a water quality plan or a water quality, you know, sort of a regulatory requirement that is done by the state and it's approved by the EPA.

581
00:41:59,000 --> 00:42:09,000
And the idea is that they look at water bodies that are said to be polluted or they're not fully meeting their water quality standards.

582
00:42:09,000 --> 00:42:19,000
And they figure out, okay, you know, what's the maximum amount of pollutant loads that water body that we could allow and still meet those water quality requirements.

583
00:42:20,000 --> 00:42:30,000
They compare that to, you know, what we think the current loads going to that water body actually are that's based on monitoring field measurements as well as modeling.

584
00:42:30,000 --> 00:42:39,000
And often what we find is that the allowable or the target pollutant loads are generally lower than the current discharges.

585
00:42:39,000 --> 00:42:45,000
So, you know, too much pollution is being discharged and oftentimes they're much lower.

586
00:42:46,000 --> 00:42:52,000
The idea behind a TMDL is that it's supposed to be water body specifics.

587
00:42:52,000 --> 00:42:56,000
You're supposed to look at actual conditions in that water body.

588
00:42:56,000 --> 00:42:59,000
There are some older regulations that are sort of more blanket.

589
00:42:59,000 --> 00:43:08,000
Like, if you know anything about stormwater regulations, there's a statewide requirement for 20% suspended salvage reduction.

590
00:43:08,000 --> 00:43:14,000
New development has like, you know, sort of blanket statewide reduction requirements.

591
00:43:14,000 --> 00:43:22,000
And, you know, there was a thought that, you know, those don't really necessarily always reflect what's really going on in an individual water body.

592
00:43:22,000 --> 00:43:25,000
So, the TMDLs are more water body focused.

593
00:43:25,000 --> 00:43:31,000
If we do see this gap, then permit holders like the city has its MS4 permit.

594
00:43:31,000 --> 00:43:37,000
You know, wastewater treatment plants have permits, certain, you know, industrial plants have permits.

595
00:43:37,000 --> 00:43:39,000
They have to make reductions in the future.

596
00:43:39,000 --> 00:43:45,000
The city is in two TMDLs right now, the Milwaukee River TMDL and the Northeast Lakeshore TMDL.

597
00:43:45,000 --> 00:43:48,000
And if you want to go to the next slide, Roger.

598
00:43:48,000 --> 00:43:51,000
The Milwaukee River TMDL is a little bit earlier or a little bit older.

599
00:43:51,000 --> 00:43:54,000
It was became effective in 2018.

600
00:43:54,000 --> 00:44:03,000
It requires total suspended salads or TSS and phosphorus reductions from two different drainage basins in the city.

601
00:44:04,000 --> 00:44:06,000
Might be able to see them and purple there.

602
00:44:06,000 --> 00:44:13,000
So, these are the areas of the city that drain towards the Milwaukee River rather than more directly to Lake Michigan.

603
00:44:13,000 --> 00:44:18,000
You know, it's, you know, not a real large part of the city.

604
00:44:18,000 --> 00:44:21,000
You know, more of the city drains more directly to Lake Michigan.

605
00:44:21,000 --> 00:44:27,000
But there were pollutant reduction requirements that are needed to meet this TMDL.

606
00:44:27,000 --> 00:44:31,000
The good news is that the city is currently meeting these requirements now.

607
00:44:31,000 --> 00:44:36,000
That's partly a result of how past development in these areas were managed.

608
00:44:36,000 --> 00:44:43,000
You know, these are some of the newer, you know, developed areas of the city where you were putting in stormwater ponds

609
00:44:43,000 --> 00:44:46,000
and stormwater treatment practices as they were developing.

610
00:44:46,000 --> 00:44:52,000
And then the city has also done a couple of recent projects to boost that pollutant removal even more.

611
00:44:52,000 --> 00:44:57,000
You did a retrofit at a stormwater pond in the Misty Ridge area.

612
00:44:57,000 --> 00:45:00,000
There was some infiltration testing that was done.

613
00:45:00,000 --> 00:45:08,000
And so the good news is that it has all helped these TMDL requirements to come to be met for the Milwaukee River TMDL.

614
00:45:08,000 --> 00:45:10,000
If you want to go to the next slide.

615
00:45:10,000 --> 00:45:17,000
The Northeast Lakeshore TMDL covers most of the city there.

616
00:45:17,000 --> 00:45:22,000
And it became effective in October of 2023.

617
00:45:23,000 --> 00:45:35,000
And, you know, sort of the not so good news is that there's a long ways to go to meet some of these pollutant reduction requirements for TSS and phosphorus.

618
00:45:35,000 --> 00:45:39,000
It's divided up into a couple different drainage areas.

619
00:45:39,000 --> 00:45:44,000
There's Salt Creek and Mineral Spring Creek are kind of lumped together there.

620
00:45:45,000 --> 00:45:50,000
Valley Creek and some areas that drain directly to Lake Michigan or hand a little bit separately.

621
00:45:50,000 --> 00:45:54,000
But, you know, the exact numbers aren't super important at this point.

622
00:45:54,000 --> 00:46:03,000
But what's important is that there's a big gap between what the TMDL says is ultimately allowable and what's that right now.

623
00:46:03,000 --> 00:46:06,000
If you want to flip to the next slide.

624
00:46:07,000 --> 00:46:20,000
You know, a challenge, I guess one of my key messages for tonight is we want to start thinking about how to meet this because it's going to be a long process and that's okay.

625
00:46:20,000 --> 00:46:22,000
But it's going to be a challenge.

626
00:46:22,000 --> 00:46:31,000
One of the challenges is that the TMDL requires you to figure out how to reduce pollutant loads from already developed areas.

627
00:46:32,000 --> 00:46:37,000
So, you know, new development has its stormwater management requirements.

628
00:46:37,000 --> 00:46:41,000
So like when the data center came in, they have to do very stringent stormwater management.

629
00:46:41,000 --> 00:46:48,000
When a residential subdivision comes in, they have to meet stringent stormwater management and stormwater treatment requirements.

630
00:46:48,000 --> 00:46:56,000
But the TMDL requires you to go back to areas that are already developed and figure out how to do stormwater in those areas.

631
00:46:57,000 --> 00:47:07,000
And if you have a dense area like downtown Port Washington or even some of the older residential areas, how do you fit stormwater treatment?

632
00:47:07,000 --> 00:47:10,000
So on the left, I've got a picture of downtown.

633
00:47:10,000 --> 00:47:12,000
On the right, I guess you can't see it very well.

634
00:47:12,000 --> 00:47:20,000
But it's a picture, an aerial photo of the Hidden Hills area, which is in the Milwaukee TMDL, which meets that TMDL requirement.

635
00:47:20,000 --> 00:47:24,000
Hidden Hills has a lot of green space that's devoted to stormwater management.

636
00:47:24,000 --> 00:47:30,000
So it's got ponds, it's got infiltration swales, it's got infiltration basins and constructed wetlands.

637
00:47:30,000 --> 00:47:37,000
So, you know, when you do new development or when you have low density residential development, you can do something like that.

638
00:47:37,000 --> 00:47:41,000
You know, how do you treat stormwater in a more densely developed area?

639
00:47:41,000 --> 00:47:43,000
That's a big challenge.

640
00:47:43,000 --> 00:47:44,000
Next slide.

641
00:47:45,000 --> 00:48:00,000
This slide talks about some different options for different practices and the types of pollutant removals you can see.

642
00:48:00,000 --> 00:48:03,000
I think I'm going to skip over this for now.

643
00:48:03,000 --> 00:48:06,000
We can come back to this if we need to.

644
00:48:06,000 --> 00:48:14,000
The good news is that, you know, the regulators like the DNR and the EPA recognize that this is going to be a hard thing to do.

645
00:48:14,000 --> 00:48:20,000
And, you know, honestly, fully meeting these TMDL requirements is probably going to take decades.

646
00:48:20,000 --> 00:48:23,000
You know, that's the sort of timeframe we're talking about.

647
00:48:23,000 --> 00:48:32,000
So, you know, the city is not required to immediately comply with these requirements or comply with them in the short term.

648
00:48:32,000 --> 00:48:39,000
You know, so that's, you know, how often do you have a regulatory requirement, you know, but you're told you have decades to meet this.

649
00:48:39,000 --> 00:48:43,000
I mean, that's a little unusual and that's good because it's going to be challenging.

650
00:48:43,000 --> 00:48:48,000
But what the regulators are going to want to see is they're going to want to see regular progress.

651
00:48:48,000 --> 00:48:54,000
You know, they're going to want to see quantifiable actions, you know, that are definitive things you're doing.

652
00:48:55,000 --> 00:49:05,000
What happens is that these TMDL requirements get written into your discharge permit and the DNR sets like interim goals for you.

653
00:49:05,000 --> 00:49:13,000
We're still waiting on a reissue of the sort of general stormwater statewide permit that the city falls under.

654
00:49:13,000 --> 00:49:16,000
That was supposed to have been out by now.

655
00:49:16,000 --> 00:49:18,000
I have not seen a draft of it.

656
00:49:18,000 --> 00:49:24,000
I think it's supposed to come at some point this year and that might have some more specifics on, you know, more details of the implementation.

657
00:49:24,000 --> 00:49:30,000
But in that permit is going to be, you know, some specific milestones for interim progress.

658
00:49:30,000 --> 00:49:32,000
Next slide.

659
00:49:35,000 --> 00:49:36,000
Last slide here.

660
00:49:36,000 --> 00:49:47,000
You know, so we've started to look at and, you know, in the future, what we want to discuss is different ways to start achieving these pollutant reductions.

661
00:49:47,000 --> 00:49:51,000
And these are some broad categories. So one is green infrastructure.

662
00:49:51,000 --> 00:49:56,000
We talked about the regenerative stormwater conveyance systems that falls into that.

663
00:49:56,000 --> 00:50:02,000
A pretty common thing is what we call bioretension areas or bioswales.

664
00:50:02,000 --> 00:50:11,000
Very similar to rain gardens, you know, often built along streets now, you know, on the terrorist area, perhaps in medians, stuff like that.

665
00:50:11,000 --> 00:50:15,000
There's other kinds of green infrastructure too that can be effective.

666
00:50:15,000 --> 00:50:25,000
Underground treatment, you see a couple of pictures here, you know, sometimes if land is, you know, in short supply, people might build underground stormwater treatment.

667
00:50:25,000 --> 00:50:27,000
Something that we could look at.

668
00:50:27,000 --> 00:50:40,000
We've had some discussions with city staff is, you know, looking at parcels of land that, you know, maybe you're vacant right now, you know, or have a spot in them that's not being used, you know, could have used for stormwater treatment.

669
00:50:41,000 --> 00:50:50,000
The DNR gives you some credit for phosphorus reduction. If you have certain things you do with your municipal leaf management program.

670
00:50:50,000 --> 00:51:01,000
So that would be a future possibility. A big one of the big requirements is that when residents, you know, put out their leaves, they don't put them in the street.

671
00:51:02,000 --> 00:51:11,000
They have to put them on the terrace, you know, so in the grass behind the curb, and then the city crews have to come up and take them off the terrace when they collect them.

672
00:51:11,000 --> 00:51:16,000
So that would be a change, you know, people, you know, not everyone would like that change, I guess.

673
00:51:16,000 --> 00:51:24,000
You know, but the idea is that you're not having all those leaves, those dead leaves, which generate a lot of phosphorus.

674
00:51:24,000 --> 00:51:33,000
Some research has shown that, you know, up more than 50% of the annual phosphorus load comes during that fall, you know, sort of leaf off period.

675
00:51:33,000 --> 00:51:40,000
The idea is that all those leaves are not sitting in the street, you know, just being rained on whenever it rains in the fall and immediately washing downstream.

676
00:51:40,000 --> 00:51:47,000
There's also certain requirements for like the frequency that you would collect those leaves and, you know, street the suite.

677
00:51:47,000 --> 00:51:50,000
And the report is going to have some more discussion of that.

678
00:51:51,000 --> 00:51:54,000
You could do retrofits of your existing stormwater facilities.

679
00:51:54,000 --> 00:51:59,000
That's something we did at Misty Ridge Pond to meet the Milwaukee River TMDL requirements.

680
00:51:59,000 --> 00:52:09,000
There's something called water quality trading, which is where you would work with someone else, like a lot of times this is done with an agricultural landowner.

681
00:52:09,000 --> 00:52:17,000
And you would, you would pay them or you would cooperate with them in some fashion to do something where they would reduce phosphorus on their land.

682
00:52:17,000 --> 00:52:26,000
And you would get some credit for it. The idea behind water quality trading is that sometimes fast reproduction and agricultural land is kind of a low hanging fruit.

683
00:52:26,000 --> 00:52:41,000
You know, and it's often like if you look at a cost per pound of phosphorus removed, oftentimes the least costly way to do that is to do some changes in agricultural, you know, farming areas.

684
00:52:42,000 --> 00:52:53,000
But, you know, the city does not, you know, you're not, you don't own a farm. So you can't directly say, you know, you're going to make a change, but the water quality trading program allows allows for that.

685
00:52:53,000 --> 00:52:56,000
So I think that's it. Is that the last slide?

686
00:53:00,000 --> 00:53:06,000
Yep. So, you know, happy to talk about it tonight. I mean, I could talk for this about an hour.

687
00:53:06,000 --> 00:53:17,000
I think we'll be back to talk about more details, but, you know, wanted to introduce this to you tonight and get everyone thinking about it and introduce to the plan update and the TMDL concept and so forth.

688
00:53:19,000 --> 00:53:23,000
All right. Thank you. Any comments? Yes.

689
00:53:24,000 --> 00:53:32,000
What is the, what is the monitoring program for ensuring you're within specs and your TMDL? Is it that you just take a sample of water every so often?

690
00:53:32,000 --> 00:53:34,000
Or how do we know that we're actually compliant?

691
00:53:35,000 --> 00:53:46,000
Yeah. The, the DNR does a lot of monitoring and, you know, other groups like the city or volunteer groups can also monitor.

692
00:53:46,000 --> 00:53:53,000
There's actually a DNR database called the, I think it's called the swims database where all this monitor monitoring data gets looked up.

693
00:53:53,000 --> 00:54:12,000
So, so they did monitoring when they developed the TMDLs and then they, they continue to do it. And I'm glad you asked the question because the way that a, the way that a TMDL ultimately ends is if monitoring shows that the water quality has improved enough.

694
00:54:12,000 --> 00:54:22,000
So like, you know, what, what occasionally happens is that, you know, the, the, the water quality monitoring trends gets better.

695
00:54:22,000 --> 00:54:28,000
And, you know, you may not have done all the BMPs that you said you're going to do, but maybe you've made some progress.

696
00:54:28,000 --> 00:54:38,000
And if, if there are other things happening in the watershed and the monitoring shows that the quality has gotten better than that TMDL will ultimately end.

697
00:54:38,000 --> 00:54:51,000
On the other hand, if you are, you know, doing BMPs, changing practices, but the monitoring data just isn't showing a change, then, you know, that TMDL is not going to end.

698
00:54:51,000 --> 00:55:03,000
I mean, you know, you're not going to be in trouble necessarily, but everyone's going to have to come together and say, you know, we thought we were doing some stuff that was going to help the monitoring data is not reflecting it.

699
00:55:03,000 --> 00:55:07,000
You know, what do we do next?

700
00:55:07,000 --> 00:55:18,000
Okay. And then also, do the, do the things they're looking for ever evolved, like, mainly fast for us, but would they ever come and say, like, we want to look at PFAS now or something or is it pretty well set?

701
00:55:18,000 --> 00:55:33,000
I potentially, but, but from what we've seen so far in Wisconsin, once they publish a TMDL, the, the pollutants that are covered in it stay pretty fixed.

702
00:55:33,000 --> 00:55:43,000
I mean, you know, they're, they're working on regulations related to, like, new chemicals and stuff like that, PFAS, microplastics, stuff like that.

703
00:55:43,000 --> 00:55:49,000
That, that will probably happen outside of the TMDL framework, though.

704
00:55:49,000 --> 00:55:59,000
You know, what, what they try for, you know, total suspended salads is one of the pollutants that, that are regulated and that you're supposed to reduce.

705
00:55:59,000 --> 00:56:03,000
And because they found that a lot of pollutants get attached to those salads.

706
00:56:03,000 --> 00:56:07,000
And so, you know, salads by themselves are not necessarily a bad thing.

707
00:56:07,000 --> 00:56:12,000
Like, you know, if you've got clean sand or clean silt or whatever, you know, a moderate amount of it is, is okay.

708
00:56:12,000 --> 00:56:16,000
But what they found is that pollutants attached to those salads.

709
00:56:16,000 --> 00:56:21,000
And the idea is that by managing those salads, you're managing a lot of other pollutants too.

710
00:56:21,000 --> 00:56:27,000
Like metals is another one that, you know, we know that, that certain kinds of metals in storm water are a problem.

711
00:56:27,000 --> 00:56:36,000
There's usually not TMDLs for metals because we assume that by managing that TSS, we're also, you know, sort of attacking that metal source.

712
00:56:36,000 --> 00:56:37,000
Thank you.

713
00:56:37,000 --> 00:56:38,000
Yeah.

714
00:56:38,000 --> 00:56:43,000
Yeah. One of the other ones that we see is bacteria that, that we have to monitor for.

715
00:56:43,000 --> 00:56:45,000
Yep.

716
00:56:45,000 --> 00:56:55,000
So in a rain event, if you look at saw Creek, you'll often notice that there's a, I presume a lot of suspended salads,

717
00:56:55,000 --> 00:57:01,000
silty suspended salads coming from outside the city coming through is.

718
00:57:01,000 --> 00:57:12,000
Will you be including recommendations at all for dealing besides, you know, the trading TMDLs stuff for waterways like that coming into the city?

719
00:57:12,000 --> 00:57:28,000
Because we do have some people to their concerned that live along the creek are concerned about erosion from it and anything that would also mitigate flooding on saw Creek coming into the city probably as beneficial to other property owners in the city.

720
00:57:28,000 --> 00:57:29,000
Yeah.

721
00:57:29,000 --> 00:57:33,000
You know, areas outside of the outside of the city. I know that.

722
00:57:33,000 --> 00:57:38,000
You know, Ozaki County does some work in various watersheds.

723
00:57:38,000 --> 00:57:48,000
The, in a TMDL, every discharger of pollutants is supposed to make similar reductions.

724
00:57:48,000 --> 00:57:59,000
You know, the idea is they try to treat people fairly. So the, there is also like an agricultural load reduction requirement.

725
00:57:59,000 --> 00:58:18,000
The, the issue is that the mechanism for actually making people reduce those agricultural loads, there's just, there's not as much leverage there, to be honest, like, you know, most, unless they're a CAFO, you know, most agricultural land does not have a discharge permit.

726
00:58:18,000 --> 00:58:24,000
A lot of them do have nutrient management plans, you know, which a lot of farmers have been good about developing and following.

727
00:58:24,000 --> 00:58:33,000
But there, TMDLs do say that this, this sediment and phosphorus load from agricultural land is supposed to happen.

728
00:58:33,000 --> 00:58:40,000
To be honest, you know, right now there's not as much regulatory leverage to try to force that to happen.

729
00:58:40,000 --> 00:58:53,000
That's one reason for the water quality trading requirement is that, you know, maybe as a watershed, you know, the most cost effective way to do it might be to try to, try to change management and some of that.

730
00:58:53,000 --> 00:59:03,000
Yeah, about 25 years ago, Zaki County tried to implement an ordinance that would have forced farmers to keep grass drips along waterways.

731
00:59:03,000 --> 00:59:08,000
And there was a very strong pushback against that and the county abandoned it.

732
00:59:08,000 --> 00:59:15,000
Yeah, it, it, it honestly goes back to the Clean Water Act, which, you know, I think originally is from like 1970 or something like that.

733
00:59:15,000 --> 00:59:23,000
There was a political decision not to treat agricultural land that the same as urban land.

734
00:59:23,000 --> 00:59:27,000
And, and there's, you know, probably like both sides of this year to that.

735
00:59:27,000 --> 00:59:30,000
But, you know, that's sort of the, the political and legal reality.

736
00:59:30,000 --> 00:59:34,000
Okay. Any other comments, questions?

737
00:59:34,000 --> 00:59:36,000
All right.

738
00:59:36,000 --> 00:59:39,000
Mike, can I just run there a little bit on water quality?

739
00:59:39,000 --> 00:59:51,000
If I'm wrong, Aaron, but so one of the issues with water quality training could be the most paying for your buck, but you're taking city taxpayer dollars training it on the town.

740
00:59:51,000 --> 00:59:58,000
The other thing is if the stream is not so improvement, then you're still on the hook for doing improvements in your own city.

741
00:59:58,000 --> 00:59:59,000
Am I correct that?

742
00:59:59,000 --> 01:00:00,000
Yeah.

743
01:00:00,000 --> 01:00:01,000
Yeah.

744
01:00:01,000 --> 01:00:03,000
So, so we lose either way.

745
01:00:03,000 --> 01:00:06,000
It's not a panacea, but it is, it is a tool.

746
01:00:06,000 --> 01:00:13,000
On the other hand, if, if they're like, let's say there's a big area of erosion upstream that, that truly is the biggest problem.

747
01:00:13,000 --> 01:00:21,000
If you were to tackle that, you know, the monitoring data might show that, that, you know, might make a noticeable difference like you were asking about.

748
01:00:21,000 --> 01:00:29,000
So, as far as the monitoring goes, do you, like the specific sites for monitoring?

749
01:00:29,000 --> 01:00:33,000
Do you monitor the stream before it enters the city of Port Washington?

750
01:00:33,000 --> 01:00:40,000
The city of Port Washington to see what's coming into the city prior to leaving the city?

751
01:00:40,000 --> 01:00:44,000
Like, how do you?

752
01:00:44,000 --> 01:00:53,000
Yeah, the, the DNR does the monitoring and they kind of decide, you know, where, where they think the appropriate monitoring points are.

753
01:00:54,000 --> 01:00:56,000
You, you could do additional monitoring.

754
01:00:56,000 --> 01:01:04,000
I mean, I've heard of communities doing that to try to make the case that, hey, the, the pollutant load is not coming from us or whatever.

755
01:01:04,000 --> 01:01:13,000
You know, it, it is a possibility, perhaps, you know, getting, getting more data to show that the watershed is behaving in a certain way.

756
01:01:17,000 --> 01:01:19,000
Any other questions?

757
01:01:19,000 --> 01:01:20,000
All right.

758
01:01:20,000 --> 01:01:21,000
Thank you.

759
01:01:22,000 --> 01:01:23,000
All right.

760
01:01:23,000 --> 01:01:30,000
They'll bring us then to item nine, consideration and possible action on a utility service agreement with the village of Sockville.

761
01:01:30,000 --> 01:01:31,000
Roger.

762
01:01:31,000 --> 01:01:32,000
Roger.

763
01:01:46,000 --> 01:01:54,000
So, we're working on our sanitary sewer service area, which, let me zoom out a little bit on this map.

764
01:02:01,000 --> 01:02:07,000
You know, which is largely depicted here.

765
01:02:07,000 --> 01:02:10,000
It's a sanitary sewer service area.

766
01:02:10,000 --> 01:02:16,000
What that, what that basically is, is that, that's areas where the city's thinking it's going to grow into it.

767
01:02:16,000 --> 01:02:19,000
It's provide sanitary services to it.

768
01:02:19,000 --> 01:02:26,000
Sewer pack looks at that area and they look at environmental issues and, and whatnot to make sure.

769
01:02:26,000 --> 01:02:38,000
So then, so then when you do actually develop a piece of this land, you'll, you submit your sanitary sewer extension permits, the sewer pack for what's called a 208 letter.

770
01:02:38,000 --> 01:02:43,000
They say, yes, it's in the sanitary sewer service area. We've, we've checked it out.

771
01:02:43,000 --> 01:02:49,000
We've, we've, we know it's not going to create an environmental impact and they for that, the DNR.

772
01:02:49,000 --> 01:02:59,000
So, so that's, that's the purpose behind it is just to make sure that, that you're growing in a kind of responsible manner.

773
01:02:59,000 --> 01:03:06,000
So, obviously, the stuff on the snore side that that's triggered by, by the data center development.

774
01:03:06,000 --> 01:03:11,000
And, and so we're looking at like, hey, these blue areas are canalsville.

775
01:03:11,000 --> 01:03:13,000
So we agreed to provide sanitary sewer.

776
01:03:14,000 --> 01:03:17,000
And that was already in our sanitary sewer service area.

777
01:03:17,000 --> 01:03:22,000
But as we, we've talked in here as what we're going to need to serve canalsville.

778
01:03:22,000 --> 01:03:26,000
We're going to have to put some lift stations in because of some sort of line areas.

779
01:03:26,000 --> 01:03:34,000
And when we do that, it's just logical then to include the next uphill area to come into that lift station.

780
01:03:35,000 --> 01:03:37,000
And that kind of expands our sanitary sewer service area.

781
01:03:37,000 --> 01:03:43,000
And we kind of look at what, what might, what might see development in 20 years.

782
01:03:43,000 --> 01:03:44,000
That's kind of working out.

783
01:03:44,000 --> 01:03:47,000
We're not thinking that this whole area is going to grow in 20 years.

784
01:03:47,000 --> 01:03:51,000
But, but there might be a something that happens up here.

785
01:03:51,000 --> 01:03:53,000
There might be something that happens over here.

786
01:03:53,000 --> 01:03:55,000
We need to get it incorporated.

787
01:03:55,000 --> 01:03:58,000
But we're not just growing on the north end.

788
01:03:58,000 --> 01:04:02,000
We're also growing.

789
01:04:02,000 --> 01:04:05,000
Well, I guess this is, this would also be considered north.

790
01:04:05,000 --> 01:04:10,000
But over here, this is the simplicity proven grounds area.

791
01:04:10,000 --> 01:04:14,000
You know, we can anticipate growth in there.

792
01:04:14,000 --> 01:04:18,000
And then what this presentation or agreement is here is.

793
01:04:18,000 --> 01:04:23,000
In this area, we also have developers calling us about developing land.

794
01:04:23,000 --> 01:04:26,000
And we're fighting up against sockville.

795
01:04:27,000 --> 01:04:32,000
So as some of you may be aware, maybe all of you are aware.

796
01:04:32,000 --> 01:04:39,000
A while back ago that the Shannon farm area, which is along highway 33.

797
01:04:39,000 --> 01:04:42,000
That's in the city's corporate limits.

798
01:04:42,000 --> 01:04:47,000
That was in sockville sanitary sewer service area.

799
01:04:47,000 --> 01:04:53,000
And result as, as for the city to develop that property.

800
01:04:54,000 --> 01:04:56,000
They get it into our sanitary sewer service area.

801
01:04:56,000 --> 01:05:01,000
We essentially paid sockville $100,000 to make it happen.

802
01:05:01,000 --> 01:05:08,000
So what this agreement is doing is saying, hey, here's where the city thing is.

803
01:05:08,000 --> 01:05:12,000
It's going to grow.

804
01:05:12,000 --> 01:05:20,000
Men here.

805
01:05:21,000 --> 01:05:24,000
I mean, so sockville's got their growth in mind.

806
01:05:24,000 --> 01:05:26,000
And so it's basically we're button up.

807
01:05:26,000 --> 01:05:29,000
And if you ladies two together, they would fit like a puzzle pieces.

808
01:05:29,000 --> 01:05:33,000
We've coordinated with them that we're not overlapping any lands.

809
01:05:33,000 --> 01:05:49,000
But what the agreement is going to say is, hey, if somebody over in this corner wants to be in poor Washington, for whatever reason, most likely is because it can be less expensive for them to get sewer for poor Washington.

810
01:05:50,000 --> 01:05:52,000
The exchange is just going to happen.

811
01:05:52,000 --> 01:05:54,000
We will do it cooperatively.

812
01:05:54,000 --> 01:06:00,000
We're not going to fight each other on who gets that development.

813
01:06:00,000 --> 01:06:08,000
So that's the purpose of this agreement.

814
01:06:08,000 --> 01:06:13,000
So this is the village of sockville, not the town of sockville we're talking about.

815
01:06:13,000 --> 01:06:14,000
Correct.

816
01:06:15,000 --> 01:06:38,000
All right, so the agreement basically leaves it then that it would both municipalities, it would be up to them to if a request is made to determine that it is not economically viable for them to service this area and thus agree to the swap.

817
01:06:39,000 --> 01:06:44,000
What teeth does that have that it has to actually be economically viable?

818
01:06:44,000 --> 01:06:49,000
And one side or the other couldn't just drag their feet on it and just say, no, we're absolutely not giving that up.

819
01:06:49,000 --> 01:06:59,000
No matter what does it, I'm just asking, does this, it's a nice, it's a nice idea that this has a cooperative agreement.

820
01:06:59,000 --> 01:07:07,000
Does it really do anything if one side or the other just decides that the other is not going to pay attention to it anymore?

821
01:07:08,000 --> 01:07:15,000
Chris Smith from VONBRIZEN will be presenting the council on the subject next week.

822
01:07:15,000 --> 01:07:25,000
He probably can answer that one better than I can, but essentially what I've been told a lot of municipal agreements are relatively easy to break.

823
01:07:25,000 --> 01:07:26,000
Yeah.

824
01:07:26,000 --> 01:07:29,000
But we just figured it's a first step.

825
01:07:29,000 --> 01:07:34,000
It puts it in writing, hopefully future councils and everybody say, yeah, this just makes sense.

826
01:07:34,000 --> 01:07:39,000
Development in the region benefits both communities.

827
01:07:39,000 --> 01:07:40,000
No.

828
01:07:40,000 --> 01:07:44,000
No, I agree that the agreements are a good idea to have.

829
01:07:44,000 --> 01:07:49,000
I'm just skeptical that when push comes to shove, it's going to hold up.

830
01:07:49,000 --> 01:07:51,000
But I hope to be proven wrong.

831
01:07:53,000 --> 01:07:56,000
Any other questions or comments?

832
01:07:56,000 --> 01:08:01,000
Seeing none, I will entertain a motion on this item.

833
01:08:02,000 --> 01:08:04,000
I'll make the motion to approve.

834
01:08:04,000 --> 01:08:06,000
So we got a motion by Alderman Miller.

835
01:08:06,000 --> 01:08:07,000
Is there a second?

836
01:08:07,000 --> 01:08:08,000
Second.

837
01:08:08,000 --> 01:08:10,000
Second by Alderman Beaster.

838
01:08:10,000 --> 01:08:13,000
Any discussion on the motion?

839
01:08:13,000 --> 01:08:15,000
Seeing none, all those in favor say aye.

840
01:08:15,000 --> 01:08:16,000
Aye.

841
01:08:16,000 --> 01:08:17,000
Opposed?

842
01:08:17,000 --> 01:08:19,000
Motion carries.

843
01:08:19,000 --> 01:08:20,000
All right.

844
01:08:20,000 --> 01:08:30,000
That moves us to item 10, consideration and possible action on a proposal from hydrocorp to continue to complete cross connection control services.

845
01:08:30,000 --> 01:08:35,000
All right.

846
01:08:35,000 --> 01:08:45,000
A cross connection control program is required by the DNR for all water, municipal or water utilities.

847
01:08:45,000 --> 01:08:59,000
Hydrocorp has been contracted by the city for almost 15 years now to basically manage the industrial commercial aspect of our cross connection program.

848
01:09:00,000 --> 01:09:04,000
So this is basically a proposal to renew our contract with them.

849
01:09:04,000 --> 01:09:07,000
Our previous contract was for two years.

850
01:09:07,000 --> 01:09:10,000
We're looking at extending this into four years.

851
01:09:10,000 --> 01:09:13,000
Just so we don't have to come back every two years to do this.

852
01:09:13,000 --> 01:09:20,000
Basically, right now they manage over 450 connections, if you will.

853
01:09:20,000 --> 01:09:26,000
That's 450 businesses.

854
01:09:27,000 --> 01:09:33,000
The city of Port has quite a few facilities that meet this requirement.

855
01:09:33,000 --> 01:09:37,000
So basically everybody in the city that has a potential cross connection.

856
01:09:37,000 --> 01:09:47,000
Hydrocorp handles the scheduling of the inspections and then they do the inspection all along the way.

857
01:09:47,000 --> 01:09:50,000
We're getting notified about everything.

858
01:09:50,000 --> 01:09:59,000
We get disconnection notices if the compliance isn't meant by these requirements.

859
01:09:59,000 --> 01:10:04,000
And then it's basically on us to enforce any kind of action on that.

860
01:10:04,000 --> 01:10:07,000
But most people are businesses comply.

861
01:10:07,000 --> 01:10:12,000
So we haven't had to do anything in my time here.

862
01:10:12,000 --> 01:10:19,000
As far as hydrocorp as a partner goes, they work very well with us.

863
01:10:20,000 --> 01:10:25,000
We've had no issues with what they do for us.

864
01:10:25,000 --> 01:10:27,000
They work with other communities around here.

865
01:10:27,000 --> 01:10:34,000
So they're a very known source of information for connections, cross connection inspections.

866
01:10:34,000 --> 01:10:43,000
We also are looking at pursuing some meter testing with them in the future for our industrial and commercial meters.

867
01:10:44,000 --> 01:10:51,000
We're kind of in the process of replacing a lot of older meters in the industrial and commercial world.

868
01:10:51,000 --> 01:10:57,000
So once those come up for testing, we're going to look at potentially hiring them for that service too.

869
01:10:57,000 --> 01:11:01,000
So, yeah, it's pretty, pretty cut and dry.

870
01:11:01,000 --> 01:11:04,000
Any questions?

871
01:11:04,000 --> 01:11:05,000
I have a question.

872
01:11:05,000 --> 01:11:08,000
Is it something that's typically subbed out in most municipalities?

873
01:11:08,000 --> 01:11:10,000
Yeah, actually, I should have talked about that.

874
01:11:10,000 --> 01:11:11,000
Yeah.

875
01:11:12,000 --> 01:11:13,000
Yes.

876
01:11:13,000 --> 01:11:17,000
The reason is most communities like our size are even smaller.

877
01:11:17,000 --> 01:11:23,000
They just don't have the capability of hiring a full-time inspector, if you will,

878
01:11:23,000 --> 01:11:28,000
or sending one of their crew members to class to be certified to do this.

879
01:11:28,000 --> 01:11:33,000
And if they did, it would basically be almost a full-time kind of position throughout the year.

880
01:11:34,000 --> 01:11:40,000
Is there a threshold where a community would consider hiring full-time, just considering the growth over the next?

881
01:11:44,000 --> 01:11:49,000
I would say it would have to be a larger community.

882
01:11:49,000 --> 01:11:55,000
And then, to be honest, with what's coming to the north, that's going to be probably out of our realm,

883
01:11:55,000 --> 01:12:00,000
where we're going to need a professional service to make sure that everything is up to date.

884
01:12:01,000 --> 01:12:05,000
I would say at paying $74,000 for it for four years.

885
01:12:05,000 --> 01:12:12,000
If it was twice that much a year, that's probably closer to the threshold of where we need to consider having our own guy.

886
01:12:12,000 --> 01:12:13,000
Yeah.

887
01:12:13,000 --> 01:12:16,000
So eight times the size of Port Washington, roughly.

888
01:12:16,000 --> 01:12:17,000
Yeah.

889
01:12:17,000 --> 01:12:23,000
I mean, there are communities to the north that they will have somebody do it, but then they share.

890
01:12:23,000 --> 01:12:28,000
They'll do multiple communities or a whole county.

891
01:12:29,000 --> 01:12:32,000
Any other comments or questions?

892
01:12:32,000 --> 01:12:38,000
If none, I will entertain a motion for this.

893
01:12:38,000 --> 01:12:40,000
I'll move to prove the staff recommendation.

894
01:12:40,000 --> 01:12:41,000
All right.

895
01:12:41,000 --> 01:12:43,000
We have a motion by committee member Pauli.

896
01:12:43,000 --> 01:12:44,000
Is there a second?

897
01:12:44,000 --> 01:12:45,000
I'll second.

898
01:12:45,000 --> 01:12:46,000
Second by Alderman Beaster.

899
01:12:46,000 --> 01:12:49,000
Any questions or discussion on the motion?

900
01:12:49,000 --> 01:12:52,000
Seeing none, all those in favor say aye.

901
01:12:52,000 --> 01:12:53,000
Aye.

902
01:12:53,000 --> 01:12:54,000
Opposed?

903
01:12:54,000 --> 01:12:55,000
Motion carries.

904
01:12:55,000 --> 01:12:56,000
Thank you.

905
01:12:56,000 --> 01:13:03,000
That brings us to item 11, Consideration and Possible Action on Bluff Stabilization Drain Line Bed.

906
01:13:03,000 --> 01:13:04,000
Roger.

907
01:13:04,000 --> 01:13:05,000
All right.

908
01:13:05,000 --> 01:13:09,000
If you recall, we bid this job earlier in the year.

909
01:13:09,000 --> 01:13:12,000
We had nine plan holders.

910
01:13:12,000 --> 01:13:14,000
None of them put a bit in.

911
01:13:14,000 --> 01:13:18,000
Every figure to scope a work a little bit.

912
01:13:18,000 --> 01:13:21,000
Mostly it gave them a little bit more time to get the work done.

913
01:13:21,000 --> 01:13:23,000
We had two interested.

914
01:13:23,000 --> 01:13:25,000
One submitted a little bit.

915
01:13:25,000 --> 01:13:27,000
The bid was $450,000.

916
01:13:27,000 --> 01:13:29,000
Our budget's $100,000.

917
01:13:29,000 --> 01:13:37,000
So again, I think we're in a position where I recommend that we reject the bid and look

918
01:13:37,000 --> 01:13:38,000
at the project again.

919
01:13:38,000 --> 01:13:46,000
See what we can do to get more bidders and get it more in line with what we have budgeted.

920
01:13:46,000 --> 01:13:50,000
What was the scope of the project again?

921
01:13:51,000 --> 01:13:58,000
Essentially, to put horizontal drill, three drain lines from the top of the bluff roughly,

922
01:13:58,000 --> 01:14:05,000
behind the road, down to the toe of slope.

923
01:14:05,000 --> 01:14:11,000
The challenge seems to be that there's a perforated section of pipe in there to hit the sand seam,

924
01:14:11,000 --> 01:14:15,000
silt seam that Mary Lou mentioned earlier tonight.

925
01:14:15,000 --> 01:14:20,000
The water, get it off, collect it, drain it down to the toe of slope without coming out

926
01:14:20,000 --> 01:14:23,000
of the face of the slope.

927
01:14:23,000 --> 01:14:31,000
It seems like some of the contractors we've talked to have a little bit concern about whether

928
01:14:31,000 --> 01:14:36,000
they can do it and deliver a project that would hold up the warranty.

929
01:14:36,000 --> 01:14:38,000
That'll function.

930
01:14:39,000 --> 01:14:45,000
My plan now is to go back to our engineer and essentially talk it over and say, okay,

931
01:14:45,000 --> 01:14:48,000
what changes do we need to make?

932
01:14:48,000 --> 01:14:55,000
They talk to some contractors when they put their design together, can they shake them?

933
01:14:55,000 --> 01:14:59,000
People lose the bid to project?

934
01:14:59,000 --> 01:15:02,000
With only the one bid, is there any way?

935
01:15:02,000 --> 01:15:07,000
I mean, do we have an idea of what this should cost?

936
01:15:07,000 --> 01:15:09,000
Right now, I wish.

937
01:15:09,000 --> 01:15:12,000
We had a couple of projects that we couldn't.

938
01:15:12,000 --> 01:15:18,000
Yes, we were given engineering estimates when the project was designed, that this project

939
01:15:18,000 --> 01:15:21,000
would be under $100,000.

940
01:15:21,000 --> 01:15:24,000
So that's why we're recommending to reject the bid.

941
01:15:24,000 --> 01:15:31,000
And so we've, yeah, we need to have more conversations.

942
01:15:31,000 --> 01:15:34,000
We have had conversations with Miller.

943
01:15:35,000 --> 01:15:40,000
But I think we need to have more and do more outreach to contractors.

944
01:15:40,000 --> 01:15:45,000
So we normally, I need a given project.

945
01:15:45,000 --> 01:15:48,000
We don't spend a lot of time recruiting contractors.

946
01:15:48,000 --> 01:15:56,000
So after receiving zero bids and nine plan holders, Roger did reach out to more contractors.

947
01:15:56,000 --> 01:16:05,000
But contractors don't often give you honest feedback until after the, well, they may never give it to you.

948
01:16:05,000 --> 01:16:11,000
But in any case, so we don't know until the bid day who's going to submit a bid.

949
01:16:11,000 --> 01:16:17,000
And so now, so twice we've had, I'll just say, disappointing results.

950
01:16:17,000 --> 01:16:30,000
And so I think we're going to have to get more aggressive in determining what is keeping contractors from bidding this work.

951
01:16:30,000 --> 01:16:33,000
I mean, some of it is there is just a ton of work out there.

952
01:16:33,000 --> 01:16:36,000
There aren't a ton of directional drillers out there.

953
01:16:36,000 --> 01:16:38,000
And so I think that's part of the problem.

954
01:16:38,000 --> 01:16:40,000
They can be very choosy these days.

955
01:16:40,000 --> 01:16:45,000
This is a little bit of a higher, I think they see this as a little bit of a higher risk project.

956
01:16:45,000 --> 01:16:46,000
It's also not a very common project.

957
01:16:46,000 --> 01:17:06,000
And so, and if we can't, if we can't accomplish getting this design work, I think we just have to go back to Miller and say, what can we do to achieve our goals with a different design.

958
01:17:06,000 --> 01:17:17,000
I mean, so I think we have to have some serious conversations with Miller.

959
01:17:17,000 --> 01:17:19,000
They didn't work with a car.

960
01:17:19,000 --> 01:17:25,000
I know they worked with a contractor who we have reached out to, and they've not submitted a bid.

961
01:17:25,000 --> 01:17:32,000
And I think we need to, again, have more conversations.

962
01:17:33,000 --> 01:17:38,000
So is there a better time of year maybe to be putting this out?

963
01:17:38,000 --> 01:17:40,000
Is this the seasonal work?

964
01:17:40,000 --> 01:17:47,000
Is this something urgent that we should be doing right away and not putting off?

965
01:17:47,000 --> 01:17:54,000
Or do you have a better feel what maybe what we're missing here?

966
01:17:54,000 --> 01:18:01,000
Well, the sooner we get it in that, you know, the sooner we install it, the better as far as dewatering the bluff.

967
01:18:02,000 --> 01:18:04,000
But Roger put it out for bids.

968
01:18:04,000 --> 01:18:10,000
We put it out for bids in early spring and gave the contractor pretty much the whole year to do it.

969
01:18:10,000 --> 01:18:12,000
And that hasn't.

970
01:18:12,000 --> 01:18:13,000
Yeah.

971
01:18:13,000 --> 01:18:18,000
It's something like November a better time because that's often when contractors are setting their schedules.

972
01:18:18,000 --> 01:18:20,000
But this is a small project.

973
01:18:20,000 --> 01:18:21,000
Right.

974
01:18:21,000 --> 01:18:22,000
You mean in terms of bidding?

975
01:18:22,000 --> 01:18:23,000
In terms of bidding?

976
01:18:23,000 --> 01:18:24,000
Yeah.

977
01:18:24,000 --> 01:18:26,000
I guess I don't.

978
01:18:27,000 --> 01:18:36,000
Or can it be combined with a different project to make it more attractive?

979
01:18:36,000 --> 01:18:47,000
I'm not sure what the recommendation we received from Miller is that this should be a standalone project like a year prior to doing any bluff work.

980
01:18:47,000 --> 01:18:50,000
But again, I just think contractors are very busy.

981
01:18:50,000 --> 01:18:53,000
This is a relatively small project for a directional drill.

982
01:18:53,000 --> 01:18:56,000
I guess I don't know all the answers.

983
01:18:56,000 --> 01:18:58,000
Roger's had more of the conversations.

984
01:18:58,000 --> 01:18:59,000
Yeah.

985
01:18:59,000 --> 01:19:04,000
I mean, I think that I guess my mind that that's I'm looking for is kind of.

986
01:19:04,000 --> 01:19:10,000
Let's work our scope and our design a little bit here.

987
01:19:10,000 --> 01:19:15,000
Get it off the street because everyone's seen this project now for.

988
01:19:15,000 --> 01:19:18,000
Six months.

989
01:19:19,000 --> 01:19:23,000
And then bring back out because this work could be done in the winter.

990
01:19:23,000 --> 01:19:26,000
I mean, there's there's nothing that's requiring.

991
01:19:26,000 --> 01:19:31,000
In fact, we prefer that not be done now when people want to be using the beach.

992
01:19:31,000 --> 01:19:34,000
I mean, we don't want to close off the beach for construction jobs.

993
01:19:34,000 --> 01:19:38,000
So maybe that that's the thing.

994
01:19:38,000 --> 01:19:43,000
Part of it is it's grand funded, you know, the grant expires at the end of the year.

995
01:19:43,000 --> 01:19:47,000
So we'll have to look at that extensions.

996
01:19:48,000 --> 01:19:51,000
Yeah, it can be extended.

997
01:19:51,000 --> 01:19:52,000
Okay.

998
01:19:52,000 --> 01:19:53,000
All right.

999
01:19:53,000 --> 01:19:55,000
Any other questions?

1000
01:19:55,000 --> 01:19:57,000
All right.

1001
01:19:57,000 --> 01:20:01,000
Seeing none, we'll be entertaining a motion on this item.

1002
01:20:01,000 --> 01:20:04,000
I'll move to approve the staff recommendation.

1003
01:20:04,000 --> 01:20:05,000
All right.

1004
01:20:05,000 --> 01:20:12,000
We have a motion to approve the staff recommendation by Alderman Miller, which is to reject the bid.

1005
01:20:12,000 --> 01:20:14,000
Is there a second?

1006
01:20:14,000 --> 01:20:15,000
I'll second.

1007
01:20:15,000 --> 01:20:21,000
Any questions on the motion?

1008
01:20:21,000 --> 01:20:22,000
Seeing none.

1009
01:20:22,000 --> 01:20:24,000
All those in favor say aye.

1010
01:20:24,000 --> 01:20:25,000
Aye.

1011
01:20:25,000 --> 01:20:26,000
Opposed?

1012
01:20:26,000 --> 01:20:27,000
Motion carries.

1013
01:20:27,000 --> 01:20:28,000
All right.

1014
01:20:28,000 --> 01:20:38,000
That brings us to item 12 consideration and possible action on construction change order five at the wastewater treatment plan.

1015
01:20:38,000 --> 01:20:39,000
All right.

1016
01:20:39,000 --> 01:20:42,000
So last board meeting, we approve this change order.

1017
01:20:42,000 --> 01:21:00,000
And then after the meeting, he essentially got it, got informed about four days later that the manufacturer of this role said, hey, by the way, there's, there's a tariff on this.

1018
01:21:00,000 --> 01:21:07,000
And currently it's 50% of the materials, which comes out there on like $35,000.

1019
01:21:07,000 --> 01:21:13,000
So that was not improved in the scope of the change order.

1020
01:21:13,000 --> 01:21:19,000
So I guess what I want to do.

1021
01:21:19,000 --> 01:21:21,000
So basically, I wanted to bring the hope out.

1022
01:21:21,000 --> 01:21:24,000
We never executed a change order done with the contractor.

1023
01:21:24,000 --> 01:21:29,000
So I thought, you know, bring it back here to discuss that a little bit.

1024
01:21:29,000 --> 01:21:36,000
We are pursuing now and we know two fabricators per se.

1025
01:21:36,000 --> 01:21:39,000
We'll give us proposals for this.

1026
01:21:39,000 --> 01:21:45,000
We had talked to some other fabricators rather than original previously.

1027
01:21:45,000 --> 01:21:53,000
But the original fabricator gave us what we thought was a reasonable price for this type of work.

1028
01:21:53,000 --> 01:21:59,000
And then sticking with, you know, like OEM parts, you know, like on a car.

1029
01:21:59,000 --> 01:22:17,000
But now with the price and then with additional with the tariffs, it's like, yeah, there might be another fabricator out there like that can beat that price and give us almost a good quality or almost a good fit for the product that would be acceptable for the process.

1030
01:22:17,000 --> 01:22:19,000
So we want to pursue that.

1031
01:22:19,000 --> 01:22:23,000
But one of the things I'm running into is

1032
01:22:24,000 --> 01:22:26,000
timing on this.

1033
01:22:26,000 --> 01:22:31,000
And I know if we stick with the original person that accompanied it, it was like a

1034
01:22:32,000 --> 01:22:41,000
16 week lead, I think, or something is pushing it out in October and getting into the time of year where it might not be feasible to install it.

1035
01:22:41,000 --> 01:22:45,000
You know, if it drags out into December, January.

1036
01:22:46,000 --> 01:22:59,000
So what I guess I'm asking the board for approval is we get these other proposals from these fabricators.

1037
01:22:59,000 --> 01:23:07,000
We essentially kind of do a risk analysis, you know, between us and our consultant and our contractor.

1038
01:23:08,000 --> 01:23:10,000
If we think it's worthwhile, you know, so look at time.

1039
01:23:10,000 --> 01:23:11,000
We look at costs.

1040
01:23:11,000 --> 01:23:24,000
We look at, you know, how well this will this newly fabricated structure by not the original manufacturer, how well will that work with our current system.

1041
01:23:27,000 --> 01:23:34,000
But if all that works out, I'd like to move ahead and then come back at the next board meeting.

1042
01:23:35,000 --> 01:23:38,000
Or official change order approval just just on the timing basis.

1043
01:23:38,000 --> 01:23:45,000
So I would say it's the original approval was 131,000.

1044
01:23:45,000 --> 01:23:53,000
So we're, you know, if you want to cap it like 170, that's kind of worst case.

1045
01:23:53,000 --> 01:23:57,000
That's where we'd be at with the current manufacturer.

1046
01:23:58,000 --> 01:24:00,000
All right.

1047
01:24:00,000 --> 01:24:10,000
So will other manufacturers be able to meet a tighter schedule to get it or they have just as long of a lead time as the preferred original manufacturer?

1048
01:24:10,000 --> 01:24:11,000
I don't know.

1049
01:24:11,000 --> 01:24:14,000
We haven't heard that from.

1050
01:24:14,000 --> 01:24:15,000
We haven't.

1051
01:24:15,000 --> 01:24:20,000
Two of them have said, yes, we'll get your proposal.

1052
01:24:20,000 --> 01:24:23,000
And that that's two main questions.

1053
01:24:23,000 --> 01:24:24,000
What is the cost?

1054
01:24:24,000 --> 01:24:26,000
How soon can you get it done?

1055
01:24:27,000 --> 01:24:31,000
But they seem to think that they could meet the schedule.

1056
01:24:31,000 --> 01:24:35,000
Otherwise, it's not worth third time or our time.

1057
01:24:35,000 --> 01:24:36,000
Okay.

1058
01:24:36,000 --> 01:24:48,000
If we have to hold over till spring to put it in, is there any extraordinary measures that we have to take to protect the facility in that time or?

1059
01:24:48,000 --> 01:24:53,000
Well, it's shut down now in a real structure already damaged.

1060
01:24:54,000 --> 01:24:56,000
So the part that's going to get damaged.

1061
01:24:56,000 --> 01:24:57,000
So I wouldn't think so.

1062
01:24:57,000 --> 01:25:02,000
I mean, we're just at the, it's 50% of our processes.

1063
01:25:02,000 --> 01:25:07,000
If the, if the other process would go down, there's no redundancy.

1064
01:25:07,000 --> 01:25:08,000
So, I mean, that's our risk.

1065
01:25:08,000 --> 01:25:22,000
We don't have any redundancy and, and, and if those kick up for a certain period of time, you look at hydraulic capacity issues, but the biggest issue is lack of redundancy.

1066
01:25:23,000 --> 01:25:24,000
Okay.

1067
01:25:24,000 --> 01:25:25,000
All right.

1068
01:25:25,000 --> 01:25:26,000
Any other questions?

1069
01:25:26,000 --> 01:25:27,000
Comments?

1070
01:25:27,000 --> 01:25:35,000
So what, what you're asking is basically just to take more time to keep evaluating.

1071
01:25:35,000 --> 01:25:47,000
Essentially, but if, if I get a good, if I get a good proposal, I want to move ahead with it right away and not wait a month to come back here.

1072
01:25:47,000 --> 01:25:49,000
So I, so what I, what I can do is I can talk to Mike.

1073
01:25:49,000 --> 01:25:51,000
I could talk to people individually.

1074
01:25:51,000 --> 01:25:53,000
I think, can I?

1075
01:25:53,000 --> 01:25:54,000
I'm not sure.

1076
01:25:54,000 --> 01:25:58,000
I have to make sure I'm avoiding a walking quorum issue here.

1077
01:25:58,000 --> 01:26:03,000
But, you know, certainly not doing things in, in the dark.

1078
01:26:03,000 --> 01:26:07,000
I let, let people know what's going on, but, but to be able to move ahead.

1079
01:26:07,000 --> 01:26:13,000
If I, if, if somebody says, hey, we can do this in six weeks, then I can wait.

1080
01:26:14,000 --> 01:26:24,000
So you're, you're basically asking for the, for the cost of what the, of what the tariff would be.

1081
01:26:24,000 --> 01:26:29,000
But then you have the flexibility to change to someone else to save that money if you can find them.

1082
01:26:29,000 --> 01:26:30,000
Yes.

1083
01:26:30,000 --> 01:26:31,000
Yes.

1084
01:26:31,000 --> 01:26:32,000
Yeah.

1085
01:26:32,000 --> 01:26:34,000
I, I like the approach.

1086
01:26:34,000 --> 01:26:35,000
I think.

1087
01:26:35,000 --> 01:26:36,000
That's great.

1088
01:26:36,000 --> 01:26:41,000
We can all have our mic side.

1089
01:26:41,000 --> 01:26:43,000
Is there, was there any effort made to negotiate?

1090
01:26:43,000 --> 01:26:49,000
I mean, we got this approved and this individual came to us after the fact with the tariff,

1091
01:26:49,000 --> 01:26:50,000
additional tariff costs.

1092
01:26:50,000 --> 01:26:57,000
And if there was, you know, if it is a matter of avoiding any redundancy issues,

1093
01:26:57,000 --> 01:27:01,000
is there been any negotiations made to try to net cost down?

1094
01:27:01,000 --> 01:27:02,000
Yeah.

1095
01:27:02,000 --> 01:27:08,000
We, we spent, like, I know the contractor himself.

1096
01:27:08,000 --> 01:27:09,000
Good.

1097
01:27:09,000 --> 01:27:14,000
Cause they're, they're once doing most of the dealing spent the same amount of time and it kind of, like.

1098
01:27:14,000 --> 01:27:17,000
Essentially run them the riot act, but, but hey, yeah.

1099
01:27:17,000 --> 01:27:19,000
Why wasn't this on it?

1100
01:27:19,000 --> 01:27:21,000
That this was nor on original quote you gave us.

1101
01:27:21,000 --> 01:27:22,000
Why is it coming now?

1102
01:27:22,000 --> 01:27:27,000
I got to go to my client and tell them cause.

1103
01:27:27,000 --> 01:27:29,000
You know, it's a big chunk of money.

1104
01:27:29,000 --> 01:27:30,000
They're not going to eat it.

1105
01:27:30,000 --> 01:27:31,000
Oh.

1106
01:27:32,000 --> 01:27:35,000
They're the ones who made the quote.

1107
01:27:35,000 --> 01:27:36,000
We're the ones who agreed.

1108
01:27:36,000 --> 01:27:38,000
Don't we have a contract for that?

1109
01:27:38,000 --> 01:27:43,000
Well, they never got executed because of this.

1110
01:27:43,000 --> 01:27:52,000
The other thing with the current administration.

1111
01:27:53,000 --> 01:27:59,000
Teriffs could get, could go away in two weeks.

1112
01:27:59,000 --> 01:28:04,000
I think, I think what you're proposing is fine.

1113
01:28:04,000 --> 01:28:05,000
I'm just.

1114
01:28:05,000 --> 01:28:06,000
Yeah.

1115
01:28:06,000 --> 01:28:07,000
Yeah.

1116
01:28:07,000 --> 01:28:11,000
I mean, so, so efforts were made to try to get them to reduce the tariff, share the cost.

1117
01:28:11,000 --> 01:28:17,000
I think if, I think if the manufacturer would have been willing to share some of the cost,

1118
01:28:17,000 --> 01:28:21,000
we could have talked to the contractor and share, you know, and it could have been, you know,

1119
01:28:21,000 --> 01:28:27,000
somewhat of a three way split, but the manufacturer is essentially telling us no deal.

1120
01:28:27,000 --> 01:28:32,000
This is, I think they think that.

1121
01:28:32,000 --> 01:28:33,000
They have the product.

1122
01:28:33,000 --> 01:28:34,000
Nobody else has the product.

1123
01:28:34,000 --> 01:28:41,000
They, they got us.

1124
01:28:41,000 --> 01:28:42,000
All right.

1125
01:28:42,000 --> 01:28:45,000
Less than anyone has additional comments or questions.

1126
01:28:45,000 --> 01:28:52,000
I will entertain a motion on this change on this change that change order.

1127
01:28:52,000 --> 01:28:56,000
I'll move to approach that recommendation.

1128
01:28:56,000 --> 01:28:57,000
All right.

1129
01:28:57,000 --> 01:29:00,000
We have a motion by committee member Polly.

1130
01:29:00,000 --> 01:29:03,000
Is there a second?

1131
01:29:03,000 --> 01:29:05,000
I will second it.

1132
01:29:05,000 --> 01:29:06,000
All right.

1133
01:29:06,000 --> 01:29:10,000
Is there any question or discussion on this on the motion?

1134
01:29:10,000 --> 01:29:11,000
Seeing none.

1135
01:29:11,000 --> 01:29:13,000
All those in favor say aye.

1136
01:29:13,000 --> 01:29:14,000
Aye.

1137
01:29:14,000 --> 01:29:15,000
Opposed?

1138
01:29:15,000 --> 01:29:17,000
Motion carries.

1139
01:29:17,000 --> 01:29:20,000
All right.

1140
01:29:20,000 --> 01:29:34,000
That brings us to item 13 review 26-1 and 26-2 utility extension projects to provide sewer and water service to Canellsville in the town of Port Washington.

1141
01:29:34,000 --> 01:29:35,000
Roger.

1142
01:29:35,000 --> 01:29:37,000
All right.

1143
01:29:38,000 --> 01:29:39,000
All right.

1144
01:29:39,000 --> 01:29:58,000
Well, I'll turn this over to Aaron from Kapoor, but essentially he's going to give us an overview of our of our of our next sewer and water project that we have coming and sort of our impacts that's going to create with the area.

1145
01:29:58,000 --> 01:29:59,000
Good evening, everybody.

1146
01:29:59,000 --> 01:30:01,000
Are you able to bring us up there?

1147
01:30:01,000 --> 01:30:02,000
Yeah.

1148
01:30:14,000 --> 01:30:15,000
Thanks, Roger.

1149
01:30:15,000 --> 01:30:17,000
Again, I'm Aaron Groh with Kapoor and Associates.

1150
01:30:17,000 --> 01:30:21,000
It's been here a few times talking in front of your group here tonight.

1151
01:30:21,000 --> 01:30:23,000
So thanks for having me.

1152
01:30:24,000 --> 01:30:38,000
So right now we are complete with our design plans for the next phase to extend utilities to the north for Canellsville and also to serve the vantage site.

1153
01:30:38,000 --> 01:30:51,000
Those two projects are 26-1 and 26-2 to the key parts of this are that we still are in discussions with PSC for approval.

1154
01:30:51,000 --> 01:30:56,000
So we are still in the process of we've had a couple of meetings with PSC.

1155
01:30:56,000 --> 01:31:16,000
We've had several clarifications questions and answers going back and forth with them, and we have not gotten all the answers that we need to verify that we can move forward with this project and submit to PSC.

1156
01:31:16,000 --> 01:31:24,000
Accordingly, so that is one item that is going to drive the schedule for these projects.

1157
01:31:24,000 --> 01:31:35,000
With that being said, this is basically a very similar presentation to what I provided before a month or two ago.

1158
01:31:35,000 --> 01:31:42,000
So this first project is 26-1. There's 10,000 feet of water main and 5,000 feet of sanitary sewer.

1159
01:31:42,000 --> 01:31:52,000
It's a long Highland Drive main branch road and then on County Trunk Highway KW up to where the boat storage facility is.

1160
01:31:52,000 --> 01:31:59,000
Also, we'll provide sanitary and water laterals to Canellsville per the agreement between the city and the town.

1161
01:31:59,000 --> 01:32:15,000
And we're estimating at just under $8 million for the construction costs and you add 20% engineering contingencies in there, it brings it up to about 9.4.

1162
01:32:16,000 --> 01:32:26,000
The schedule still is hoping to shoot for late June or early July with construction considering in late July or early August.

1163
01:32:26,000 --> 01:32:39,000
As I just mentioned before with these projects, PSC permitting is still an item that is driving the schedule, and until we can identify the permit process with PSC,

1164
01:32:39,000 --> 01:32:44,000
we're in a holding pattern until we get that approval.

1165
01:32:44,000 --> 01:32:52,000
Drive control detours routes is another item as far as how we broke this project into different phases.

1166
01:32:52,000 --> 01:33:06,000
And then we also wanted to identify attractive sized projects to bring a lot of bidders to these two jobs, 26-1 and 26-2.

1167
01:33:06,000 --> 01:33:11,000
We don't want to put out such a large project that you only have two or three bidders.

1168
01:33:11,000 --> 01:33:20,000
We want to have normal size contracts that we think we can attract 10 or 15 different contractors that can put out really competitive prices.

1169
01:33:21,000 --> 01:33:24,000
So 26-2, very similar.

1170
01:33:24,000 --> 01:33:26,000
So this is 11,000 feet of water main.

1171
01:33:26,000 --> 01:33:39,000
It's only water main and it's on KW Lake Drive from the storage facility north to Lake Drive and then east to the main entrance to the vantage project.

1172
01:33:39,000 --> 01:33:47,000
Also add water main services along KW and to other other parcels that are within the town.

1173
01:33:48,000 --> 01:33:52,000
This will provide secondary fee to redundancy.

1174
01:33:52,000 --> 01:33:58,000
So what Roger was just speaking about before redundancy is a key component to engineering.

1175
01:33:58,000 --> 01:34:07,000
And this is one of the main reasons why we want to provide the water to the north side of the project site for redundancy reasons.

1176
01:34:07,000 --> 01:34:17,000
This estimated cost is $5 billion for construction, but if you add engineering contingencies at about 20%, it brings us up to just over $6 million.

1177
01:34:17,000 --> 01:34:25,000
This schedule is similar June or early July to bid out and advertise with construction.

1178
01:34:25,000 --> 01:34:33,000
This section is just water main and this is completely driven by the schedule of PSC.

1179
01:34:33,000 --> 01:34:42,000
So instead of maybe starting this in July or August, we don't expect this project to start until at least October.

1180
01:34:42,000 --> 01:34:45,000
Water main, we would expect to be installed by directional drilling.

1181
01:34:45,000 --> 01:34:49,000
The PSC permits, as I mentioned before.

1182
01:34:49,000 --> 01:35:02,000
The reason why we want to add directional drilling as a construction method is because it's quicker and it will also reduce the impacts to traffic in the businesses and the properties that are along KW.

1183
01:35:02,000 --> 01:35:12,000
It's smaller work zones and just be easier for traffic to get around while they're working within KW.

1184
01:35:12,000 --> 01:35:22,000
So this is a layout of proposed detours and work zones in the first phase of 26-1.

1185
01:35:22,000 --> 01:35:30,000
So this is when we start up, we expect to start up in the intersection of H and Mink Ranch Road.

1186
01:35:30,000 --> 01:35:39,000
We'll have to shift traffic onto County Trunk Highway H, just southbound lanes only, so only in one direction.

1187
01:35:39,000 --> 01:35:45,000
The detour will also go on to County Trunk B to H and also on A to LL.

1188
01:35:45,000 --> 01:35:56,000
We've met with the County City staff and Kapoor, we met with the County to make sure that they were in agreement with these routes and these routes they concurred with us to do this.

1189
01:35:56,000 --> 01:36:11,000
One of the things that we discussed as well, could we maybe have a detour route on B up to A on the left side instead of having the yellow route that we show, which is on LL and County Trunk Highway A.

1190
01:36:11,000 --> 01:36:20,000
We have to have the detour on LL and A for numerous phases and therefore we felt just from a consistency standpoint for those that are driving out here.

1191
01:36:20,000 --> 01:36:25,000
If we change the detours back and forth and back and forth, it's going to get confusing.

1192
01:36:25,000 --> 01:36:33,000
So even though maybe it'll be a little bit longer detour route, we just feel it's better for those that live in the area, so it's a consistent detour routes.

1193
01:36:33,000 --> 01:36:37,000
All right.

1194
01:36:37,000 --> 01:36:43,000
The roads that are under construction will remain open to local traffic only, so that's key.

1195
01:36:43,000 --> 01:36:52,000
So we'll still can get on the construction routes when we're working on Highland or Mink Ranch or KW.

1196
01:36:52,000 --> 01:37:09,000
And then on this first little section here on Mink Ranch and I-43 crossing will also be working on extending our concrete and asphalt pavement that's going to be coordinated with the next phase.

1197
01:37:09,000 --> 01:37:11,000
You can go to the next sheet, please.

1198
01:37:11,000 --> 01:37:12,000
Thank you.

1199
01:37:13,000 --> 01:37:28,000
So this is on Highland Drive, so we will be connecting to where we ended the current construction project that just finished, which is just on Highland Drive just on the north side of the bridge on Highland Lane.

1200
01:37:28,000 --> 01:37:37,000
So we'll connect to that point and then extend to kind of Trunk Highway H and the intersection of KW.

1201
01:37:37,000 --> 01:37:43,000
We'll stop just short of KW and H to allow that section of road to remain open to traffic.

1202
01:37:43,000 --> 01:37:57,000
We also want to make sure with the phasing of this that we are cognizant of the garbage drop off for the town and then also for the local restaurant that's right at this intersection.

1203
01:37:58,000 --> 01:38:08,000
So that's one of the reasons why we wanted to stay short of KW and H to be able to allow traffic to get in and out of those areas during construction.

1204
01:38:08,000 --> 01:38:14,000
And then this detour would be route through County Trunk Highway LL and A.

1205
01:38:14,000 --> 01:38:18,000
Next phase, so this is the third and final phase for 26-1.

1206
01:38:18,000 --> 01:38:26,000
So this is extending up KW and also a little bit of an extension on County Trunk Highway H.

1207
01:38:26,000 --> 01:38:34,000
So we're completing everything else that's within that within the project scope, extending up to the boat storage facility.

1208
01:38:34,000 --> 01:38:41,000
And then we also will extend several hundred feet up, County Trunk Highway H this season.

1209
01:38:41,000 --> 01:38:51,000
So then the following season, if you remember our five-year outlook, County Trunk Highway H is anticipated to be constructed in 2028.

1210
01:38:51,000 --> 01:38:58,000
And we want to be completely out of that busy intersection with County Trunk H and County Trunk KW.

1211
01:38:58,000 --> 01:39:01,000
We don't want to be in that intersection two years in a row.

1212
01:39:01,000 --> 01:39:06,000
So we plan extending about two or three hundred feet north into H.

1213
01:39:06,000 --> 01:39:11,000
Get outside of the concrete pavement, the concrete pavement where that ends is where we end our project.

1214
01:39:11,000 --> 01:39:17,000
The northbound lanes of County Trunk Highway H would be closed during this process.

1215
01:39:17,000 --> 01:39:27,000
And so anybody that's coming from the city proper running up will be asked a detour on County Trunk Highway LL to A.

1216
01:39:27,000 --> 01:39:31,000
Again, the roads under construction are made open to local traffic.

1217
01:39:31,000 --> 01:39:43,000
And then we also want to make sure that we're cognizant of the restaurant that's on the intersection for this third phase of 26-1.

1218
01:39:43,000 --> 01:39:50,000
Lastly is 26-2. So this is just the water main only in County Trunk Highway KW and on Lake Drive.

1219
01:39:50,000 --> 01:39:56,000
The detour is on LL and A to the right and the yellow that you see.

1220
01:39:56,000 --> 01:40:06,000
As I noted before, we expect to have this directionally drilled and then wherever there's hydrants, which is about every 600 feet,

1221
01:40:06,000 --> 01:40:13,000
there'll be an open cut within the road. So we expect to have the majority of the road to remain as is.

1222
01:40:13,000 --> 01:40:19,000
As they install the water main, they'll cut open a location for where the hydrants is and then continue on.

1223
01:40:19,000 --> 01:40:28,000
So we're trying to make sure that we minimize the amount of impacts to the residents and the business owners along KW.

1224
01:40:29,000 --> 01:40:41,000
We're also specifying that when one project is going on, 26-1, we can't be working in KW in 26-2.

1225
01:40:41,000 --> 01:40:47,000
So our specifications are written in such a way that one job needs to finish before the other one starts.

1226
01:40:47,000 --> 01:40:51,000
So we don't have two contractors working on KW at the same time.

1227
01:40:51,000 --> 01:40:57,000
Again, we're trying to be as cognizant as we can to the business owners and the residents along KW.

1228
01:40:57,000 --> 01:41:05,000
Just a question. Wouldn't it be preferable, though, to have them both working simultaneously so we can have a shorter closure on KW?

1229
01:41:05,000 --> 01:41:17,000
Well, part of that also is driven by the PSC approval, which we expect that we won't get on this leg on 26-2,

1230
01:41:17,000 --> 01:41:21,000
and therefore, this section likely won't start up until October.

1231
01:41:21,000 --> 01:41:25,000
So part of that has to do with that plays a role into this, too.

1232
01:41:25,000 --> 01:41:30,000
Yeah, I hate to see us close it, open it for a week, and then close it again.

1233
01:41:30,000 --> 01:41:37,000
Understood, yes. We'll be very cognizant of working with both contractors, assuming that we have two different contractors that win these awards.

1234
01:41:37,000 --> 01:41:42,000
We'll work with them to try and make sure that we minimize those changes.

1235
01:41:43,000 --> 01:41:46,000
There's some things that you can't avoid, but point taken.

1236
01:41:46,000 --> 01:41:47,000
Yes.

1237
01:41:50,000 --> 01:42:02,000
Also, we identified that during warm weather, we'll use asphalt patching, and if it gets to cold weather, we're going to require them to use concrete patching.

1238
01:42:03,000 --> 01:42:11,000
One other thing is that we're specifying to minimize potential risk or overruns to the city.

1239
01:42:11,000 --> 01:42:15,000
We're anticipating that all this work would occur.

1240
01:42:15,000 --> 01:42:20,000
26-1 would occur yet all in the 26, year of 26.

1241
01:42:20,000 --> 01:42:25,000
26-2 may trickle into the year 2027.

1242
01:42:25,000 --> 01:42:38,000
If that's the case, what our specifications are saying is that contractor, we don't expect for them to work from the timeframe of December 15th to March 15th.

1243
01:42:38,000 --> 01:42:43,000
And if they so choose, they can do so at their own risk and at no additional cost to the city.

1244
01:42:43,000 --> 01:42:47,000
Therefore, no change orders for cold weather applications or things of that nature.

1245
01:42:47,000 --> 01:42:51,000
So we expect them no work from December to March.

1246
01:42:51,000 --> 01:42:57,000
However, we would allow them if they wanted to do it, again, at no additional cost to the city.

1247
01:42:57,000 --> 01:43:01,000
And I think that is the final sheet.

1248
01:43:01,000 --> 01:43:02,000
Any questions?

1249
01:43:02,000 --> 01:43:03,000
Yeah.

1250
01:43:03,000 --> 01:43:08,000
On the detour route running on LL as opposed to B.

1251
01:43:08,000 --> 01:43:16,000
Do we have any concern about, especially when Lake and LL will be closed for that project that all of the construction traffic is going to also be accessing this project?

1252
01:43:16,000 --> 01:43:19,000
Accessing the site from East off of LL.

1253
01:43:19,000 --> 01:43:20,000
Yes.

1254
01:43:20,000 --> 01:43:28,000
Would it in that case be better to have that detour on B so that it is not sharing the roads with all the construction traffic?

1255
01:43:28,000 --> 01:43:33,000
Other than, of course, when you get up to A, you're going to have an intersection with construction traffic.

1256
01:43:33,000 --> 01:43:36,000
There are multiple reasons why we chose that.

1257
01:43:36,000 --> 01:43:42,000
We also were looking at the tight angle on B and H as well.

1258
01:43:42,000 --> 01:43:47,000
And if you if you ran or ran the detour with some of these tight angles.

1259
01:43:47,000 --> 01:43:58,000
We also consideration of when the county part of this work is county work where the detours need to be done through county roads, right?

1260
01:43:58,000 --> 01:44:05,000
So will a road might be a good application to have a detour, but we really can't if we have some of the county projects going on.

1261
01:44:05,000 --> 01:44:07,000
Will the counties going to be paving on some of this?

1262
01:44:07,000 --> 01:44:09,000
So those all played into it.

1263
01:44:10,000 --> 01:44:17,000
We also coordinated these with the vantage design team specifically.

1264
01:44:17,000 --> 01:44:28,000
GRAFE and they're the ones that I looked at improving all the intersections and coordinating the traffic signals, the temporary traffic signals that are planned for the intersection with I 43.

1265
01:44:28,000 --> 01:44:36,000
And we bounced all these off of them and made sure that it worked with their plans and there were they felt that this would work as well.

1266
01:44:36,000 --> 01:44:44,000
So we don't need to take any extraordinary measures at lake in L.L. just by having all the traffic piling up there during construction.

1267
01:44:44,000 --> 01:44:48,000
Other than right now where we have sheriff's deputies out directing traffic twice a day.

1268
01:44:48,000 --> 01:44:50,000
Well, part of the soul.

1269
01:44:50,000 --> 01:45:03,000
Yes. So the the there will be traffic alleviated because right now Highland Drive does not have any access to construction traffic as we're completing that work.

1270
01:45:03,000 --> 01:45:06,000
We're about a week to two weeks from that all being complete.

1271
01:45:06,000 --> 01:45:13,000
And at that point in time, the vantage team will open the southern entrance off of Highland Drive.

1272
01:45:13,000 --> 01:45:21,000
So about half the trucks and equipment that are coming now to lake half of them now will be coming up the south side on Highland Drive.

1273
01:45:21,000 --> 01:45:28,000
So we'll alleviate a lot of the pressure that you have at both KW and L.L. at Lake Drive.

1274
01:45:28,000 --> 01:45:34,000
So that's probably going to be the biggest impact of being able to open up the access point off of Highland Drive.

1275
01:45:34,000 --> 01:45:36,000
All right. Any other questions?

1276
01:45:36,000 --> 01:45:37,000
Yes.

1277
01:45:37,000 --> 01:45:43,000
Have you spoken to Johnson bus company? Are we concerned about school kids and?

1278
01:45:43,000 --> 01:45:50,000
Yes. So we've spoken with them and we also have it written on to our specifications that we will be coordinating with them.

1279
01:45:50,000 --> 01:46:05,000
And we will discuss the contractor will be required to meet with Johnson bus once we have a preliminary schedule put together and we can talk with them as far as what the best routes are is that they need to go north or if they need to go south.

1280
01:46:05,000 --> 01:46:18,000
So yes, that is written into our contract specifically that the contractor has to meet with Johnson bus to make sure that they are able to proceed business wise as they should.

1281
01:46:18,000 --> 01:46:21,000
Yeah, because we don't want to hear stories about how they're an hour late for school.

1282
01:46:21,000 --> 01:46:23,000
Yes, we understood.

1283
01:46:23,000 --> 01:46:27,000
Thank you.

1284
01:46:27,000 --> 01:46:32,000
Who is primarily responsible for sharing us out to the community?

1285
01:46:32,000 --> 01:46:35,000
Because most people aren't going to watch public works meetings.

1286
01:46:35,000 --> 01:46:39,000
So if it's because like there's this construction updates website on the vantage D.C.

1287
01:46:40,000 --> 01:46:41,000
lighthouse campus.

1288
01:46:41,000 --> 01:46:44,000
Do you guys have anything to do with that or is that vantage themselves?

1289
01:46:44,000 --> 01:46:48,000
Because the last update on here was from April.

1290
01:46:48,000 --> 01:46:53,000
So vantage has their own updates. I don't know Roger if you have any more to add to that.

1291
01:46:53,000 --> 01:46:56,000
They're doing their own updates.

1292
01:46:57,000 --> 01:47:09,000
We are planning on doing a P.I.M. meeting with the town public information meeting specifically Johnson bus.

1293
01:47:09,000 --> 01:47:12,000
Piers restaurant.

1294
01:47:12,000 --> 01:47:14,000
Great Lakes bolt.

1295
01:47:14,000 --> 01:47:19,000
And it's got an operation in there just so that we could.

1296
01:47:19,000 --> 01:47:23,000
Kind of have the same meeting discussion that we're having here.

1297
01:47:23,000 --> 01:47:28,000
And I do apologize that was one of the key points I wanted to mention today and I forgot.

1298
01:47:28,000 --> 01:47:35,000
Yeah, we are planning on scheduling of P.I.M. prior to any sort of road work construction.

1299
01:47:35,000 --> 01:47:42,000
I just think if they could keep this construction updates website a little bit more updated with so people know what to expect ahead of time would be.

1300
01:47:42,000 --> 01:47:48,000
So we can share I can certainly share this information with vantage and ask for them to add it to their site.

1301
01:47:48,000 --> 01:47:53,000
That would be I would assume that they would be fine with doing that.

1302
01:47:53,000 --> 01:47:57,000
Thank you.

1303
01:47:57,000 --> 01:48:00,000
This is probably more of a question for Robin Roger.

1304
01:48:00,000 --> 01:48:15,000
But since the project is going to be putting in curb stops for future water connections, are we doing any marketing at all to those property owners that they are going to be aware that they can connect to city water?

1305
01:48:16,000 --> 01:48:23,000
Because we probably don't want it happening simultaneously with the project, but the curb stop will be there be easy for them to continue.

1306
01:48:23,000 --> 01:48:37,000
Just want to make sure that they're all aware so that they can start making those connections and we can produce a little bit of water revenue off of those areas.

1307
01:48:38,000 --> 01:48:43,000
We haven't done it, but I know the town chairman has gone door door to court to inform everyone.

1308
01:48:43,000 --> 01:48:44,000
All right.

1309
01:48:44,000 --> 01:48:45,000
Good.

1310
01:48:45,000 --> 01:48:46,000
All right.

1311
01:48:46,000 --> 01:48:50,000
Any other comments or questions?

1312
01:48:50,000 --> 01:48:51,000
All right.

1313
01:48:51,000 --> 01:48:52,000
Thank you.

1314
01:48:52,000 --> 01:48:53,000
Thank you.

1315
01:48:56,000 --> 01:48:57,000
All right.

1316
01:48:57,000 --> 01:49:01,000
That brings us to item 14.

1317
01:49:02,000 --> 01:49:08,000
Review proposed projects under consideration for inclusion in the 10 year capital improvement plan.

1318
01:49:08,000 --> 01:49:09,000
Rob.

1319
01:49:09,000 --> 01:49:10,000
Sure.

1320
01:49:10,000 --> 01:49:11,000
Okay.

1321
01:49:11,000 --> 01:49:12,000
So I will present.

1322
01:49:12,000 --> 01:49:14,000
I can do it versus air media.

1323
01:49:14,000 --> 01:49:19,000
I just need the number.

1324
01:49:32,000 --> 01:49:37,000
So if you go to that.

1325
01:49:37,000 --> 01:49:44,000
The disconnect is in the middle right in the middle of that little box to the right to the right to the right to the right a little more right.

1326
01:49:44,000 --> 01:49:51,000
There you go.

1327
01:49:52,000 --> 01:49:54,000
Okay.

1328
01:49:54,000 --> 01:50:02,000
So I do not apologize.

1329
01:50:02,000 --> 01:50:15,000
I do not have a handout and I want to preface this by saying, you know, the finance director.

1330
01:50:16,000 --> 01:50:23,000
Essentially directed me to bring this to the Board of Public Works in July.

1331
01:50:23,000 --> 01:50:28,000
I wanted to bring it in June and July so that we got.

1332
01:50:28,000 --> 01:50:34,000
Information out in some conversation with the board about what priority projects are for the city.

1333
01:50:34,000 --> 01:50:38,000
So I have a list that we have our 10 year CIP.

1334
01:50:38,000 --> 01:50:39,000
This is very rough.

1335
01:50:39,000 --> 01:50:41,000
This is a very this is a rough cut.

1336
01:50:42,000 --> 01:50:43,000
The first take at it.

1337
01:50:43,000 --> 01:50:49,000
This is the 10 again, 10 year capital improvement project schedule.

1338
01:50:49,000 --> 01:50:58,000
And again, the purpose is I just want to make you aware of what is on our list for those 10 years.

1339
01:50:58,000 --> 01:51:02,000
We have a number of the projects that you'll see tonight.

1340
01:51:02,000 --> 01:51:04,000
Scheduled for 2027.

1341
01:51:04,000 --> 01:51:06,000
That doesn't mean that's where they're going to land.

1342
01:51:07,000 --> 01:51:08,000
All right.

1343
01:51:08,000 --> 01:51:12,000
So, but it's easier to push a project back then to move it forward.

1344
01:51:12,000 --> 01:51:15,000
And so I'm going to go through this.

1345
01:51:15,000 --> 01:51:17,000
Feel free to interrupt me and ask questions.

1346
01:51:17,000 --> 01:51:23,000
But otherwise at the end, we can have more conversation about again.

1347
01:51:23,000 --> 01:51:34,000
It's good to hear feedback about we, you know, we of course knows about projects that are priority projects for the city in terms of providing essential services.

1348
01:51:35,000 --> 01:51:40,000
You know, we need to hear back from you about, you know, some of the other some projects and what.

1349
01:51:40,000 --> 01:51:44,000
You know, what are the projects that excite, excite the board, right?

1350
01:51:44,000 --> 01:51:46,000
So that and the council.

1351
01:51:46,000 --> 01:51:50,000
So the schedule for this is so we'll talk about it tonight.

1352
01:51:50,000 --> 01:52:03,000
We'll talk about it at our July meeting and we'll vote on it at the July meeting and then it'll go to council on August 4th for approval by council.

1353
01:52:04,000 --> 01:52:08,000
And so with that, I will just launch into it again.

1354
01:52:08,000 --> 01:52:12,000
You know, it's been a long meeting, so I'm not going to spend a ton of time on this.

1355
01:52:12,000 --> 01:52:16,000
I've been working on it to try and make it a better presentation.

1356
01:52:16,000 --> 01:52:20,000
But in any case, felt felt short of the time.

1357
01:52:20,000 --> 01:52:23,000
So again, this is a this is a rough cut.

1358
01:52:23,000 --> 01:52:27,000
I'll include a touch on a little bit while we're doing in 26.

1359
01:52:27,000 --> 01:52:32,000
Sometimes they do relate to 27 like our first project.

1360
01:52:33,000 --> 01:52:38,000
But when you see this in July, it'll just be from 2027 to 2036.

1361
01:52:38,000 --> 01:52:43,000
So starting with our road projects.

1362
01:52:43,000 --> 01:52:44,000
All right.

1363
01:52:44,000 --> 01:52:46,000
Everything everyone can see that. Okay.

1364
01:52:46,000 --> 01:52:47,000
I apologize.

1365
01:52:47,000 --> 01:52:50,000
They don't normally wear a little bigger.

1366
01:52:50,000 --> 01:52:52,000
Yeah, there's no problem.

1367
01:52:52,000 --> 01:52:54,000
Normally don't wear glasses.

1368
01:52:54,000 --> 01:52:55,000
So these.

1369
01:52:55,000 --> 01:52:58,000
Had a little eye problems lately.

1370
01:52:59,000 --> 01:53:01,000
So, yeah.

1371
01:53:01,000 --> 01:53:03,000
Okay. All right, super.

1372
01:53:03,000 --> 01:53:04,000
All right.

1373
01:53:04,000 --> 01:53:07,000
So starting with Holden Street and.

1374
01:53:09,000 --> 01:53:10,000
Yeah.

1375
01:53:10,000 --> 01:53:23,000
So these are sexually the sections of Holden Street that are currently in the design phase from orchard lane up to Walters.

1376
01:53:23,000 --> 01:53:27,000
We are we are going to wind up.

1377
01:53:28,000 --> 01:53:42,000
Surfacing the second resurfacing the section here, but this is getting rebuilt in what's blue resurfacing this section in front of the middle school and then all the way up to Barry.

1378
01:53:42,000 --> 01:53:50,000
That is under design and that is scheduled for construction next year.

1379
01:53:51,000 --> 01:54:05,000
That we're pretty much locked into, but then we do have a DOT grant paying about 25% of that $400,000 is noted there and will be happy to complete that arterial Washington Street.

1380
01:54:05,000 --> 01:54:10,000
This is the this is the section between Franklin Street and Lake Lake Street.

1381
01:54:10,000 --> 01:54:19,000
This in front of inventors and so some of the things that will be coming to the board with later this year is.

1382
01:54:19,000 --> 01:54:21,000
Some ideas for streetscaping.

1383
01:54:21,000 --> 01:54:33,000
So this isn't this isn't Franklin Street, but it is part of our downtown and we want to not only make it functional, but make it attractive place for.

1384
01:54:33,000 --> 01:54:40,000
Our residents and visitors is Holden, including water main replacement and sanitary sewer lining.

1385
01:54:40,000 --> 01:54:41,000
Yes.

1386
01:54:41,000 --> 01:54:42,000
Yes.

1387
01:54:42,000 --> 01:54:43,000
Yes.

1388
01:54:43,000 --> 01:54:44,000
Okay.

1389
01:54:44,000 --> 01:54:48,000
Isn't the southern half of Holden's already PVC.

1390
01:54:49,000 --> 01:54:50,000
Yes.

1391
01:54:50,000 --> 01:54:51,000
Yes.

1392
01:54:51,000 --> 01:54:53,000
So, so that that we're not replacing.

1393
01:54:53,000 --> 01:54:54,000
Yeah.

1394
01:54:54,000 --> 01:54:55,000
What's PVC where not.

1395
01:54:55,000 --> 01:54:56,000
We're not.

1396
01:54:56,000 --> 01:54:57,000
Okay.

1397
01:54:57,000 --> 01:54:58,000
Yeah.

1398
01:54:58,000 --> 01:54:59,000
All right.

1399
01:54:59,000 --> 01:55:00,000
Just.

1400
01:55:00,000 --> 01:55:01,000
Yes.

1401
01:55:01,000 --> 01:55:02,000
Just the cast iron or duct.

1402
01:55:02,000 --> 01:55:04,000
Whatever is not PVC will be replaced.

1403
01:55:04,000 --> 01:55:05,000
All the.

1404
01:55:05,000 --> 01:55:07,000
PVC will stay in place.

1405
01:55:07,000 --> 01:55:15,000
And so we'll be lining the mains and we are looking at either replacing.

1406
01:55:16,000 --> 01:55:21,000
Sewer laterals up to the property line or possibly.

1407
01:55:21,000 --> 01:55:27,000
Doing a grounding of them because we're finding that we're getting.

1408
01:55:27,000 --> 01:55:29,000
Too much inflow from our.

1409
01:55:29,000 --> 01:55:32,000
I should say infiltration from the.

1410
01:55:32,000 --> 01:55:34,000
From the sewer laterals.

1411
01:55:34,000 --> 01:55:36,000
All right.

1412
01:55:36,000 --> 01:55:41,000
The same thing for Washington will replace the block that has.

1413
01:55:42,000 --> 01:55:44,000
One block has.

1414
01:55:44,000 --> 01:55:45,000
Duck line pipe.

1415
01:55:45,000 --> 01:55:47,000
The other block has.

1416
01:55:47,000 --> 01:55:48,000
Is PVC.

1417
01:55:48,000 --> 01:55:50,000
So we're.

1418
01:55:50,000 --> 01:55:52,000
Be replacing the iron pipe.

1419
01:55:52,000 --> 01:55:54,000
And not to be difficult with it.

1420
01:55:54,000 --> 01:55:56,000
But for next month.

1421
01:55:56,000 --> 01:56:00,000
Could you have the breakdown as to what my other costs then is.

1422
01:56:00,000 --> 01:56:03,000
For water and sewer utility also with it.

1423
01:56:03,000 --> 01:56:05,000
Those are in different.

1424
01:56:05,000 --> 01:56:06,000
Well, those are different.

1425
01:56:06,000 --> 01:56:07,000
Okay.

1426
01:56:07,000 --> 01:56:08,000
Okay.

1427
01:56:08,000 --> 01:56:09,000
This is just the road.

1428
01:56:09,000 --> 01:56:10,000
Okay.

1429
01:56:11,000 --> 01:56:13,000
So you didn't think that was enough money is what you're.

1430
01:56:13,000 --> 01:56:14,000
Is what you're driving at.

1431
01:56:14,000 --> 01:56:16,000
I know it was enough for not.

1432
01:56:16,000 --> 01:56:18,000
I know that wouldn't be enough.

1433
01:56:18,000 --> 01:56:19,000
Okay.

1434
01:56:19,000 --> 01:56:20,000
Yeah.

1435
01:56:20,000 --> 01:56:21,000
Yes.

1436
01:56:21,000 --> 01:56:24,000
Downtown streetlight replacement.

1437
01:56:24,000 --> 01:56:27,000
This is under design.

1438
01:56:27,000 --> 01:56:31,000
We're doing some budget refinement on this.

1439
01:56:31,000 --> 01:56:32,000
But let's see.

1440
01:56:32,000 --> 01:56:33,000
This too.

1441
01:56:33,000 --> 01:56:34,000
So all these.

1442
01:56:34,000 --> 01:56:36,000
All these squares.

1443
01:56:36,000 --> 01:56:37,000
These are.

1444
01:56:38,000 --> 01:56:41,000
Street lights that'll be replaced, but ignore what's in the.

1445
01:56:41,000 --> 01:56:42,000
Marina parking lot.

1446
01:56:42,000 --> 01:56:45,000
This does not include the marina parking lot.

1447
01:56:45,000 --> 01:56:48,000
That would be a separate project for another day.

1448
01:56:48,000 --> 01:56:50,000
Alley projects.

1449
01:56:50,000 --> 01:56:52,000
We've identified.

1450
01:56:52,000 --> 01:56:54,000
Oops.

1451
01:56:54,000 --> 01:56:59,000
So we have this little map.

1452
01:56:59,000 --> 01:57:03,000
This will be included in the budget, which has an alley condition rating.

1453
01:57:04,000 --> 01:57:06,000
You know, overall are.

1454
01:57:06,000 --> 01:57:09,000
You know, our overall.

1455
01:57:09,000 --> 01:57:10,000
Alley condition.

1456
01:57:10,000 --> 01:57:11,000
Pretty.

1457
01:57:11,000 --> 01:57:13,000
There's a pretty good.

1458
01:57:13,000 --> 01:57:15,000
Distribution between rebuild.

1459
01:57:15,000 --> 01:57:16,000
Poor.

1460
01:57:16,000 --> 01:57:17,000
Okay.

1461
01:57:17,000 --> 01:57:18,000
Good new.

1462
01:57:18,000 --> 01:57:21,000
We are focusing on these.

1463
01:57:21,000 --> 01:57:22,000
Two southern ones.

1464
01:57:22,000 --> 01:57:23,000
Right.

1465
01:57:23,000 --> 01:57:24,000
Roger.

1466
01:57:24,000 --> 01:57:25,000
And.

1467
01:57:25,000 --> 01:57:28,000
Possibly one more or two more.

1468
01:57:28,000 --> 01:57:30,000
Up in the north.

1469
01:57:30,000 --> 01:57:31,000
This one here.

1470
01:57:31,000 --> 01:57:32,000
Yes.

1471
01:57:32,000 --> 01:57:33,000
Okay.

1472
01:57:33,000 --> 01:57:34,000
So the.

1473
01:57:34,000 --> 01:57:35,000
Oh, yeah.

1474
01:57:35,000 --> 01:57:36,000
That's right.

1475
01:57:36,000 --> 01:57:37,000
Behind Millen Street.

1476
01:57:37,000 --> 01:57:38,000
By Woodland.

1477
01:57:38,000 --> 01:57:39,000
Right.

1478
01:57:39,000 --> 01:57:43,000
And possibly who we hope to do one up near Cleveland street.

1479
01:57:43,000 --> 01:57:48,000
If there's favorable bidding, but I'm not holding my breath.

1480
01:57:48,000 --> 01:57:52,000
Did we ever come up with a solution for the Laraby street?

1481
01:57:52,000 --> 01:58:00,000
Alley considering that it's very much outside of the right away.

1482
01:58:00,000 --> 01:58:01,000
Or significant portions of it.

1483
01:58:01,000 --> 01:58:03,000
I should see her outside the right way.

1484
01:58:03,000 --> 01:58:04,000
It's right.

1485
01:58:04,000 --> 01:58:05,000
We're.

1486
01:58:05,000 --> 01:58:07,000
That one's going to take a little bit more work.

1487
01:58:07,000 --> 01:58:08,000
Okay.

1488
01:58:08,000 --> 01:58:09,000
Yeah.

1489
01:58:09,000 --> 01:58:12,000
So we're very unlikely that we'll be doing anything with it this year.

1490
01:58:12,000 --> 01:58:13,000
All right.

1491
01:58:13,000 --> 01:58:16,000
General sidewalk projects were in the.

1492
01:58:16,000 --> 01:58:18,000
We're just beginning our.

1493
01:58:18,000 --> 01:58:20,000
What is actually money from 2025.

1494
01:58:20,000 --> 01:58:22,000
That was pushed over to 2026.

1495
01:58:22,000 --> 01:58:26,000
And in the process of doing survey work for our 26 project.

1496
01:58:27,000 --> 01:58:30,000
But again, this isn't every every year project sidewalk.

1497
01:58:30,000 --> 01:58:37,000
Of course needs to be replaced every year to keep up with.

1498
01:58:37,000 --> 01:58:40,000
Eliminating trip hazards.

1499
01:58:40,000 --> 01:58:42,000
Future street projects.

1500
01:58:42,000 --> 01:58:46,000
I'm not going to take the time to go through all of them, but this is.

1501
01:58:46,000 --> 01:58:47,000
See if I can.

1502
01:58:47,000 --> 01:58:50,000
And I'll have to shrink this down here for a moment.

1503
01:58:50,000 --> 01:58:54,000
To be able to see it, but this is where we.

1504
01:58:55,000 --> 01:59:00,000
Have projected right now these various street improvements.

1505
01:59:00,000 --> 01:59:07,000
But these are subject to change based on experiences we have with replacing water mains.

1506
01:59:07,000 --> 01:59:13,000
Street deterioration sometimes accelerates.

1507
01:59:13,000 --> 01:59:17,000
These are in really, I think.

1508
01:59:17,000 --> 01:59:23,000
Maybe it's no coincidence, but they do correlate really well to.

1509
01:59:23,000 --> 01:59:28,000
The street condition in the presence of lead laterals coincide.

1510
01:59:28,000 --> 01:59:29,000
So.

1511
01:59:29,000 --> 01:59:33,000
So every street that's going to have to be torn up for.

1512
01:59:33,000 --> 01:59:36,000
Lead service lateral replacement.

1513
01:59:36,000 --> 01:59:39,000
Is it is a street that's.

1514
01:59:39,000 --> 01:59:43,000
In poor condition anyway, so we're not tearing up any.

1515
01:59:43,000 --> 01:59:47,000
Newer streets for for our lead lateral replacement.

1516
01:59:47,000 --> 01:59:49,000
And conversely, they just bought.

1517
01:59:49,000 --> 01:59:51,000
Well, I shouldn't say that we do have.

1518
01:59:51,000 --> 01:59:54,000
We do have streets in our poor condition that don't have lead laterals, but.

1519
01:59:54,000 --> 01:59:57,000
We're prioritizing those first.

1520
01:59:57,000 --> 02:00:04,000
Okay, and they'll get us bigger again.

1521
02:00:04,000 --> 02:00:07,000
Okay.

1522
02:00:07,000 --> 02:00:09,000
Okay.

1523
02:00:10,000 --> 02:00:11,000
This is off.

1524
02:00:11,000 --> 02:00:17,000
So, and because this is expanded, you can't see this D column is is the current year 2026.

1525
02:00:17,000 --> 02:00:19,000
He is 2027.

1526
02:00:19,000 --> 02:00:22,000
He's 2028 and so on.

1527
02:00:22,000 --> 02:00:24,000
So just.

1528
02:00:24,000 --> 02:00:29,000
This is a section of sock road that's.

1529
02:00:29,000 --> 02:00:32,000
Essentially West of.

1530
02:00:32,000 --> 02:00:35,000
Yeah, West of Newport Vista on the sock road.

1531
02:00:35,000 --> 02:00:38,000
There's three or four.

1532
02:00:39,000 --> 02:00:41,000
Jurisdictions.

1533
02:00:41,000 --> 02:00:42,000
Four.

1534
02:00:42,000 --> 02:00:43,000
Yes, I thought.

1535
02:00:43,000 --> 02:00:44,000
So there's four.

1536
02:00:44,000 --> 02:00:46,000
There's four taxing jurisdictions.

1537
02:00:46,000 --> 02:00:47,000
So we're dividing the cost.

1538
02:00:47,000 --> 02:00:52,000
That's why that $150,000 is ended for our portion of it.

1539
02:00:52,000 --> 02:00:55,000
That highway 33 grand Avenue.

1540
02:00:55,000 --> 02:00:57,000
That's not the project that's that's happening.

1541
02:00:57,000 --> 02:00:59,000
That's beginning next week.

1542
02:00:59,000 --> 02:01:02,000
That's currently scheduled for 2034.

1543
02:01:02,000 --> 02:01:07,000
That's a complete reconstruction of grand Avenue all the way from tower and summit down to Franklin street.

1544
02:01:08,000 --> 02:01:15,000
And when we do that project, we can incorporate, hopefully, none of the number of the elements from the downtown plan.

1545
02:01:15,000 --> 02:01:17,000
So we're keeping that on the radar.

1546
02:01:17,000 --> 02:01:18,000
But.

1547
02:01:18,000 --> 02:01:24,000
Right now, I think we have a budget number in there of $2.2 million, but we don't have an SMA yet.

1548
02:01:24,000 --> 02:01:27,000
That's a statement is full agreement with the DOT.

1549
02:01:27,000 --> 02:01:28,000
So I can't.

1550
02:01:28,000 --> 02:01:30,000
I don't have.

1551
02:01:30,000 --> 02:01:32,000
I don't have a lot of information on it.

1552
02:01:32,000 --> 02:01:36,000
But again, it's we're looking at eight or nine years out.

1553
02:01:37,000 --> 02:01:42,000
We talked last week about the last month about the inner urban trail railroad underpass.

1554
02:01:42,000 --> 02:01:46,000
And that has been submitted to the federal highway administration.

1555
02:01:46,000 --> 02:01:49,000
And so we're keeping our fingers crossed that we do get that grant.

1556
02:01:49,000 --> 02:01:54,000
And right now we have that in 2028, 2029.

1557
02:01:54,000 --> 02:02:03,000
Again, that is we are we as staff are looking at that as a grant dependent project so that if the grant goes away,

1558
02:02:03,000 --> 02:02:11,000
the project goes away unless the board and the council would put it back in the budget.

1559
02:02:11,000 --> 02:02:18,000
That first item of highway 33 crossover, it's Sweetwater Drive.

1560
02:02:18,000 --> 02:02:28,000
So when was that resurfaces the highway this year, they will be putting in a left hand turn lane to go north into the future.

1561
02:02:29,000 --> 02:02:34,000
Extension of Sweetwater south of highway 33 for development of the Shannon farm.

1562
02:02:34,000 --> 02:02:37,000
Roger alluded to earlier.

1563
02:02:37,000 --> 02:02:39,000
We're also working on.

1564
02:02:39,000 --> 02:02:46,000
We have money in the budget this year for improvements to meet our TMDL as Aaron was talking about before.

1565
02:02:46,000 --> 02:02:50,000
So it all kind of ties in traffic signal upgrades.

1566
02:02:50,000 --> 02:02:51,000
So we upgraded that.

1567
02:02:51,000 --> 02:02:54,000
So we only have three traffic signals in the whole city.

1568
02:02:54,000 --> 02:02:58,000
So we improved the one here at the intersection downtown.

1569
02:02:58,000 --> 02:03:06,000
And so we're going to improve Spring Street and the intersection at LL on 32 this year with that money.

1570
02:03:06,000 --> 02:03:14,000
And traffic safety has some budget and amounts for next year for safety improvements at.

1571
02:03:14,000 --> 02:03:16,000
Interurban trail crossings.

1572
02:03:16,000 --> 02:03:18,000
I won't get into it.

1573
02:03:19,000 --> 02:03:20,000
I'm going to be looking at the

1574
02:03:20,000 --> 02:03:24,000
project expansion and renovation.

1575
02:03:24,000 --> 02:03:29,000
As many of you know, we have a.

1576
02:03:29,000 --> 02:03:38,000
We established impact fees this year to fund design and construction of garage expansion renovation for the street department and.

1577
02:03:38,000 --> 02:03:40,000
The parks.

1578
02:03:40,000 --> 02:03:42,000
Parks department.

1579
02:03:43,000 --> 02:03:47,000
And right now I have that plugged in is 2027 and 2028.

1580
02:03:47,000 --> 02:03:50,000
But again, this is the don't.

1581
02:03:50,000 --> 02:03:54,000
That that could well shift and it's going to tie into.

1582
02:03:54,000 --> 02:03:58,000
I'm likely going to be coming back with the proposal to do.

1583
02:03:58,000 --> 02:04:04,000
A study on how that meshes with our water treatment plant.

1584
02:04:04,000 --> 02:04:09,000
Field operations because they are looking for a new home after.

1585
02:04:10,000 --> 02:04:13,000
They're much of their space was taken by.

1586
02:04:13,000 --> 02:04:20,000
The plant renovations. So we had looked at expanding the footprint of the water utility building.

1587
02:04:20,000 --> 02:04:26,000
We decided not to do that. So we're going to go in a different location.

1588
02:04:26,000 --> 02:04:32,000
So whether or not that pairs with the street department garage, we've yet to.

1589
02:04:32,000 --> 02:04:37,000
Closely study what is in our best interest.

1590
02:04:38,000 --> 02:04:43,000
But in either case, we are looking at street department improvements.

1591
02:04:43,000 --> 02:04:47,000
City Hall.

1592
02:04:47,000 --> 02:04:50,000
City Hall, the library and senior center.

1593
02:04:50,000 --> 02:04:56,000
I'll need some HVAC improvements. So I've kind of it's a they're all working well, but.

1594
02:04:56,000 --> 02:05:00,000
Also nearing the end of their life. And so it's a little bit of a.

1595
02:05:01,000 --> 02:05:05,000
Guessing game is to, you know, how long.

1596
02:05:05,000 --> 02:05:09,000
We can rely on them, but I have that scheduled out for 2029.

1597
02:05:09,000 --> 02:05:12,000
Boiler replacements is beyond that.

1598
02:05:12,000 --> 02:05:15,000
Generated the generator for this building.

1599
02:05:15,000 --> 02:05:20,000
Really doesn't do a lot other than light a few outlets in the.

1600
02:05:20,000 --> 02:05:25,000
And the finance director's office. And so we are looking at.

1601
02:05:25,000 --> 02:05:33,000
Increasing the size of that and its ability to power the building in case there would be a.

1602
02:05:33,000 --> 02:05:38,000
And a long term outage.

1603
02:05:40,000 --> 02:05:45,000
Going to the fire alarm panel is this is from our facility condition assessment.

1604
02:05:45,000 --> 02:05:49,000
That's beyond its useful life. And so we have that programmed in.

1605
02:05:49,000 --> 02:05:52,000
I skipped over the plumbing and city hall.

1606
02:05:52,000 --> 02:05:56,000
Some of it is pretty poor and we've had to do some replacements.

1607
02:05:56,000 --> 02:06:03,000
And so we're we're looking out again in like 2029 to replace all the plumbing.

1608
02:06:03,000 --> 02:06:10,000
I'm going to take I took this one. I'm going to take that one out. That is going to go in a different section, but.

1609
02:06:10,000 --> 02:06:21,000
Maybe it's worth noting that it's possible that we might need to make some maybe improvements as we've had some difficulties at the end of the night, but that's again, that is not.

1610
02:06:22,000 --> 02:06:25,000
Part of the.

1611
02:06:25,000 --> 02:06:27,000
Public works.

1612
02:06:27,000 --> 02:06:29,000
Budget.

1613
02:06:29,000 --> 02:06:34,000
All right, we'll skip over recreation. John will cover that with the park and rec.

1614
02:06:34,000 --> 02:06:40,000
As well as the senior center, although I'll just I will note since I'm maintaining the facilities.

1615
02:06:40,000 --> 02:06:43,000
We do have the sandstone.

1616
02:06:44,000 --> 02:06:52,000
At the front entrance resetting that and windows and tuck pointing. I have that currently in the budget for next year.

1617
02:06:52,000 --> 02:07:01,000
HVC HVAC out a little further, but again, that can all these things can can move as we go through the budget.

1618
02:07:01,000 --> 02:07:08,000
Library don't have anything scheduled for for next year, but again, still being evaluated.

1619
02:07:09,000 --> 02:07:13,000
Valley Creek.

1620
02:07:13,000 --> 02:07:21,000
Again, I don't know if this project is going to begin in 2027. A lot of it is grand dependent, even though we have funding in the TID.

1621
02:07:21,000 --> 02:07:25,000
And in terms of.

1622
02:07:25,000 --> 02:07:30,000
There's there's only certain times we can work in the creek because of.

1623
02:07:31,000 --> 02:07:40,000
Fish movements and so whether or not this is a project that begins in 2027 or 2028 is still to be determined.

1624
02:07:40,000 --> 02:07:43,000
But.

1625
02:07:43,000 --> 02:07:45,000
And.

1626
02:07:45,000 --> 02:07:50,000
Given that our intent at least at this point is to.

1627
02:07:50,000 --> 02:07:59,000
We are hopefully going to come back with that $5 million grant from national fish and wildlife coastal resiliency fund.

1628
02:07:59,000 --> 02:08:08,000
And then apply for presumably another $5 million in the following year.

1629
02:08:08,000 --> 02:08:12,000
Partly Park the only well, there's two items I want to.

1630
02:08:12,000 --> 02:08:19,000
Well, I guess more than two. So the items. I'm not going to focus on the bathrooms that parks and rack, but moving the.

1631
02:08:19,000 --> 02:08:21,000
Moving the road.

1632
02:08:21,000 --> 02:08:26,000
You know, that's something I guess I want to get a feel from this board on.

1633
02:08:26,000 --> 02:08:30,000
You know, tell me right now, but on how.

1634
02:08:30,000 --> 02:08:32,000
We would like to.

1635
02:08:32,000 --> 02:08:40,000
What urgency we would want to give that project. So we've talked about moving the road. Of course, we moved it on a temporary measure to.

1636
02:08:40,000 --> 02:08:48,000
In response to the bluff erosion, but we've we've talked about.

1637
02:08:48,000 --> 02:08:56,000
Realigning that street on the west side of the park so that it's no longer in danger of being eroded and having a.

1638
02:08:56,000 --> 02:09:03,000
A walkway system so that that pedestrians and bicyclists don't have to be on the road.

1639
02:09:03,000 --> 02:09:06,000
And the.

1640
02:09:06,000 --> 02:09:14,000
And the lighting up there is we energies lighting and they've been telling me for years that it's failing. And so anytime a light goes out.

1641
02:09:14,000 --> 02:09:20,000
It essentially gets taken off the taking off the grid. And so there are some lights out there that are.

1642
02:09:20,000 --> 02:09:26,000
Not lit and will not be lit. And so they're eventually we're going to have to replace that system either with the new.

1643
02:09:26,000 --> 02:09:31,000
We energy system or our own system. So I put in a placeholder.

1644
02:09:31,000 --> 02:09:41,000
For that as well. Again, I'm showing 2027 design 2028 construction, but as you'll see as we go through this, we have a lot of things.

1645
02:09:41,000 --> 02:09:46,000
And the budget for 2027 and.

1646
02:09:46,000 --> 02:09:55,000
Really only me and Roger. And so there's a little bit of capacity issue that we have to address to make sure that we give these into these projects, the.

1647
02:09:55,000 --> 02:09:58,000
The tension that they need.

1648
02:09:58,000 --> 02:10:03,000
And then lastly here in the yellow is the grant we just talked about the.

1649
02:10:04,000 --> 02:10:11,000
So go grant that is a grant that we have been awarded and that is the upper lake park.

1650
02:10:11,000 --> 02:10:17,000
Essentially prayer restoration and stormwater management and that that ties into the current.

1651
02:10:17,000 --> 02:10:19,000
Court plan.

1652
02:10:19,000 --> 02:10:25,000
Comprehensive outdoor recreation plan shows shows these improvements in it. And so though.

1653
02:10:25,000 --> 02:10:28,000
Those things align.

1654
02:10:29,000 --> 02:10:38,000
I'll just know John has 10. This is from the facility condition assessment recommendations that we do a swimming pool study. So John has that in his budget.

1655
02:10:38,000 --> 02:10:41,000
He's a number of projects over the next.

1656
02:10:41,000 --> 02:10:45,000
Well, this year next year for his parks.

1657
02:10:45,000 --> 02:10:53,000
Pebble House rehabilitation that is budgeted for this year. I'll be honest, we have not gotten started on that.

1658
02:10:54,000 --> 02:10:55,000
Yet.

1659
02:10:55,000 --> 02:10:56,000
The judge Eggert House.

1660
02:10:56,000 --> 02:11:02,000
General repairs is underway and we are working with them also on roof.

1661
02:11:02,000 --> 02:11:04,000
Replacement. So we had that.

1662
02:11:04,000 --> 02:11:12,000
With the roof scheduled out of a few years initially, but I believe that's going to be accomplished this year.

1663
02:11:12,000 --> 02:11:14,000
Late House generator.

1664
02:11:14,000 --> 02:11:18,000
Actually called me about that today. We have yet to speak.

1665
02:11:19,000 --> 02:11:22,000
Streets division has a number of.

1666
02:11:22,000 --> 02:11:25,000
You know, we're on a rotating basis with our.

1667
02:11:25,000 --> 02:11:29,000
Working with our finance director on equipment and.

1668
02:11:29,000 --> 02:11:32,000
And vehicles and so this is reflected.

1669
02:11:32,000 --> 02:11:36,000
On these line items here.

1670
02:11:36,000 --> 02:11:48,000
All right, so we're televising, we're televising about eight miles every year.

1671
02:11:48,000 --> 02:11:51,000
We're lining about two miles every year.

1672
02:11:51,000 --> 02:11:59,000
These the sewer laterals, those align with our street improvement projects where we're going to.

1673
02:12:00,000 --> 02:12:12,000
I never do improve the private laterals. We haven't done that in the past, but we're again, getting so much infiltration from the laterals that we feel that.

1674
02:12:12,000 --> 02:12:16,000
Now is the time to address that when we're reconstructing.

1675
02:12:16,000 --> 02:12:19,000
Our older streets.

1676
02:12:19,000 --> 02:12:26,000
This is just a street overflow man hall that's.

1677
02:12:27,000 --> 02:12:32,000
Long held project that we're hopefully finally going to complete this year.

1678
02:12:32,000 --> 02:12:37,000
And moving on to this is.

1679
02:12:37,000 --> 02:12:42,000
So on mineral Springs Creek, we have.

1680
02:12:42,000 --> 02:12:48,000
Two crossings where the pipe was once under the creek and it is now going through the creek.

1681
02:12:48,000 --> 02:12:53,000
So we want to protect those pipes from from damage of.

1682
02:12:54,000 --> 02:12:57,000
Bolders or whatnot coming down the creek and.

1683
02:12:57,000 --> 02:13:01,000
Naturally, we don't want our sanitary sewers on the surface of the.

1684
02:13:01,000 --> 02:13:05,000
On the on the surface and so we are working with the.

1685
02:13:05,000 --> 02:13:09,000
County to get those buried and.

1686
02:13:09,000 --> 02:13:16,000
So we're in the design phase this year and we would like to have the improvements constructed next year again.

1687
02:13:16,000 --> 02:13:21,000
This is that is a project of some urgency.

1688
02:13:22,000 --> 02:13:25,000
The remote site septage receiving station.

1689
02:13:25,000 --> 02:13:29,000
I'm sorry, don't have any pictures, but.

1690
02:13:29,000 --> 02:13:38,000
But this is where all our haulers come to bring in outside waste, whether it's Port of John or trailer park or.

1691
02:13:38,000 --> 02:13:41,000
Other ways that are brought in.

1692
02:13:41,000 --> 02:13:50,000
It's a revenue generator for the wastewater plant, but it's a bit outdated in that much of it is pretty much on the honor system out there.

1693
02:13:50,000 --> 02:13:56,000
And so this board has already improved the approve the.

1694
02:13:56,000 --> 02:14:01,000
Design of modifications to the plan to essentially.

1695
02:14:01,000 --> 02:14:06,000
Modernize it, make it more secure and make it.

1696
02:14:06,000 --> 02:14:12,000
Unreliant on the honor system and includes a sampling sampling system.

1697
02:14:12,000 --> 02:14:17,000
So we know the strength of the waste and monitors the amount of waste that they're.

1698
02:14:18,000 --> 02:14:22,000
Putting into the receiving station. This $1.2 million.

1699
02:14:22,000 --> 02:14:25,000
Dan assures me that this is.

1700
02:14:25,000 --> 02:14:28,000
That's just a placeholder seat.

1701
02:14:28,000 --> 02:14:32,000
I think you're going to anticipate that number coming down quite a bit.

1702
02:14:32,000 --> 02:14:36,000
Moving forward.

1703
02:14:36,000 --> 02:14:44,000
We're maintaining the equipment in our lift stations and so Dan has that spread out over the next three years.

1704
02:14:44,000 --> 02:14:47,000
Waste water treatment plan.

1705
02:14:47,000 --> 02:14:50,000
Is.

1706
02:14:50,000 --> 02:14:57,000
The the EFS so that's the EFS that's the coating is kind of like a stucco that's on the on the building.

1707
02:14:57,000 --> 02:15:00,000
I think is on the it's adhered to the original brick.

1708
02:15:00,000 --> 02:15:04,000
So that's failing in a number of areas and in the paint.

1709
02:15:04,000 --> 02:15:07,000
See if I.

1710
02:15:08,000 --> 02:15:15,000
It's not looking super sharp over there and so we are looking to.

1711
02:15:15,000 --> 02:15:20,000
Prove the appearance of the plant and improve security down there.

1712
02:15:20,000 --> 02:15:22,000
And so Dan has a placeholder for.

1713
02:15:22,000 --> 02:15:24,000
For that work.

1714
02:15:24,000 --> 02:15:27,000
The gravity belt thickeners need to be rebuilt.

1715
02:15:27,000 --> 02:15:33,000
And if you're wondering what a gravity belt thickener looks like, there it is.

1716
02:15:34,000 --> 02:15:39,000
And so this we have to do these thickeners that again.

1717
02:15:39,000 --> 02:15:44,000
We need that redundancy and we need them need them to be.

1718
02:15:44,000 --> 02:15:52,000
Operational and so we have money budgeted over the next two years to rebuild those.

1719
02:15:52,000 --> 02:15:59,000
Some other items maintaining the equipment of the wastewater treatment plant.

1720
02:16:00,000 --> 02:16:05,000
And then the future replacement of our emergent.

1721
02:16:05,000 --> 02:16:09,000
Our mobile emergency generator and our mobile emergency trash pump.

1722
02:16:09,000 --> 02:16:17,000
So if we have a failed sewer, we need to make sure that we can bypass pump quickly.

1723
02:16:18,000 --> 02:16:25,000
Utility truck and crane, which will assist us in.

1724
02:16:25,000 --> 02:16:28,000
Maintaining our pumps, which we're currently not.

1725
02:16:28,000 --> 02:16:32,000
Are not being maintained to the.

1726
02:16:32,000 --> 02:16:35,000
To the extent that we.

1727
02:16:35,000 --> 02:16:36,000
Yeah, it's what.

1728
02:16:36,000 --> 02:16:38,000
No, but they're not.

1729
02:16:38,000 --> 02:16:41,000
They still are they pulling them every month.

1730
02:16:42,000 --> 02:16:46,000
Yeah, so it's currently being contracted.

1731
02:16:46,000 --> 02:16:55,000
But again, we would elevate the level of service that they would get if we would have the equipment that could assist us in that work.

1732
02:16:55,000 --> 02:17:00,000
Marina projects, North building renovation.

1733
02:17:00,000 --> 02:17:04,000
This is this is a project that was originally.

1734
02:17:05,000 --> 02:17:13,000
Included in this year's budget for design of improvements to enclose the breeze way.

1735
02:17:13,000 --> 02:17:19,000
It sent separates the bathrooms from the lounge area and kind of the picnic area and would.

1736
02:17:19,000 --> 02:17:25,000
Cover the picnic area with something a little more permanent than a tent.

1737
02:17:25,000 --> 02:17:33,000
And so that that is currently been moved to 2027 and 2028.

1738
02:17:34,000 --> 02:17:37,000
The windows and doors need to be replaced at the Marina control building.

1739
02:17:37,000 --> 02:17:40,000
So again, that does not come out of the general fund.

1740
02:17:40,000 --> 02:17:46,000
That is all out of Marina reserves, which is fully paid for by the Marina tenants.

1741
02:17:46,000 --> 02:17:52,000
I resurfaced seeing the parking lot. We have out to 2029, but that's something, you know, I was.

1742
02:17:52,000 --> 02:17:55,000
Thinking about again, as Aaron was talking, Aaron.

1743
02:17:56,000 --> 02:18:01,000
I was talking about earlier that ways that we can meet the Northeast TMDL and that's something that we did.

1744
02:18:01,000 --> 02:18:08,000
That we'll be strongly looking at to see what effect that could have on meeting those.

1745
02:18:08,000 --> 02:18:13,000
Stormwater quality goals by perhaps.

1746
02:18:13,000 --> 02:18:18,000
Instituting some green or including some green infrastructure under the Marina parking lot.

1747
02:18:18,000 --> 02:18:24,000
So that's something again, we have concept plan or schematic engineering.

1748
02:18:24,000 --> 02:18:31,000
There's command occurs that are we at 60% sorry to put you on the spot.

1749
02:18:31,000 --> 02:18:39,000
Yeah, it is schematic. So that's 30% design of parking lot improvements that was funded by through a grant.

1750
02:18:39,000 --> 02:18:43,000
And that work was done by Edgewater, but we have yet to implement that.

1751
02:18:43,000 --> 02:18:47,000
So we have that we have that kicked out a little bit.

1752
02:18:48,000 --> 02:18:55,000
Ultimately, the Marina would like to replace their fixed peers and the West.

1753
02:18:55,000 --> 02:19:01,000
I'm sorry, the North slip with floating docks, but that does have an effect on their.

1754
02:19:01,000 --> 02:19:07,000
The amount of docs that are available. And so that's something that is.

1755
02:19:07,000 --> 02:19:11,000
Currently being scheduled for 2030.

1756
02:19:11,000 --> 02:19:15,000
And dredging is out, I think about 10 years.

1757
02:19:16,000 --> 02:19:20,000
And then the Marina parking lot lights as we're going through our.

1758
02:19:20,000 --> 02:19:26,000
That street light project are consultant noted that.

1759
02:19:26,000 --> 02:19:28,000
That they are.

1760
02:19:28,000 --> 02:19:35,000
In rough shape down there, and so that may be something we need to address as early as 2029.

1761
02:19:36,000 --> 02:19:48,000
Water main project. So we have Holden Street and Washington Street that we talked about future water main projects associated with all those other street improvements.

1762
02:19:48,000 --> 02:19:54,000
Same thing for Grand Grand Avenue. That's programmed out for 2034.

1763
02:19:55,000 --> 02:19:59,000
In 2026, we'd like to.

1764
02:19:59,000 --> 02:20:06,000
Implement SCADA and electrical improvements to our Thomas tower so that we have better control from the plant.

1765
02:20:06,000 --> 02:20:12,000
Of what's going on at the tower so that they essentially communicate better.

1766
02:20:12,000 --> 02:20:21,000
We also want to install a mixer in the Thomas tower because we have problems with icing and water quality that we'd like that.

1767
02:20:21,000 --> 02:20:25,000
We feel could be improved by that.

1768
02:20:25,000 --> 02:20:31,000
And then doing the same thing at the West tower and mineral Springs tower in the future.

1769
02:20:31,000 --> 02:20:38,000
A PRV is a pressure reducing valve that needs to be replaced on hails trails.

1770
02:20:38,000 --> 02:20:42,000
So we have that schedule for this year.

1771
02:20:42,000 --> 02:20:50,000
Yeah, done. I thought it was done. All right. And Woodland Avenue scheduled for next year.

1772
02:20:51,000 --> 02:20:57,000
Let lateral replacement again. That is something we have a 13 year window to complete. And so we have.

1773
02:20:57,000 --> 02:21:01,000
This we have that essentially budgeted.

1774
02:21:01,000 --> 02:21:07,000
Through the next 10 years to replace lead laterals and to special assess.

1775
02:21:07,000 --> 02:21:14,000
Properties, but that will be going to GGF at the July 7th meeting. I do believe.

1776
02:21:15,000 --> 02:21:23,000
Water plant roof replacement that was when that was installed about.

1777
02:21:23,000 --> 02:21:30,000
15 years ago at a 20 year life and so right at around year 20 is where we have it.

1778
02:21:30,000 --> 02:21:34,000
Budgeted for replacement.

1779
02:21:34,000 --> 02:21:43,000
We've talked at this board before about a service driveway to the generator which we may recall we installed the generator on the north side of the.

1780
02:21:43,000 --> 02:21:48,000
Water treatment plant rather than putting it on.

1781
02:21:48,000 --> 02:21:55,000
Then adding what amounted to was a portion of a second story to the.

1782
02:21:55,000 --> 02:21:59,000
To the where we have the nuclear well building.

1783
02:21:59,000 --> 02:22:06,000
We felt this was kind of a win win. The neighbors across the street were happy that the building had a lower profile and.

1784
02:22:06,000 --> 02:22:12,000
And it also opened up more room for us in the new.

1785
02:22:12,000 --> 02:22:15,000
In the new building so.

1786
02:22:15,000 --> 02:22:21,000
East path restoration so I have an image of that as well I can share so.

1787
02:22:21,000 --> 02:22:26,000
Dan has some ideas to improve that the.

1788
02:22:26,000 --> 02:22:33,000
Appearance and functionality of this important piece of our lakefront walkway.

1789
02:22:33,000 --> 02:22:35,000
So I have some money budgeted.

1790
02:22:36,000 --> 02:22:38,000
For that.

1791
02:22:38,000 --> 02:22:41,000
Replacement of the water utility.

1792
02:22:41,000 --> 02:22:46,000
The water utility wants to replace its 2002 back loader backhoe.

1793
02:22:46,000 --> 02:22:49,000
And purchase an aerial lift.

1794
02:22:49,000 --> 02:22:54,000
Truck and equipment and a floor scrubber for the new building.

1795
02:22:55,000 --> 02:23:03,000
So these are other pending items that these are essentially.

1796
02:23:03,000 --> 02:23:08,000
Various projects I guess.

1797
02:23:08,000 --> 02:23:12,000
And so I've included in here I guess I want to highlight.

1798
02:23:12,000 --> 02:23:19,000
Cellular tower construction so we are considering taking our antennas off of the.

1799
02:23:20,000 --> 02:23:24,000
Water towers we only have well we have none the north tower in the west tower.

1800
02:23:24,000 --> 02:23:28,000
And putting them on stand alone poles because.

1801
02:23:28,000 --> 02:23:34,000
Of us to eliminate security concerns and also.

1802
02:23:34,000 --> 02:23:39,000
You know these these antennas can damage the.

1803
02:23:39,000 --> 02:23:41,000
Water tower and.

1804
02:23:41,000 --> 02:23:45,000
They create a problem for maintenance of the tower and so.

1805
02:23:46,000 --> 02:23:48,000
So if we take.

1806
02:23:48,000 --> 02:23:50,000
Antennas off of the.

1807
02:23:50,000 --> 02:23:53,000
Water towers we are.

1808
02:23:53,000 --> 02:23:58,000
Looking at the possibility of constructing a pole onto which those could be.

1809
02:23:58,000 --> 02:24:01,000
Adhered and then the revenue would.

1810
02:24:01,000 --> 02:24:05,000
Would come to the city rather than the water utility.

1811
02:24:05,000 --> 02:24:09,000
But that is that's that project has not been.

1812
02:24:09,000 --> 02:24:10,000
Brought to.

1813
02:24:10,000 --> 02:24:14,000
Any committee so far so but that is something where.

1814
02:24:15,000 --> 02:24:20,000
Anticipating to happen soon because we do need to paint the.

1815
02:24:20,000 --> 02:24:25,000
Thomas tower was actually originally scheduled for this year and it was put off.

1816
02:24:25,000 --> 02:24:32,000
Because of concerns with the antennas that are on it.

1817
02:24:32,000 --> 02:24:35,000
This has been on for a while the county trunk L.

1818
02:24:36,000 --> 02:24:38,000
Sidewalk.

1819
02:24:38,000 --> 02:24:41,000
Sunset bike trail so that.

1820
02:24:41,000 --> 02:24:44,000
That is the section of.

1821
02:24:44,000 --> 02:24:48,000
Bike trail that's I would say missing between sunset.

1822
02:24:48,000 --> 02:24:50,000
And.

1823
02:24:50,000 --> 02:24:54,000
The inner urban trail on the west side of L L.

1824
02:24:54,000 --> 02:24:57,000
Sorry I don't have a picture but if you can picture clean test.

1825
02:24:57,000 --> 02:25:02,000
Running alongside L on again on the west side of L L between.

1826
02:25:03,000 --> 02:25:08,000
Sunset in the inner urban trail I think that's been a segment that's been missing for.

1827
02:25:08,000 --> 02:25:10,000
Quite some time with.

1828
02:25:10,000 --> 02:25:12,000
Our development in a west of L. L. so that.

1829
02:25:12,000 --> 02:25:14,000
Ultimately they can.

1830
02:25:14,000 --> 02:25:17,000
Go southbound on the trail without having to travel.

1831
02:25:17,000 --> 02:25:21,000
East down to the bike trail on sunset and then.

1832
02:25:21,000 --> 02:25:25,000
Backtracking and then having to cross L. L. twice.

1833
02:25:25,000 --> 02:25:26,000
Wouldn't that.

1834
02:25:27,000 --> 02:25:29,000
Wouldn't that make sense to include with.

1835
02:25:29,000 --> 02:25:32,000
As part of the sunset and L. L. intersection.

1836
02:25:32,000 --> 02:25:35,000
Save a separate project.

1837
02:25:35,000 --> 02:25:38,000
I think so but.

1838
02:25:38,000 --> 02:25:40,000
The county is.

1839
02:25:40,000 --> 02:25:43,000
Just a way to say I want to make sure.

1840
02:25:43,000 --> 02:25:45,000
Include it with which project.

1841
02:25:45,000 --> 02:25:47,000
So just down to.

1842
02:25:47,000 --> 02:25:49,000
Sunset and L. L. intersection.

1843
02:25:49,000 --> 02:25:51,000
And you have the sunset.

1844
02:25:52,000 --> 02:25:54,000
The bike trail the sunset.

1845
02:25:54,000 --> 02:25:56,000
Sidewalk the year prior.

1846
02:25:56,000 --> 02:26:00,000
And it almost seems like if the intersections going forward it would make sense to.

1847
02:26:00,000 --> 02:26:04,000
Bump that back a year and include those together.

1848
02:26:04,000 --> 02:26:07,000
Right so that I mean that's a project that.

1849
02:26:07,000 --> 02:26:12,000
Really hasn't been talked about beyond traffic safety and so.

1850
02:26:12,000 --> 02:26:17,000
So some of these are some of these are placeholders for.

1851
02:26:18,000 --> 02:26:21,000
Projects that may happen but have not been yet approved.

1852
02:26:21,000 --> 02:26:25,000
And that's part of that I guess that's.

1853
02:26:25,000 --> 02:26:27,000
Part of the discussion I.

1854
02:26:27,000 --> 02:26:34,000
That I value coming out of this so that these are some of the ideas that are being talked about and.

1855
02:26:34,000 --> 02:26:40,000
In other committees like traffic safety and and whether or not this so this is something as we know there's.

1856
02:26:41,000 --> 02:26:44,000
Well some people may not know.

1857
02:26:44,000 --> 02:26:51,000
So the intersection in the city that has the most traffic accidents is L. L. and sunset and so.

1858
02:26:51,000 --> 02:26:58,000
We've been looking at ways to improve that intersection over the years and I think we have improved that intersection over the years.

1859
02:26:58,000 --> 02:27:02,000
But but accidents continue to happen.

1860
02:27:02,000 --> 02:27:09,000
And traffic safety has talked about the possibility of constructing around about at that intersection.

1861
02:27:10,000 --> 02:27:12,000
We have talked with.

1862
02:27:12,000 --> 02:27:17,000
We've reached out to the DOT for a.

1863
02:27:17,000 --> 02:27:20,000
His up grant.

1864
02:27:20,000 --> 02:27:24,000
I weigh safety improvement program and.

1865
02:27:24,000 --> 02:27:29,000
So far I haven't gotten any way but anywhere with it but have not given up on.

1866
02:27:29,000 --> 02:27:32,000
I'm trying to get money to.

1867
02:27:32,000 --> 02:27:37,000
To make some more significant improvements that intersection but.

1868
02:27:37,000 --> 02:27:41,000
Honestly if you if you ask me the.

1869
02:27:41,000 --> 02:27:48,000
The sidewalk on L. L. from sunset to the bike trail is long overdue.

1870
02:27:48,000 --> 02:27:52,000
I would say but right right now we haven't scheduled out for twenty twenty.

1871
02:27:52,000 --> 02:27:56,000
Eight and again that's something that could move in either direction.

1872
02:27:56,000 --> 02:28:00,000
And really the same thing to could be said.

1873
02:28:01,000 --> 02:28:11,000
From an L. L. on both sides of L. L. from Aster Street which is the woods at White Pine intersection down to where the sidewalk terminates the reason.

1874
02:28:11,000 --> 02:28:18,000
That's the reason that hasn't been built well one is because it's only urbanized.

1875
02:28:18,000 --> 02:28:22,000
To about halfway between.

1876
02:28:22,000 --> 02:28:26,000
Grand Avenue and Aster Street but.

1877
02:28:27,000 --> 02:28:30,000
It's a lot trickier is I'm sure you know Mike.

1878
02:28:30,000 --> 02:28:35,000
To put sidewalk there because the side slopes of the highway are so so steep.

1879
02:28:35,000 --> 02:28:38,000
There is adequate room.

1880
02:28:38,000 --> 02:28:41,000
There's there's plenty of flat area between.

1881
02:28:41,000 --> 02:28:46,000
Sunset and the bike trail to build that other section so it'd be a lot.

1882
02:28:46,000 --> 02:28:50,000
And it's only one side of the street on that.

1883
02:28:50,000 --> 02:28:55,000
Stretch so but these are two I think you know very these would be well appreciated by the people and.

1884
02:28:55,000 --> 02:29:07,000
Greystone and then woods at White Pine and so it's again been an issue of money and just staff capacity to build these improvements.

1885
02:29:07,000 --> 02:29:12,000
Robert oh yeah are you able to share this out with the board so we can.

1886
02:29:12,000 --> 02:29:14,000
Deep deep dive a little bit more.

1887
02:29:14,000 --> 02:29:19,000
Yeah I can let me clean it up and I'll get it back to.

1888
02:29:20,000 --> 02:29:22,000
Yeah I can get out to everyone.

1889
02:29:22,000 --> 02:29:27,000
I'll get it out to everyone well before the next meeting.

1890
02:29:30,000 --> 02:29:35,000
You know the same thing goes for Spring Street and Garfield box culverts at one.

1891
02:29:35,000 --> 02:29:43,000
So the Spring Street and Boxfield Garfield box culverts for those of you who have not been on the board for a while or for a long time.

1892
02:29:44,000 --> 02:29:45,000
This is.

1893
02:29:47,000 --> 02:29:57,000
Had been part of a recommendation when when Stantec did an evaluation of the watershed that essentially.

1894
02:29:57,000 --> 02:30:01,000
Carries and what's really an unnamed Creek.

1895
02:30:01,000 --> 02:30:09,000
I'll call it that we call it the spinnaker the spinnaker layer be Creek that comes through.

1896
02:30:10,000 --> 02:30:22,000
Spinnaker West and flows along underneath Larry B Street for a portion and then behind the houses that are on the north side of Larry B Street.

1897
02:30:22,000 --> 02:30:29,000
Underneath Spring Street through clean test and down through the street department garage and out to.

1898
02:30:30,000 --> 02:30:35,000
And so when we've had and and so we made.

1899
02:30:35,000 --> 02:30:46,000
Huge improvement to it by improving the stormwater ponds that are in spinnaker West and we did that with a grant from the National Fish and Wildlife Foundation.

1900
02:30:46,000 --> 02:30:51,000
Just like we're doing with Valley Creek and so.

1901
02:30:51,000 --> 02:30:56,000
That is something I have not given up on in terms of getting funded so.

1902
02:30:57,000 --> 02:31:06,000
We're we're our focus right now is on Valley Creek because of course that has even more significant issues and is a little.

1903
02:31:06,000 --> 02:31:19,000
It's it's a little less complicated than the I'll call the spinnaker layer be Creek because as Michael alluded to we own all the property.

1904
02:31:20,000 --> 02:31:24,000
That that Creek is in.

1905
02:31:24,000 --> 02:31:28,000
And so that's a little bit of a lighter lift even though it's a huge project.

1906
02:31:28,000 --> 02:31:36,000
The Spring Street and Garfield project is a little bit more complicated but I've not given up on.

1907
02:31:36,000 --> 02:31:42,000
A more holistic approach to that rather than just building large box culverts.

1908
02:31:42,000 --> 02:31:47,000
That essentially serve will serve to.

1909
02:31:47,000 --> 02:31:55,000
Reduce the threat of flooding to five or six homes that have exposed basements in that area.

1910
02:31:55,000 --> 02:31:59,000
So something again that's going.

1911
02:31:59,000 --> 02:32:04,000
I feel that working with stand tech we can probably.

1912
02:32:04,000 --> 02:32:13,000
Have a legitimate opportunity to obtain some grant monies for things for green infrastructure for Creek stream day lighting.

1913
02:32:13,000 --> 02:32:15,000
For.

1914
02:32:15,000 --> 02:32:20,000
These regenerative stormwater conveyance systems.

1915
02:32:20,000 --> 02:32:25,000
But we just haven't we haven't got to that point yet so I mean.

1916
02:32:25,000 --> 02:32:31,000
So the city will have the choice to either you know move ahead and with.

1917
02:32:31,000 --> 02:32:35,000
So the city will have the choice to do that.

1918
02:32:35,000 --> 02:32:39,000
So we're installing the box culverts that will convey the water out of these.

1919
02:32:39,000 --> 02:32:41,000
Out of that area.

1920
02:32:41,000 --> 02:32:44,000
More quickly or.

1921
02:32:44,000 --> 02:32:49,000
Take the time necessary in order to make it again part of a bigger project.

1922
02:32:49,000 --> 02:32:54,000
So these are all things that are ongoing.

1923
02:32:55,000 --> 02:33:00,000
We've down here beach revetment nourishment bluff stabilization currently that's.

1924
02:33:00,000 --> 02:33:03,000
Sitting out at the year.

1925
02:33:03,000 --> 02:33:05,000
Twenty thirty.

1926
02:33:05,000 --> 02:33:08,000
Nine sorry twenty nine.

1927
02:33:08,000 --> 02:33:14,000
So again is that something you know that's a big price tag is that something that.

1928
02:33:14,000 --> 02:33:17,000
Of course it's we.

1929
02:33:18,000 --> 02:33:23,000
We will know more when we complete our wastewater treatment plant.

1930
02:33:23,000 --> 02:33:28,000
Facilities evaluation this by the end of this year.

1931
02:33:28,000 --> 02:33:34,000
We will know more about what we need to stabilize in order to facilitate.

1932
02:33:34,000 --> 02:33:41,000
Further expansion of the plan but that bluff stabilization would allow the city to.

1933
02:33:42,000 --> 02:33:47,000
You know essentially create a greater connection between the park and the beach and.

1934
02:33:47,000 --> 02:33:52,000
And greatly reduce you know the risk of blood slot.

1935
02:33:52,000 --> 02:33:56,000
Bluff slides like we had earlier this year.

1936
02:33:56,000 --> 02:34:02,000
And then I'm not going to go through this but these are all the downtown unless you want me to.

1937
02:34:02,000 --> 02:34:07,000
All the downtown plan items are kind of hanging out in that.

1938
02:34:08,000 --> 02:34:12,000
Right now again they're at like twenty twenty eight but none of these.

1939
02:34:12,000 --> 02:34:17,000
Have been approved as standalone projects and then I have.

1940
02:34:17,000 --> 02:34:20,000
We have not gone deeper on the.

1941
02:34:20,000 --> 02:34:22,000
TIFF projects.

1942
02:34:22,000 --> 02:34:30,000
But beyond what you saw tonight and what we had previously presented to the board kind of giving an outline of that.

1943
02:34:30,000 --> 02:34:36,000
Of the more imminent projects that are included in the TIFF.

1944
02:34:37,000 --> 02:34:41,000
And that is the 10 year capital plan as.

1945
02:34:41,000 --> 02:34:44,000
As I said the rough the rough cut.

1946
02:34:44,000 --> 02:34:49,000
So I'd be happy to take any questions or.

1947
02:34:49,000 --> 02:34:53,000
Any comments about any of the projects in here again that.

1948
02:34:53,000 --> 02:34:55,000
Excite you that you want to see.

1949
02:34:55,000 --> 02:34:58,000
Celerated that you want to see slow walked.

1950
02:34:58,000 --> 02:35:01,000
I'm just excited about that you presented it to us.

1951
02:35:01,000 --> 02:35:05,000
So I want to thank you for that update during the CIP.

1952
02:35:05,000 --> 02:35:14,000
I realize this may be boring to many but I believe this has been an excellent information to consider for this committee.

1953
02:35:14,000 --> 02:35:21,000
And also for the community as a whole as to what we have down the pipeline what we're looking at why we're looking at it.

1954
02:35:21,000 --> 02:35:25,000
And the steps that it takes to get us to where we want to be.

1955
02:35:26,000 --> 02:35:30,000
Sometimes you know we sit back and we wonder what's going on and.

1956
02:35:30,000 --> 02:35:38,000
At least now we know there is a plan. We know there's other things in the work. So I appreciate that. Thank you.

1957
02:35:38,000 --> 02:35:45,000
I still like to see us get back to annual street projects because we're falling behind.

1958
02:35:45,000 --> 02:35:51,000
Every year that we don't do annual street projects but I know budgetarily that's a challenge.

1959
02:35:52,000 --> 02:35:56,000
I guess I would say yes and no the.

1960
02:35:56,000 --> 02:36:04,000
The projects were the they are every other they're programmed every other year but they're they're essentially twice as big.

1961
02:36:04,000 --> 02:36:11,000
So there's positives and negatives to that. So I mean obviously it takes takes longer.

1962
02:36:11,000 --> 02:36:19,000
It is a larger scale of inconvenience I think but.

1963
02:36:20,000 --> 02:36:27,000
But even at twice as big were we doing the mile and a half of road a year that we really need to keep up.

1964
02:36:27,000 --> 02:36:32,000
It varies but it's.

1965
02:36:32,000 --> 02:36:38,000
Off the top off the top my head I can't answer that question whether or not it's it's.

1966
02:36:38,000 --> 02:36:43,000
What the mileage comes out for each but it does vary.

1967
02:36:43,000 --> 02:36:46,000
It's getting the yeah it's it is close.

1968
02:36:47,000 --> 02:36:52,000
I mean this if we the plan that we have presented will.

1969
02:36:52,000 --> 02:36:55,000
Accomplish the mission of.

1970
02:36:55,000 --> 02:37:00,000
Replacing all the lead lateral lines and take care of our.

1971
02:37:00,000 --> 02:37:03,000
You know we have some areas where we.

1972
02:37:03,000 --> 02:37:05,000
On.

1973
02:37:05,000 --> 02:37:08,000
Mike in your district I think on.

1974
02:37:09,000 --> 02:37:13,000
We had three or four water main breaks this year alone so.

1975
02:37:13,000 --> 02:37:18,000
You know so I think there's some fatigue out there for water main breaks.

1976
02:37:18,000 --> 02:37:21,000
And so again but it does accomplish it.

1977
02:37:21,000 --> 02:37:27,000
It's just it's going to take 10 years and.

1978
02:37:27,000 --> 02:37:30,000
All right any other question.

1979
02:37:30,000 --> 02:37:33,000
I just reiterate what Mary Lou said thanks for presenting it.

1980
02:37:33,000 --> 02:37:36,000
Obviously for me the first time seeing it so.

1981
02:37:36,000 --> 02:37:39,000
Look forward to going into a little more detail.

1982
02:37:39,000 --> 02:37:43,000
Just as an example of something that I've heard people talking about is you know on.

1983
02:37:43,000 --> 02:37:45,000
In my word on port view.

1984
02:37:45,000 --> 02:37:48,000
People kind of whipped down that street pretty fast.

1985
02:37:48,000 --> 02:37:52,000
I see people go 30 or 40 miles an hour down there so.

1986
02:37:52,000 --> 02:37:59,000
There's just one example so like we do something to try to slow traffic down a little bit I don't know if it would be like a four way stop but.

1987
02:37:59,000 --> 02:38:02,000
I don't know if it would be like a four way stop.

1988
02:38:02,000 --> 02:38:05,000
I don't know if it would be like a four way stop.

1989
02:38:05,000 --> 02:38:08,000
Westport and port view.

1990
02:38:08,000 --> 02:38:13,000
For speed bumps or something but.

1991
02:38:13,000 --> 02:38:21,000
And I am excited about the grand dev round about wherever that's going to be.

1992
02:38:21,000 --> 02:38:28,000
I will give one reframe though on the stop signs or that traffic engineer stable stop signs that is stop signs are not.

1993
02:38:28,000 --> 02:38:34,000
The traffic is not as effective as you would hope the stick extra stop signs in.

1994
02:38:34,000 --> 02:38:39,000
Yeah I guess I'll have said this before and I'll.

1995
02:38:39,000 --> 02:38:41,000
Say it again.

1996
02:38:41,000 --> 02:38:44,000
Whenever I'm the most.

1997
02:38:44,000 --> 02:38:49,000
I think in my career as an engineer the most common complaint I get is.

1998
02:38:49,000 --> 02:38:54,000
Traffic is going too fast on our street and we'd like you to do something about it.

1999
02:38:54,000 --> 02:38:57,000
And so it's it's also it's.

2000
02:38:57,000 --> 02:38:59,000
It's.

2001
02:38:59,000 --> 02:39:03,000
Yeah it's frustrating because I want to do something about it but it's it's.

2002
02:39:03,000 --> 02:39:06,000
We can't solve it with.

2003
02:39:06,000 --> 02:39:09,000
Stop signs and speed bumps it.

2004
02:39:09,000 --> 02:39:11,000
It's making the motorist feet.

2005
02:39:11,000 --> 02:39:21,000
So it's making the motorist feel like the speedy is traveling is the appropriate speed for the way the road is constructed.

2006
02:39:21,000 --> 02:39:25,000
So a super wide road makes a person feel.

2007
02:39:25,000 --> 02:39:28,000
Super confident going super fast.

2008
02:39:28,000 --> 02:39:33,000
You know compare that to like an alley right nobody's going 40 miles an hour down an alley.

2009
02:39:33,000 --> 02:39:35,000
They sure shouldn't be right.

2010
02:39:35,000 --> 02:39:41,000
But so you know there's something in between an alley in a freeway right so that's why.

2011
02:39:41,000 --> 02:39:44,000
I've been persistent in.

2012
02:39:45,000 --> 02:39:50,000
Every road construction project we do taking a very close look at.

2013
02:39:50,000 --> 02:39:59,000
If the road is constructed appropriately in Portview when we did that when we reconstructed that we did what we put in all the.

2014
02:39:59,000 --> 02:40:03,000
Bumpouts to at least reduce the crosswalk.

2015
02:40:03,000 --> 02:40:12,000
The crosswalk length for school kids and there are some areas where you know we're trying to use traffic calming but.

2016
02:40:13,000 --> 02:40:16,000
I'm glad you said that because.

2017
02:40:16,000 --> 02:40:21,000
I think it's important to people and anything we can do to slow traffic down is a good.

2018
02:40:21,000 --> 02:40:25,000
Good thing other than stop signs in every corner but.

2019
02:40:25,000 --> 02:40:27,000
I get it.

2020
02:40:27,000 --> 02:40:28,000
Yeah.

2021
02:40:28,000 --> 02:40:31,000
I guess you mentioned doing more rows I know.

2022
02:40:31,000 --> 02:40:35,000
I have also received the comment that people like us to get the alley were.

2023
02:40:36,000 --> 02:40:41,000
So if that's something the board wants to sleep on also.

2024
02:40:41,000 --> 02:40:44,000
All right any other questions or comments.

2025
02:40:44,000 --> 02:40:50,000
All right then we'll move on to item 15 review staff monthly reports.

2026
02:40:50,000 --> 02:40:54,000
All right.

2027
02:40:54,000 --> 02:40:56,000
I have it here.

2028
02:40:56,000 --> 02:40:58,000
I'll just bring it.

2029
02:40:59,000 --> 02:41:02,000
Bring it up and I'll need to bring it a little bigger here.

2030
02:41:02,000 --> 02:41:05,000
I'll just touch on a few.

2031
02:41:05,000 --> 02:41:11,000
Just a few highlights again it's a long meeting but as I mentioned earlier.

2032
02:41:15,000 --> 02:41:23,000
So yeah highway 33 is scheduled to start next week I tell you when this project first.

2033
02:41:23,000 --> 02:41:27,000
Was initiated by the DOT I think it was.

2034
02:41:28,000 --> 02:41:42,000
Four years ago I couldn't believe we were talking about resurfacing highway 33 because we just reconstructed it and 20 completed it in 2013 but the DOT has a more aggressive resurfacing program and they've had in the past.

2035
02:41:42,000 --> 02:41:47,000
But excited for the improvement and it's it's here.

2036
02:41:47,000 --> 02:41:54,000
It's a three month project and they have sent out flyers to neighboring residents.

2037
02:41:54,000 --> 02:42:05,000
And if you've driven down Grand Avenue you've probably seen the big sign that says it's going to be under construction starting next Monday.

2038
02:42:05,000 --> 02:42:23,000
And then just kind of is an informational thing I put in here that the marine sanctuary people are going to be back in in the city they were here last year doing their survey of people who visit and finding out who comes to Port Washington to visit the marine

2039
02:42:23,000 --> 02:42:37,000
sanctuary and there's quite a few and that's good news for him and them and good news for the city too because it brings in tourism dollars and I think a certain energy to the city.

2040
02:42:37,000 --> 02:42:47,000
And then if you've driven down Jackson Street they're well on their way to getting their mural completed and again that's just a great community involvement project.

2041
02:42:48,000 --> 02:42:52,000
North Beach access has been open for a few weeks now.

2042
02:42:52,000 --> 02:42:56,000
The seating and straw matting is down.

2043
02:42:56,000 --> 02:43:02,000
And the beach is open for anyone who was ready to hit the beach supposed to be hot tomorrow.

2044
02:43:02,000 --> 02:43:05,000
Crack filling is already underway.

2045
02:43:05,000 --> 02:43:14,000
Our summer help is here I think in all our departments in fact we were told I think there's 79 seasonal employees hired for this summer.

2046
02:43:14,000 --> 02:43:17,000
So great to have that help.

2047
02:43:17,000 --> 02:43:19,000
We have a new employee.

2048
02:43:19,000 --> 02:43:20,000
We lost the employee.

2049
02:43:20,000 --> 02:43:34,000
We were sad to see Jesse leave us earlier this year but our summer, our summer employee has worked out really well and decided to make a career of it.

2050
02:43:34,000 --> 02:43:40,000
And so we have hired Taylor Zivolowski.

2051
02:43:40,000 --> 02:43:41,000
Thank you.

2052
02:43:41,000 --> 02:43:43,000
Do you know Taylor?

2053
02:43:43,000 --> 02:43:44,000
Okay.

2054
02:43:44,000 --> 02:43:45,000
All right.

2055
02:43:45,000 --> 02:43:50,000
And so we're excited to have, we're excited to have him with us.

2056
02:43:50,000 --> 02:43:55,000
And so there's also other informative things on our sewer and water page too.

2057
02:43:55,000 --> 02:44:00,000
So if there's any questions let me know.

2058
02:44:00,000 --> 02:44:05,000
Just seeing your website about the Spring Street Interceptor.

2059
02:44:05,000 --> 02:44:12,000
It didn't hit another retaining wall did it.

2060
02:44:12,000 --> 02:44:16,000
Is that a holdover from a previous month?

2061
02:44:16,000 --> 02:44:20,000
It seems like.

2062
02:44:20,000 --> 02:44:21,000
Yes.

2063
02:44:21,000 --> 02:44:24,000
There's a retaining wall attached to the wing wall.

2064
02:44:24,000 --> 02:44:29,000
The way I read the abandonment documents thought it was gone but.

2065
02:44:29,000 --> 02:44:30,000
Okay.

2066
02:44:30,000 --> 02:44:32,000
Here's to be there and we missed it with our boring soul.

2067
02:44:32,000 --> 02:44:34,000
We're looking at.

2068
02:44:34,000 --> 02:44:44,000
At directional drilling and poke and holes on our alignment and then left and right and basically drilling all the way.

2069
02:44:44,000 --> 02:44:48,000
Through non-set of vertical drilling the final limits.

2070
02:44:48,000 --> 02:44:53,000
Vertical exploration missed the wall that.

2071
02:44:53,000 --> 02:44:57,000
That the pipe directional drilling ran into.

2072
02:44:57,000 --> 02:45:03,000
And so we are going to use other methods in order to.

2073
02:45:03,000 --> 02:45:06,000
Make certain.

2074
02:45:06,000 --> 02:45:09,000
At the next alignment is not going to hit another.

2075
02:45:09,000 --> 02:45:12,000
Buried abutment or wall or.

2076
02:45:12,000 --> 02:45:15,000
Yeah, it's also where we did the ground penetrating radar.

2077
02:45:15,000 --> 02:45:17,000
So none of that.

2078
02:45:17,000 --> 02:45:19,000
Picked it up.

2079
02:45:19,000 --> 02:45:25,000
So how long is it delayed now.

2080
02:45:26,000 --> 02:45:31,000
I had a bunch of emails on that today.

2081
02:45:31,000 --> 02:45:35,000
From what I was tied up with some other stuff I haven't responded but.

2082
02:45:35,000 --> 02:45:38,000
I think we know what we want to do.

2083
02:45:38,000 --> 02:45:39,000
How we're going to do it.

2084
02:45:39,000 --> 02:45:43,000
Now we got to coordinate with the railroad to see when they're available.

2085
02:45:43,000 --> 02:45:47,000
Watch this work.

2086
02:45:47,000 --> 02:45:50,000
The joy of union Pacific.

2087
02:45:51,000 --> 02:45:52,000
All right.

2088
02:45:52,000 --> 02:45:55,000
Any other comments or questions.

2089
02:45:55,000 --> 02:45:56,000
No.

2090
02:45:56,000 --> 02:45:57,000
All right.

2091
02:45:57,000 --> 02:46:00,000
That then brings us to item 16 chairman's business.

2092
02:46:00,000 --> 02:46:02,000
I have none.

2093
02:46:02,000 --> 02:46:05,000
So item 17 members and liaisons business.

2094
02:46:05,000 --> 02:46:08,000
Anybody have any business for the board?

2095
02:46:08,000 --> 02:46:09,000
No.

2096
02:46:09,000 --> 02:46:10,000
All right.

2097
02:46:10,000 --> 02:46:13,000
That brings us to item 18 public comments and appearances.

2098
02:46:13,000 --> 02:46:16,000
Do we have any public comments or appearances?

2099
02:46:16,000 --> 02:46:17,000
Paul, you showed up late.

2100
02:46:17,000 --> 02:46:18,000
You got anything?

2101
02:46:18,000 --> 02:46:19,000
No.

2102
02:46:20,000 --> 02:46:21,000
All right.

2103
02:46:21,000 --> 02:46:23,000
That will bring us then to item 19.

2104
02:46:23,000 --> 02:46:30,000
Our next meeting will be July 14th, 2026, which is the week preceding fish days.

2105
02:46:30,000 --> 02:46:33,000
And including fish days, I guess.

2106
02:46:33,000 --> 02:46:35,000
So hope to see you all then.

2107
02:46:35,000 --> 02:46:37,000
And that'll bring us to adjournment.

2108
02:46:37,000 --> 02:46:39,000
Do we have a motion to adjourn?

2109
02:46:39,000 --> 02:46:40,000
Move to adjourn.

2110
02:46:40,000 --> 02:46:43,000
We have a motion by older woman Miller.

2111
02:46:43,000 --> 02:46:44,000
Is there a second?

2112
02:46:44,000 --> 02:46:45,000
Second.

2113
02:46:45,000 --> 02:46:48,000
We have a second and I missed two of us.

2114
02:46:48,000 --> 02:46:49,000
Okay.

2115
02:46:49,000 --> 02:46:50,000
Bye.

2116
02:46:50,000 --> 02:46:51,000
Committee member, Paul.

2117
02:46:51,000 --> 02:46:54,000
All those in favor say aye.

2118
02:46:54,000 --> 02:46:55,000
Opposed?

2119
02:46:55,000 --> 02:46:56,000
We are adjourned.
